UNDERSTANDING AN INSURER’S SUBROGATION RIGHTS

health-insuranceThere are situations where an owner sues its property insurer (or builders risk insurer) in addition to suing its contractor or design professional for defects / damage. Sometimes, the owner’s lawsuit against its insurer is filed simultaneously with the lawsuit against its contractor and sometimes it is filed before or after it settles its dispute with its contractor. The contractor, if it knows the owner is suing its insurer, wants to ensure that once it settles with an owner, that the owner’s insurer will not pursue a subrogation claim against it. (In a subrogation claim, an insurer that pays its insured can stand in the shoes of the insured and sue third parties deemed liable for the claim.)

 
If a contractor settles with an owner and obtains a well-written release (that would release the contractor for all claims [known and unknown], damages, etc. arising out of or relating to the project and subject matter of the lawsuit/claim, etc.) the insurer will be precluded from asserting a subrogation claim against the contractor. The reason being is that the insured owner already released the contractor. See, e.g., Landmark American Ins. Co. v. Santa Rosa Beach Development Corp., 107 So.3d 1135 (Fla. 1st DCA 2012) (condominium development’s agreement with developer and contractor that was interpreted as containing release barred development’s insurer from seeking subrogation claim).
However, if the insurer is already suing the contractor in a subrogation claim or has perfected its rights, the contractor cannot try to settle with the owner and obtain a release thinking that the insurer’s claim would then be barred. The insurer cannot be prejudiced like this, especially if it already perfected its subrogation rights. For instance, in Twin City Fire Ins. Co. v. Jones, 918 So.2d 403 (Fla. 5th DCA 2006), an insurer paid an insured’s claim and then sued the defendants in a subrogation claim. The insured also filed a separate lawsuit against the defendants. The insured settled with the defendants and released the defendants. The defendants used the release to argue that the insurer should be barred from its subrogation claim. The Fifth District held that “a settlement executed by the insured cannot act as a bar to an action for subrogation by the insurer against a third party tortfeasor if, prior to the settlement, the tortfeasor learns of the insurer’s perfected subrogation rights. Twin City Fire Ins. Co., 918 So.2d at 404 quoting Lincoln Nat’l Health & Cas. Ins. Co. v. Mitsubishi Motor Sales of Am., Inc., 666 So.2d 159, 163 (Fla. 5th DCA 1995).

 
Understanding an insurer’s subrogation rights is important in construction. Oftentimes, there are waiver of subrogation rights that are set forth in contracts. Sometimes, these provisions are either stricken or the contract does not contain a waiver of subrogation. It is important to consider subrogation as a contractor if you have knowledge that the party suing you is also suing an insurer and/or you are being sued by an insurer in a subrogation claim (or the insurer has taken steps to perfect subrogation rights) so that you know your rights and options as the dispute progresses to settlement.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

UNDERSTANDING COMMON LAW INDEMNITY

SHOWERDOOR4Common law indemnification is a “common” third party claim in multi-party litigation, particularly construction defect litigation. For instance, if a general contractor is sued by an owner for defects, the contractor may third party in the applicable subcontractors and assert a common law indemnification theory against the subcontractors to flow through liability. However, common law indemnity does not have to be asserted as a third party claim, but can be asserted as an affirmative claim after a judgment is entered against a party.

 

For example, in Diplomat Resorts Limited Partnership v. Tecnoglass, LLC, 38 Fla. L. Weekly D1126a (Fla. 4th DCA 2013), a hotel owner hired a contractor to furnish and install glass shower doors in hotel rooms. The subcontractor, naturally, purchased the glass doors from a fabricator / manufacturer and then installed the doors at the hotel. Unfortunately, many of the glass shower doors spontaneously fractured. The hotel owner obtained a judgment against the contractor in arbitration for the damages it incurred in replacing the doors. However, because the contractor was likely not collectible, the hotel owner took an assignment of the contractor’s claims against the fabricator / manufacturer because the thought was the glass fractured due to a defect in the fabrication process.

 

The hotel owner, standing in the shoes of its contractor through the assignment, sued the fabricator / manufacturer and asserted a common law indemnification claim which was dismissed with prejudice by the trial court. On appeal, the Fourth District reversed finding that the hotel owner (standing in the shoes as the contractor) properly asserted the following elements of common law indemnification: 1) that the contractor is wholly without fault, 2) the fabricator / manufacturer is at fault, and 3) the fabricator / manufacturer is liable to the contractor because the contractor was vicariously, constructively, derivatively, or technically liable to the hotel owner for the wrongful acts of the fabricator / manufacturer.

 

One of the challenges with common law indemnification is that there are court decisions that require the party seeking indemnification to be in a “special relationship” with the party it is seeking indemnification from. The Fourth District, however, maintained that a party does not need to specifically plead the existence of a special relationship because this “merely describes a relationship which makes a faultless party ‘only vicariously, constructively, derivatively, or technically liable for the wrongful acts” of the party at fault.”  Diplomat Resorts Limited Partnership.

 

Although the Fourth District’s decision in Diplomat Resorts appears to make a common law indemnification claim easier to prevail on a motion to dismiss, it is still a challenging claim to prove because it requires the party seeking indemnity to be wholly without fault. In other words, if that party is slightly at fault, there is no common law indemnity. Putting this in context, if the contractor is slightly at fault regarding installing the shower doors, it will not prevail on its common law indemnification claim.

 

In fact, the fabricator / installer in Diplomat Resorts argued that the contractor failed to properly install the glass doors for this very reason; however, there was no finding by the arbitrator that the contractor improperly installed the glass doors. Had there been a specific finding, there likely would be no common law indemnification claim because “a former adjudication against an indemnitee [e.g., contractor], finding the indemnitee’s acts to be wrongful, is binding against the indemnitee and precludes indemnification.” Diplomat Resorts Limited Partnership.

 

Notably, there are times in arbitration or litigation where parties do not want specific findings of fact. One of those is in a situation where a defendant may look to another for a common law indemnification claim (such as against a manufacturer) because that party does not want a finding that it did anything wrong that would be contradictory to its position that its liability flows 100% from the party it is pursuing the common law indemnification claim against.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE DIFFERENCE BETWEEN LOST PROFIT AND LOSS OF USE DAMAGES

ProfitSharingLost profits are a type of damages that are sometimes thrown around in a litigation.  However, these damages are very difficult to establish and prove and they really require expert testimony.  If the theory to recover lost profits is speculative, or the way the lost profits is measured is speculative, they will not be recoverable.  (Typically, lost profits require a history of profits to measure against and/or establishing the profitability of another business using a substantially similar business model for comparative purposes).  Lost profit damages have a difficult burden of proof in order to avoid the argument that they are speculative in nature.

 

Loss of use is another type of damages that is often confused with lost profit damages. Loss of use damages is generally the rental value of property / fair market value due to the loss of use of that property. See B&B Tree Service, Inc. v. Tampa Crane & Body, Inc., 38 Fla. L. Weekly, D970a (Fla. 2d DCA 2013) citing MD. Cas. Co. v. Fla. Produce Distribs., Inc., 498 So.2d 1383 (Fla. 5th DCA 1986) and Meakin v. Dreier, 209 So.2d 252 (Fla. 2d DCA 1968).  Hypothetically speaking, this type of damage can come into play if an owner is trying to recoup the rental value of units / fair market value of units that are out of service due to a defect, i.e., water intrusion problem.

 

There is a better argument for an owner under Florida caselaw to testify as to loss of use damages than lost profits, although with both types of damages, a qualified expert is preferential. “An owner is qualified to testify to the value of his property based on a presumed familiarity with the characteristics of the property, knowledge or acquaintance with its uses and purposes, and experience dealing with it….An owner must be shown to have knowledge regarding the property and its value sufficient to qualify him.” B&B Tree Service quoting Craig v. Craig, 982 So.2d, 724, 729 (Fla. 1st DCA 1993) (internal quotations omitted). The key is the owner’s familiarity with the property and value to support his opinion testimony regarding loss of use damages.

 

Understanding the differences between lost profit damages and loss of use damages, as well as the ways to prove such damages, is important if these are damages a party is looking to recover. Not understanding the burdens of proof for these types of damages can be fatal to recovery or can lead a party to an unrealistic method of thinking during the course of a case and prevent the party from entertaining reasonable settlement offers.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SUBCONTRACTORS – READ AND UNDERSTAND THE IMPLICATIONS OF VENUE PROVISIONS

imagesCA7D565LSubcontracts often have venue provisions. However, these are often overlooked until a dispute arises. In many instances, the venue provision requires disputes to be brought in a court in a different venue than where the project is located. This could have the adverse effect of exposing a subcontractor, in particular, to disputes in multiple forums. The recent case of East Coast Metal Decks, Inc. v. Boran Craig Barber Engel Construction Co., Inc., 38 Fla. L. Weekly D1061a (Fla. 2d DCA 2013), explains the undesirable dynamics of venue provisions.
In East Coast Metal Decks, the general contractor hired the subcontractor on two public projects in Brevard County and Sarasota County. The general contractor, however, sued the subcontractor in Collier County due to a venue provision in the subcontract. The subcontractor brought the general contractor’s payment bond surety into the fold and then tried to transfer the venue to Brevard County because the subcontractor was being sued by material suppliers in that County. The trial court denied the transfer of venue because of the Collier County venue provision in the subcontract.

 

On appeal, the Second District affirmed the trial court’s ruling. The Second District found that (i) the parties were bound by the subcontract venue provision as there was not a compelling reason not to enforce the provision and (ii) because the payment bond was a public payment issued under Florida Statute s. 255.05, venue for a claim against the bond did not have to lie in Brevard County (where the project was located).

 
What does this case mean? Well, it means that the subcontractor needs to litigate with the suppliers in Brevard County and litigate with the general contractor in Collier County even though the disputes are related. Most likely, the suppliers sued the subcontractor because they were not paid and the general contractor did not pay the subcontractor due to the facts related to the general contractor’s claim against the subcontractor in Collier County.
Litigation in different counties over a related dispute can become expensive and undesirable. It is important to understand and consider the impact of venue provisions in contracts. Sometimes, it makes sense to argue the compelling reasons why the venue provision should not be enforced. However, courts do favor venue provisions because that is what parties negotiated and agreed to on the front-end. Other times, it makes sense to resolve the smaller lawsuits or lawsuits where the facts may not be in your favor (such as a subcontractor’s lawsuit with a supplier) to focus on the lawsuit with more upside (the subcontractor’s lawsuit with the general contractor or payment bond surety).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.