LIEN TRANSFER BONDS AND VENUE

theVenue(1)The Fourth District Court of Appeals in Attaway Electric, Inc. v. Kelsey Construction, Inc., 38 Fla. L. Weekly D1693a (Fla. 4th DCA 2013)  recently ruled that an action on a lien transfer bond (posted pursuant to Fla. Stat. s. 713.24 in the county where the project is located and lien recorded) needs to be initiated in the county where the bond is recorded. This means that even if there is a contract between the parties that requires a different venue outside of where the lien transfer bond is posted, that venue provision will not be enforced so that an action as to the lien transfer bond and an action under the contract can both be brought in the same county, i.e., where the lien transfer bond is posted.
In Attaway Electric, a subcontractor recorded liens for alleged nonpayment on Broward County projects with the same general contractor. The liens were transferred to lien transfer bonds by the general contractor. The subcontractor moved to foreclose the liens in Broward County and also sued the general contractor for breach of contract. The general contractor then moved to transfer venue to Orange County pursuant to a forum selection provision in the subcontract. The trial court granted the motion and transferred venue. The Fourth District, however, reversed finding that an action on a lien transfer bond must be brought in the county where it is recorded and “contract claims involving the same matters should be brought in the same place to avoid inconsistent rulings.Attaway Electric.

 
This recent decision is important because contractors that want to obtain the benefit of a forum selection provision in a subcontract probably need to have a payment bond and ensure in the subcontract that the forum selection provision covers claims as to the payment bond surety. If there is no payment bond, specifically for a private project, a subcontractor can lien the private project for monies owed. If the general contractor (or even perhaps the owner) then transfers the lien to a lien transfer bond, the subcontractor will be able to foreclose the lien as to the lien transfer bond in the county where the bond is recorded as well as pursue a breach of contract claim against the contractor in the same county, even if the subcontract contains a forum selection provision with a different venue.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.