STATUTE OF LIMITATIONS AND REPOSE FOR INDEMNIFICATION CLAIMS (STEMMING FROM CONSTRUCTION DEFECT)

images-1I have written articles regarding the statute of limitations and statute of repose relating to construction disputes governed under Florida Statute s. 95.11(3)(c):

 

Within Four Years.  An action founded on the design, planning, or construction of an improvement to real property, with the time running from the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest; except that, when the action involves a latent defect, the time runs from the time the defect is discovered or should have been discovered with the exercise of due diligence. In any event, the action must be commenced within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.

 

In the construction defect context, a claimant has four years to sue from the date they knew or reasonably should have known with the exercise of due diligence the defect (e.g, the latent defect).  This is the statute of limitations.  Nonetheless, a claimant must sue no matter what on a latent defect within ten years from the project’s completion (see statute above).  This is the statute of reposeA construction defect lawsuit cannot be initiated after the expiration of the statute of repose.

 

Let’s assume the following dates:

 

            Project completion (start of limitations)                                          2005

            First discovery of water intrusion                                                   2008

            General contractor completes repairs                                            2011

            General contractor sues subcontractor for indemnification            2013

 

In this scenario, the subcontractor may argue that the general contractor’s statute of limitations to sue the subcontractor for the defect and damage is barred by the statute of limitations since the first discovery of water intrusion was in 2008 and the general contractor waited to sue until 2013 (five years later).

 

But, wait…the general contractor is going to sue the subcontractor for indemnification (preferably, contractual indemnification based on the terms of the subcontract). In this scenario, the general contractor is suing after it completed repairs and established its liability to the owner for repairing the defects and damage. 

 

The statute of limitations for an action seeking indemnity does not being running until the litigation against the third-party plaintiff [general contractor] has ended or the liability [against the third-party plaintiff], if any, has been settled or discharged by payment.” Castle Constr. Co. v. Huttig Sash & Door Co., 425 So.2d 573, 575 (Fla. 2d DCA 1982) (finding general contractor’s indemnity claim against subcontractor did not accrue until the owner’s litigation against the general contractor ended or the general contractor’s liability determined).  Stated differently, the statute of limitations for the general contractor’s indemnification claim did not begin to start running until 2011 when its liability to the owner for the defects was discharged / settled.

 

Now, let’s assume the following dates:

 

     Project completion (start of limitations)                                          2005

            First discovery of water intrusion                                                   2008

            General contractor completes repairs                                            2013

            General contractor sues subcontractor for indemnification            2016

 

In this instance, the subcontractor may argue that the statute of repose expired because the general contractor waited until 2016 or eleven years after the statute of limitations started to accrue in 2005.  Guess what?  The subcontractor would be right.  See Dep’t of Transp. V. Echeverri, 736 So.2d 791 (Fla. 3d DCA 1999) (explaining that the statute of repose for construction defect claims still applies to claims for indemnity).  Stated differently, even though the general contractor sued the subcontractor for indemnification within three years of establishing its liability, it was still bound by the ten year statute of repose that started accruing in 2005, meaning such lawsuits were barred after 2015.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

Posted in Construction Defects, Indemnification, statute of limitations and tagged , , , , , , .