RECOVERING DELAY RELATED DAMAGES FROM PUBLIC PAYMENT BOND

imagesOne of the advantages to subcontractors of public payment bonds issued under the Federal Miller Act (or even the Little Miller Act) is that there is an argument for the recovery of unexecuted change orders and, and as it particularly pertains to this article, impact-related costs (whether delay or inefficiency / lost productivity). This should not be overlooked although language in the governing subcontract, etc. could dilute these arguments. However, having the argument and opportunity to recover impact-related costs from a payment bond is a huge upside.

 

If a subcontractor is owed money for inefficiency or delay, etc., and there is a public payment bond in place, it should not automatically forego pursuing these claims against the bond. Unlike a lien where these types of costs / damages are not lienable and could render an otherwise valid lien fraudulent in Florida, these are damages that could be pursued against a public payment bond. The subcontractor should carefully craft its argument in furtherance of maximizing its best chance to recover these types of damages.

 

For example, in the opinion of Fisk Elec. Co. v. Travelers Cas. and Sur. Co., 2009 WL 196032 (S.D.Fla. 2009), a subcontractor sought inefficiency / lost productivity damages against a payment bond surety that appeared to be issued under Florida Statute s. 255.05 (also known as Florida’s Little Miller Act). The payment bond surety moved to dismiss the subcontractor’s complaint arguing that these types of damages are not recoverable under the bond. The Southern District, relying on federal cases interpreting the Federal Miller Act, found that a subcontractor can pursue such damages against the payment bond for its out-of-pocket unreimbursed expenses. See, e.g, U.S. f/u/b/o Pertun Const. Co. v. Harvesters Group, Inc., 918 F.2d 915, 918 (11th Cir. 1990) (finding that subcontractor could recover under Federal Miller Act bond for out-of-pocket expenses resulting from prime contractor’s delay).

 

To maximize the recoverability for impact-related costs, the costs should be supportable costs that the subcontractor actually incurred in the performance of its contract work. Organizing the back-up supporting these costs and theory of the impact is critical and the subcontractor looking to pursue these costs from a public payment bond should consult counsel to best position its arguments to support recovery.  On the other hand, the prime contractor should ensure that its subcontract has contractual provisions that will make it challenging and provide hurdles for the subcontractor to recover such damages.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

Posted in Delay Damages, Miller Act, payment bond and tagged , , , .