BAILOUT FOR AN IMPROPERLY DRAFTED INDEMNIFICATION PROVISION

shutterstock_1060051475A recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact.  In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect). 

 

This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts.  Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06.  The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06.  (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.) 

 

The trial court held that because the indemnification clause was unenforceable under Florida Statute s. 725.06, the general contractor’s contractual indemnification claims fail.   But, the appellate court reversed providing a bailout to an unenforceable indemnification clause by simply severing out the unenforceable portion. Thus, while a subcontractor would be required to indemnify the general contractor for its own negligence, it would not be required to indemnify the general contractor for any partial negligence caused by the general contractor.  

 

This case leads to a couple of very important takeaways:

 

  • Make sure the indemnification clauses in your construction contracts comply with Florida Statute s. 725.06.  Have a construction attorney review the indemnification provision.  Do not, and I mean, do not, bank on this ruling that even if the indemnification provision is noncompliant, only the unenforceable part will be severed.  That is not good practice.

 

  • Include a severability provision in your contract. Always.  Even though this case did not discuss such a clause, the clause will bolster the argument that only the unenforceable aspect of the provision should be severed. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

Spread the love
Posted in Indemnification and tagged , , , , , , .