
Let me
Represent YOUR
Construction
Interests!
Analyzing legal issues that
impact parties across the
construction industry.
QUICK NOTE: TERMINATION FOR CONVENIENCE PROVISIONS GIVE A PARTY BROAD DISCRETION TO END A CONTRACTUAL RELATIONSHIP
QUICK NOTE: JUST BECAUSE A DISCRETIONARY CONTRACTUAL PROVISION DOESN’T GO YOUR WAY DOESN’T MEAN THE OTHER PARTY BREACHED THEIR IMPLIED COVENANT OF GOOD FAITH AND FAIR DEALING
In the previous posting, I discussed a contractor that lost its constructive acceleration claim. In the same case, the contractor argued that the government / owner breached the implied covenant of good faith and fair dealing that exists in every contract. The...
PROVING THE ELEMENTS OF A CONSTRUCTIVE ACCELERATION CLAIM REQUIRES PROOF THAT THERE WAS AN EXCUSABLE DELAY
In a recent dispute out of the Federal Circuit, Amatea/Grimberg JV v. Secretary of the Navy, 2025 WL 1752375 (Fed.Cir. 2025), a contractor submitted a constructive acceleration claim to the government after its request for time extension was denied. The contractor claimed it directed its subcontractors...
CONTRACTOR’S FAILURE TO PROVIDE CRITICAL PATH ANALYSIS CAN BE FATAL TO DELAY CLAIM
QUICK NOTE: PRINCIPAL ARGUING BAD FAITH AGAINST ITS OWN SURETY
The General Agreement of Indemnity a principal executes with its surety is the most--and certainly one of the most--powerful documents in construction. Consider this when executing a General Agreement of Indemnity in order to procure bonds.
In a recent case, the surety sought indemnity from its indemnitors...
About The Author
David Adelstein
Phone: (954) 361-4720
Email: Dadelstein@gmail.com
Pages
- About Me (David Adelstein)
- Bid Protests (Florida bid protests and Federal bid protests)
- Construction & Design Defects (and Florida Statutes Chapter 558)
- Construction Contracts
- Construction Liens
- Construction Safety, Workers Compensation Insurance, and Premise Liability Claims
- Delays, Acceleration, and Inefficiency (Lost Productivity)
- Insurance and Performance Bonds
- Payment Bonds Including Miller Act
Recent Posts
- QUICK NOTE: TERMINATION FOR CONVENIENCE PROVISIONS GIVE A PARTY BROAD DISCRETION TO END A CONTRACTUAL RELATIONSHIP
- QUICK NOTE: JUST BECAUSE A DISCRETIONARY CONTRACTUAL PROVISION DOESN’T GO YOUR WAY DOESN’T MEAN THE OTHER PARTY BREACHED THEIR IMPLIED COVENANT OF GOOD FAITH AND FAIR DEALING
- PROVING THE ELEMENTS OF A CONSTRUCTIVE ACCELERATION CLAIM REQUIRES PROOF THAT THERE WAS AN EXCUSABLE DELAY