Posted on August 6, 2017August 6, 2017 by Edward Garber

OWNERS SHOULD SERVE REQUEST FOR SWORN STATEMENT OF ACCOUNT ON LIENOR

shutterstock_521792092When an owner receives a construction lien, an owner should serve the lienor with a Request for Sworn Statement of Account.    The Request for Sworn Statement is authorized by Florida Statute s. 713.16(2) and should be in the following form:

 

 

 

 

 

 

 

 

REQUEST FOR SWORN STATEMENT OF ACCOUNT 

WARNING: YOUR FAILURE TO FURNISH THE REQUESTED STATEMENT, SIGNED UNDER OATH, WITHIN 30 DAYS OR THE FURNISHING OF A FALSE STATEMENT WILL RESULT IN THE LOSS OF YOUR LIEN.

To: (Lienor’s name and address) 

The undersigned hereby demands a written statement under oath of his or her account showing the nature of the labor or services performed and to be performed, if any, the materials furnished, the materials to be furnished, if known, the amount paid on account to date, the amount due, and the amount to become due, if known, as of the date of the statement for the improvement of real property identified as (property description) .

(name of contractor) 

(name of the lienor’s customer, as set forth in the lienor’s Notice to Owner, if such notice has been served) 

(signature and address of owner) 
(date of request for sworn statement of account) 

 

From both an owner and lienor’s perspective, the bolded, capitalized language is key.  It states that if the lienor fails to respond under oath within 30 days, it will LOSE its lien.  That is a very punitive measure for a lienor’s failure to respond, meaning a lienor should absolutely respond, no questions asked.  Plus, a lienor’s response to a Request for Sworn Statement of Account is not a burdensome ordeal.  It is pretty simple, as exemplified in the response form below.

  

RESPONSE TO REQUEST FOR SWORN STATEMENT OF ACCOUNT 

To:      [Owner]

  1. [Lienor] performed _____________ at the Owner’s project.
  2. [Lienor] has been paid $________ to date. 
  3. The principal amount remaining due and owing [Lienor] is $___________.
  4. The amount to become due to [Lienor] is $______________.

                                                                                                ____________________________

[Lienor], Authorized Representative  

 STATE OF FLORIDA

COUNTY OF ______

  Sworn to and subscribed before me this ____ day of _______, by ________ of [Lienor], who is personally known to me and who did take an oath.

           

Again, a lienor’s failure to respond under oath will result in a LOSS of its lien and court’s have not been sympathetic to a lienor’s failure to properly or timely respond.   See, e.g., Palmer Elec.  Services, Inc. v. Filler, 482 So.2d 509 (Fla. 2d DCA 1986) (lienor lost lien by failing to respond to owner’s Request for Sworn Statement, even though request failed to recite statute or the bolded and capitalized warning); accord Stresscon v. Madiedo, 582 So.2d 158 (Fla. 1991) (affirming that lienor’s failure to respond under oath to Request for Sworn Statement of Account is fatal to its lien and cannot be cured after-the-fact); Gonas v. Home Elec. of Dade County, Inc., 537 So.2d 490 (Fla. 3d DCA 1988) (reversing summary judgment in favor of lienor because lienor failed to respond to Request for Sworn Statement of Account even though Request did not specify statute or include the bolded and capitalized warning) aff’d by Home Elec. of Dade County, Inv. V. Gonas, 547 So.2d 209 (Fla. 1989).

 

 

There are only two instances when a lienor does not have to respond to an Owner’s Request for Sworn Statement of Account: (1) the lienor has already filed its lien foreclosure lawsuit – the Request for Sworn Statement was served on the liener after the lienor filed suit or (2) the Owner has already served a Request for Sworn Statement of Account and the lienor’s response will be the same as a prior response.  Even with these two instances, a lienor should always make it a habit to respond because, as shown above, the response is uncomplicated. And, it is always advisable for a lienor to work with counsel to ensure its response is perfected and served since the failure to do so will result in the punitive loss of its lien.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

Posted in Lien and tagged construction lien, Florida Statute 713.16, lien, lienor, request for sworn statement of account, sworn statement of account.

Post navigation

← GOOD OLE DUTY TO DEFEND
THE RELEVANCE AND REASONABLENESS OF… →

David Adelstein

Phone: (954) 361-4720
Email: Dadelstein@gmail.com

Navigation

  • Home
  • About Me
  • Contact Me
  • Archive
Copyrights © Florida Construction Legal Updates. Website By Brand Partners.