SIGNIFICANT ISSUES TEST APPLIES TO FRAUDULENT LIEN CLAIMS TO DETERMINE ATTORNEY’S FEES

imagesConstruction lienors need to appreciate on the frontend that recovering statutory attorney’s fees in a construction lien action is NOT automatic—far from it.  This is because the prevailing party for purposes of attorney’s fees in a construction lien action is determined by the significant issues test,”subjective test with no bright line standards based on who the trial court finds prevailed on the significant issues in the case.  If you want to talk about the subjective and convoluted nature of recovering attorney’s fees in a construction lien action under the significant issues test, a recent opinion by the Fourth District Court of Appeal is unfortunately another nail in the coffin.   

 

In Newman v. Guerra, 2017 WL 33702 (Fla. 4th DCA 2017), a contractor recorded a construction lien on a residential renovation project and filed a lien foreclosure lawsuit.  The homeowner countersued the contractor and asserted a fraudulent lien claim pursuant to Florida Statute s. 713.31.  An evidentiary hearing was held on whether the lien was a fraudulent lien and the trial court held that the lien was fraudulent (therefore unenforceable) because it included amounts that were not lienable under the law.  The remaining claims including both parties’ breach of contract claims proceeded to trial.  There was no attorney’s fees provision in the contract.  At the conclusion of the trial, the court found that the contractor was entitled a monetary judgment on its breach of contract claim. 

 

Question:  If the owner prevailed in the contractor’s construction lien claim and established that the lien was in fact fraudulent, is the owner entitled to his statutory attorney’s fees? 

 

While equity may suggest “yes” as the answer, the answer is not necessarily.  This is because of the significant issues test where the court is going to look at the outcome of the entire litigation to determine the party that prevailed on the significant issues in the entire case.   Since the contractor ultimately recovered a money judgment, the court held the owner was not the prevailing party for purposes of attorney’s fees under the significant issues test.  The contractor was not either, but this is beside the point since the owner established the lien was fraudulent and the contractor recovered a money judgment under a breach of contract claim that did not provide for attorney’s fees.  Nonetheless, the court maintained:

 

In sum, the trial court properly applied the “significant issues” test…in denying the homeowner’s claim for attorney’s fees under section 713.31 [fraudulent lien statute]. Even if a party prevails on a fraudulent lien claim, the party must be the prevailing party in the case as a whole to be entitled to attorney’s fees under section 713.31.

Newman, supra, at *4.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

Spread the love
Posted in attorneys fees, Lien and tagged , , , , , .