OWNER TAKING ASSIGNMENT OF GENERAL CONTRACTOR’S CLAIMS AGAINST A SUBCONTRACTOR(S)

Here’s a scenario that occurs in construction defect cases. An owner sues a general contractor and subs for construction defects.  The owner settles with a number of parties and takes an assignment of the general contractor’s claims against some or all of the subs and pursues the remaining parties for indemnity based on the assignment of the general contractor’s claims.

This was the scenario in Craftsman Plastering and Lath, Inc. v. Rath Mor, LLC, 2026 WL 2328032 (Fla. 4th DCA 2026). The owner settled with the general contractor and all subs except one. The owner took an assignment of the general contractor’s claim against the sub, and really the indemnity claim. The owner was then substituted as the real party in interest as it relates to the general contractor’s claims against the sub. The owner sought roughly $780,000 in attorney’s fees and costs in connection with the dispute claiming the sub was liable for such fees. The jury didn’t buy the argument and awarded the owner about $55,000. Basically, the jury seemingly prorated the fees by the number of parties, at least, that’s how the math worked out.  The owner didn’t like that and moved for an additur to increase the jury’s verdict which the trial court granted. This was reversed on appeal despite the fact that a trial court has broad discretion to grant a motion for additur.

An additur applies if the trial court finds the jury’s verdict was inadequate. See Craftsman citing Fla. Stat. s. 768.74(2) (citing to factors the trial court needs to consider).

But here’s the issue.  The trial court is NOT here to sit as another juror. The issue is whether “the undisputed evidence supports an award calculation different than that awarded by the jury.” Craftsman, supra.  At trial, the jury could have awarded the damages based on the evidence and jury instructions.

[Owner] defends the additur award by contending “the unrefuted evidence established that [the general contractor] spent almost $780,000 because of [the subcontractor’s] breach and this was the amount that would fairly compensate [Owner].” While [Owner] is correct that [the subcontractor] did not present evidence to support a specific money damages amount, [subcontractor’s] cross-examination of [the general contractor’s attorney] questioned the reliability of the damages amount sought. Specifically, [the subcontractor] noted that [the general contractor’s attorney’s] total damages calculation had included legal fees and costs incurred by suing the other thirteen subcontractors for not performing as agreed, which is not an “act or omission” for which [the subcontractor] agreed to be held liable. Additionally, [subcontractor’s] cross-examination of [the general contractor’s attorney] established that [he] did not bother to separate out the expenses attributable to suing the other subcontractors because “[i]t would probably take weeks to do. You’d have to sit there and go through every entry of billing.”

Craftsman, supra.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

PROVING AND DEFENDING AGAINST CONSTRUCTION DEFECT DAMAGES

Recent decisions in Florida (see here) have harshly come out against owners in construction defect cases that fail to properly measure their damages as of the date of the breach. The result has been a big “L” for owners in these cases based on an appeal even though the owners won at the trial level.

In a recent case, an owner presented construction defect damages from an expert and prevailed at trial. However, the damages were NOT measured as of the date of the breach, but years after. The appellate court reversed and remanded in favor of the contractor, meaning the owner lost the case.

If you are involved in a construction defect case, make sure the below is instilled in your thought process and analysis because you NEED to know how to prove construction defect damages and defend against construction defect damages:

“Damages for a breach of contract should be measured as of the date of the breach. Fluctuations in value after the breach do not affect the nonbreaching party’s recovery.” Damages are not supported by competent, substantial evidence when damages are assessed for a time other than that of the time of breach.
***
The homeowners “had a duty to prove each element of their claim, including the proper measure of damages.” “The generally prevailing rule is that a party will not be permitted a new trial on remand to remedy its own failure to present sufficient evidence to support its claim.” On remand, the homeowners are not entitled to a new trial on damages “because such a hearing ‘improperly allows appellee “a second bite at the apple” at proving damages.’ ”

Vuletic Group L.L.C. v. Malkin, 50 Fla.L.Weekly D1546c (Fla. 4th DCA 2025) (internal citations omitted).

Do not neglect the proper measure of damages in construction defect cases!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION DEFECT DISPUTES: KNOW YOUR MEASURE OF DAMAGES!!!!!

Remember this: know your measure of damages in a construction defect dispute. If you don’t, as shown below, the outcome can be unforgiving. The measure of damages is one of your most important elements of proof. You are filing suit for damages; thus, knowing what you can reasonably recovery is paramount.

In a recent dispute, Bandklayder Development, LLC v. Sabga, 50 Fla.L.Weekly D91e (Fla. 3d DCA 2025), a residential developer sold a single-family house while it was under construction in an as-is purchase agreement. Post-closing, the purchasers claimed defects and served a Florida Statutes Chapter 558 notice of construction defects letter. The purchaser subsequently initiated a construction defect lawsuit. During the nonjury trial, the purchaser’s expert testified that the purchasers suffered damages approximating $323,000 calculated as of January 19, 2022 (which was the date of the expert’s report). The expert further testified that the cost to finish the incomplete/defective work increased by 35% at the date of the May 2023 trial. However, the expert never testified as to the amount of damages as of the date of the contractual breach, which at the latest, would have been in April 2018 when the notice of construction defects letter was sent (or, at its earliest, June 2017 when closing occurred). At trial, the judge entered judgment for the purchasers in the amount of about $425,0000.  This was reversed on appeal with judgment to be entered in favor of the developer.  Why? Because the purchasers employed the wrong measure of damages and the only thing that prevented them from introducing the right measure of damages was within their control.  Harsh outcome for not applying the correct measure of damages!

To apply the correction measure of damages:

As a general rule in construction defect cases, “the measure of damages is the reasonable cost of making the performed work conform to the contract.”  “The purpose of compensation is to restore the injured party to the condition which he would have been in had the contract been performed.” 

It is well-established in Florida that damages for breach of a construction contract based on defective work are calculated as of the date of the breach. In 1982, the Florida Supreme Court, in Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037 (Fla. 1982), adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which provides:

(1) For a breach by one who has contracted to construct a specified product, the other party can get judgment for compensatory damages for all unavoidable harm that the builder had reason to foresee when the contract was made, less such part of the contract price as has not been paid and is not still payable, determined as follows:

(a) For defective or unfinished construction he can get judgment for either

(i) the reasonable cost of construction and completion in accordance with the contract, if this is possible and does not involve unreasonable economic waste; or

(ii) the difference between the value that the product contracted for would have had and the value of the performance that has been received by the plaintiff, if construction and completion in accordance with the contract would involve unreasonable economic waste.

In doing so, the Court observed: “Subsection 346(1)(a), therefore, is designed to restore the injured party to the condition he would have been in if the contract had been performed. This aim corresponds with general Florida law. We adopt subsection 346(1)(a) as the law in Florida regarding breaches of construction contracts.” 

Importantly, the Court then held:

Damages for a breach of contract should be measured as of the date of the breach.  Fluctuations in value after the breach do not affect the nonbreaching party’s recovery.

See Bandklayder Development, supra (internal citations omitted).

The purchasers’ problem here, is that they failed to prove their damages or offer evidence of their damages as of the date of the breach. Otherwise, damages is based on guesswork which is a big no-no! “‘[D]amages cannot be based upon speculation or guesswork, but must have some reasonable basis in fact.’” See Bandklayder, supra.  This guesswork is demonstrated by the purchaser’s expert that testified that the repair damages increased by about 35% from the date of his report to the date of the trial.

If you need help understanding your measure of damages, please consult a construction lawyer that works collaboratively with an expert.  Just remember: KNOW YOUR MEASURE OF DAMAGES!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

RES JUDICATA NOT APPLY TO BAR OVERLAPPING DAMAGES IN SEPARATE SUITS AGAINST CONTRACTOR AND SUBCONTRACTOR

Can the doctrine of res judicata bar an owner’s claim against the general contractor after the owner also sued and obtained a satisfied judgment against the subcontractor when there are identical, overlapping damages pursued in separate lawsuits.  A recent case says, not really.

In Pickell v. Lennar Homes, LLC, 48 Fla.L.Weekly D2037a (Fla. 6th DCA 2023), a homeowner sued a homebuilder and the homebuilder’s mechanical subcontractor in separate lawsuits.  The claims and damages asserted in the separate lawsuits were substantially identical. The homeowner obtained a judgment against the mechanical subcontractor which was satisfied (i.e., paid).  The homebuilder tried to use this as a get-out-jail-free card and claimed the homeowner was barred from suing it under the doctrine of res judicata based on overlapping claims and damages.

To successfully assert a defense of res judicata, a party must prove four “identities”: “(1) identity of the thing sued for; (2) identity of the cause of action; (3) identity of persons and parties to the action; and (4) identity of the quality of the persons for or against whom the claim is made.” Pickell, supra (citation omitted).

The issue in this case was the third identity – the identity of the parties which applies to the “same parties or their privies.” Pickell, supra (citation omitted).

Here, though, the mechanical subcontractor was NOT the privy of the homebuilder.  First, the homebuilder’s interest in the separate lawsuit was not bound by the final judgment of the mechanical subcontractor. This could occur if the homebuilder had indemnification responsibilities to the mechanical subcontractor. However, that was not the case.  While the mechanical subcontractor owed the homebuilder an indemnification obligation, that indemnification was not reciprocal meaning the homebuilder did not owe the indemnification obligation to the mechanical subcontractor.  (“But the obligation of indemnification must run from the party asserting the res judicata defense to the party who was sued in the separate action.  Here, the indemnification responsibility does not run from [the home builder] to the [mechanical contractor]; rather, the subcontract requires [the mechanical subcontractor] to indemnify the homebuilder.”)

Now, you may sit back and say this seems unfair if the claims and damages are substantially identical because it allows the homeowner to double dip in damages. However, it does not. It may be inefficient in that it would have made more sense for the lawsuits to be in the same lawsuit versus separate lawsuits. I would agree with this. But there is no double dipping because “satisfaction of ‘overlapping items of compensation’ in different judgments is a ‘post-judgment collections issue.’” Pickell, supra, at n.1.  In other words, “any recovery from [the mechanical subcontractor] would be set-off post-judgment from a potential future judgment against [the homebuilder].” Id

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

FLORIDA’S STATUTE OF LIMITATIONS / REPOSE FOR ACTIONS FOUNDED ON CONSTRUCTION IMPROVEMENT MODIFIED

On April 13, 2023, Florida’s all-important four-year statute of limitations–Florida Statute s. 95.11(3)(c)–relating to actions founded on construction of an improvement of real property was modified.  This is a key statute of limitations for ALL construction practitioners because it also includes the statute of repose for latent construction defects.

At the bottom of this posting is the current version fo s. 95.11(3)(c) with the underlined section being recent additions. (They hyperlink above will identify the deletions and additions.)  Important things to note:

Statute of Repose. The statute of repose has been reduced from 10 years to 7 years.  There is now an objective date for when the repose period commences: “within 7 years after the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest.”

Statute of Limitations. Similarly, the commencement of the statute of limitations now commences based on an objective date: “with the time running from the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest.

Multiple Buildings. If dealing with a project regarding multiple buildings with each building getting its own TCO, CO, or certificate of completion: “[I]f the improvement to real property consists of the design, planning, or construction of multiple buildings, each building must be considered its own improvement for purposes of determining the limitations period set forth in this paragraph.”

Application. The modifications to this statute of limitations apply “to any action commenced on or after the effective date of this act, regardless of when the cause of action accrued, except that any action that would not have been barred under s. 95.11(3)(c), Florida Statutes, before the amendments made by this act must be commenced on or before July 1, 2024. If the action is not commenced by July 1, 2024, and is barred by the amendments to s. 95.11(3)(c), Florida Statutes, made by this act, then the action is barred.”

Florida Statute 95.11(3)(c)

An action founded on the design, planning, or construction of an improvement to real property, with the time running from the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest; except that, when the action involves a latent defect, the time runs from the time the defect is discovered or should have been discovered with the exercise of due diligence. In any event, the action must be commenced within 7 years after the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest. However, counterclaims, cross-claims, and third-party claims that arise out of the conduct, transaction, or occurrence set out or attempted to be set out in a pleading may be commenced up to 1 year after the pleading to which such claims relate is served, even if such claims would otherwise be time barred. With respect to actions founded on the design, planning, or construction of an improvement to real property, if such construction is performed pursuant to a duly issued building permit and if the authority having jurisdiction has issued a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, then as to the construction which is within the scope of such building permit and certificate, the correction of defects to completed work or repair of completed work, whether performed under warranty or otherwise, does not extend the period of time within which an action must be commenced. If a newly constructed single-dwelling residential building is used as a model home, the time begins to run from the date that a deed is recorded first transferring title to another party. Notwithstanding any provision of this section to the contrary, if the improvement to real property consists of the design, planning, or construction of multiple buildings, each building must be considered its own improvement for purposes of determining the limitations period set forth in this paragraph.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

ECONOMIC WASTE DOCTRINE AND CONSTRUCTION DEFECTS / NONCONFORMING WORK

I recently did a presentation on the economic waste doctrine. It is an applicable doctrine dealing with construction defects and nonconforming work.  When it comes to construction defects and nonconforming work, EVERYTHING starts with your measure of damages.  How are you going to prove your damages?  Next, what evidence are you going to use to prove your damages?  Or, what are the defenses and how do you prove those defenses to a construction defect and nonconforming work claim including the economic waste doctrine?

If you are interested in learning more, the below presentation can shed detail.  However, don’t rely on the presentation in a vacuum.  Work with knowledgeable construction counsel (like me!) that can best position your case whether you are the one proving construction defects and nonconforming work or the one defending against such a claim. This way, if you are arguing economic waste, you are not just throwing it out there, but you are arguing it to actually mean it!

Loader Loading...
EAD Logo Taking too long?

Reload Reload document
| Open Open in new tab

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SUBSEQUENT PURCHASER CAN ASSERT CLAIMS FOR CONSTRUCTION DEFECTS

Can a subsequent purchaser pursue construction defect claims relating to the original construction of the property?  This was the threshold issue on a motion for summary judgment by a drywall manufacturer against a subsequent purchaser of a home in Karpel v. Knauf Gips KG, 2022 WL 4366946 (S.D. Fla. 2022).  This matter deals with the defective Chinese drywall that was installed in homes years ago.  The plaintiffs, which were subsequent purchasers of a home, sued the manufacturer of the defective drywall for various theories including negligence, negligence per se, strict liability, breach of express and/or implied warranty, private nuisance, unjust enrichment, and Florida’s Deceptive and Unfair Trade Practices Act.

The trial court noted, from the onset, that Florida does NOT have a subsequent purchaser rule that prohibits subsequent purchasers from asserting construction defect claims. With this consideration in mind, the trial court went through the claims the plaintiff, as a subsequent purchaser, asserted against the manufacturer to determine whether they were viable claims as a matter of law.

Negligence Claim

The trial court found that a subsequent purchaser could sue in negligence.  “Florida courts have long allowed subsequent purchasers to sue for negligence including in construction defect litigation.”  Karpel, supra, at *2.

Negligence Per Se and Strict Liability Claims

The trial court held that the plaintiff’s negligence per se and strict liability claims were duplicative. Both could not stand; for this reason, the court entered summary judgment as to the duplicative negligence per se claim. “Strict liability means negligence as a matter of law or negligence per se, the effect of which is to remove the burden from the user of proving specific acts of negligence.Karpel, supra, at *3 (quotation and citation omitted).

A subsequent purchaser could pursue a strict liability claim against a manufacturer.  “[A] manufacturer is strictly liable in tort when an article he places on the market, knowing that it is to be used without inspection for defects, proves to have a defect that causes injury to a human being.”  Karpel, supra, at *4 (quotation and citation omitted).

Even Section 402A of the Second Restatement of Torts, adopted by Florida’s Supreme Court, provides: “(1) One who sells any product in a defective condition unreasonably dangerous to the user or consumer or to his property is subject to liability for physical harm caused to the ultimate user or consumer, or to his property, if (a) the seller is engaged in the business of selling such product, and (b) it is expected to and does reach the user or consumer without substantial change in the condition in which it is sold.” Karpel, supra, at *4.

There are, however, limits on strict liability.

First, Florida disallows recovery in tort where plaintiffs only claim economic losses such as ‘damages for inadequate value, costs of repair, and replacement of the defective product, or consequent loss of profits—without any claim of personal injury or damage to other property.Karpel, supra, at *4 (citation omitted).

Second, Florida courts will disallow recovery for strict liability where the purchaser was subject to the common law doctrine of caveat emptor.”  Karpel, supra, at *4.

Thus, a subsequent purchaser’s strict liability claim could be pursued against a manufacturer provided such damages are not barred by the economic loss rule or the doctrine of caveat emptor (which applies to commercial property and property purchased at judicial auction sales).  Karpel, supra, at *4.

Breach of Implied Warranty

The trial court found that a subsequent purchaser could NOT sue a manufacturer for breach of implied warranty.  “[I]t is abundantly clear that in cases like these, where no contractual relationship between a subsequent purchaser and a manufacturer exists, the former’s recourse is a claim for strict liability.Karpel, supra, at *4.

Breach of Express Warranty

While a contractual relationship is typically required for breach of express warranty, this requirement is relaxed if the express warranty is intended to benefit subsequent purchasers.  “A manufacturer’s liability for breach of an express warranty derives from, and is measured by, the terms of that warranty.”  Karpel, supra, at *4 (quotations and citation omitted).  However, in this case, plaintiff’s breach of express warranty claim failed because the plaintiff never introduced any express warranty into the record.

Private Nuisance

The trial court held that the subsequent purchaser could NOT pursue a private nuisance claim against the manufacturer.   To sustain a private nuisance claim, the plaintiff must prove that the defendant’s maintenance of the nuisance was the proximate cause of the plaintiff’s damages.  Karpel, supra, at *8.  “The Plaintiffs’ ownership and current control over the drywall conclusively forecloses them from arguing that the Defendants actively “maintain” the ‘nuisance’ they complain of.”  Id.

Unjust Enrichment

The trial court held that the subsequent purchaser could NOT pursue an unjust enrichment claim against the manufacturer.  An unjust enrichment claim requires the plaintiff to prove that the plaintiff conferred a direct benefit on the defendant. “The Plaintiffs conferred no direct benefit on the Defendant.” Karpel, supra, at *8 (finding that plaintiffs, as subsequent purchasers, obtained their homes from previous owners so the plaintiffs conferred no direct financial benefit on the manufacturer).

Florida’s Deceptive and Unfair Trade Practices Act (FDUTPA)

The trial court found that a subsequent purchaser could theortetically pursue a FDUTPA claim. “Because the law is clear that a plaintiff need not have actually relied on the purported deceptive or unfair practice, the Court’s analysis need not go further….The Plaintiffs’ status as subsequent purchasers does not foreclose them from arguing that the Defendants’ practices violated FDUTPA.”  Karpel, supra, at *9.

However, the trial court noted that actual damages under FDUTPA may implicate the economic loss rule because actual damages under the statute “are the difference in the market value of the product or service in the condition in which it was delivered and its market value in the condition in which it should have been delivered according to the contract of the parties.”  Karpel, supra, at *9 (quotation and citation omitted). For this reason, the court ordered the plaintiff and defendant to submit supplemental briefing because if the economic loss rule is implicated, the FDUTPA claim will fail (due to the same limitations relating to the strict liability claim).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

COMMENCING OF THE STATUTE OF REPOSE FOR CONSTRUCTION DEFECTS

Florida has a ten-year statute of repose which applies predominantly to construction defect claims.   This can be found in Florida Statute s. 95.11(3)(c).  After ten years, any rights relative to a construction defect claim are time-barred.  However, the statute of repose date has been watered down and can be made to be more of a factual question due to the lack of objectivity as to the date that starts the ten-year repose clock.  The watering down of the statute of repose date benefits parties asserting construction defect claims provided they strategically appreciate the question of fact that can be created when up against the statute of repose. Stated differently, when up against the clock to assert a construction defect claim, strategically develop those facts, evidence, and arguments to maximize creating a question of fact as to when the statute of repose clock commenced. Conversely, as a defendant sued for construction defects, you want to maximize the facts, evidence, and arguments to fully establish the date the statute of repose clock had to commence for purposes of a statute of repose defense.

The recent opinion in Spring Isle Community Association, Inc. v. Herme Enterprises, Inc., 46 Fla. L. Weekly D2306b (Fla. 5th DCA 2021) demonstrates the factual question associated with the clock that starts the statute of repose date.  This factual question is created by Florida Statute s. 95.11(3)(c) that provides:

[T]he action [founded on the design, planning, or construction of an improvement to real property] must be commenced within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.

Spring Isle Community Association, supra.  (Note, see also current s. 95.11(3)(c) version in effect per hyperlink above.)

Thus, the statute of repose must commence AFTER: (1) after the date of actual possession by the owner, (2) the date of the issuance of the certificate of occupancy, (3) the date of abandonment of construction if not completed, or (4) the date of completion or termination of the contract, WHICHEVER DATE IS LATEST.  This foster the factual argument — which is the latest date and the facts supporting the latest date.

In this case, an association of a townhome community sued a homebuilder for construction defects.  The homebuilder third-partied in implicated subcontractors.  The homebuilder had a master contract with subcontractors and would issue applicable work orders to the subcontractors, which is a common practice with homebuilders. The stucco subcontractor moved for summary judgment based on the ten-year statute of repose arguing that the statute of repose period started when each townhome was issued a certificate of occupancy.  This was based on this date occurring AFTER the homebuilders’ records reflecting it made payment to the stucco subcontractor after the stucco work was complete on a townhome building but prior to the certificate of occupancy on each townhome building.  The trial court agreed and granted summary judgment as to the homebuilder’s third-party claim against the subcontractor.  The homebuilder appealed arguing that the statute of repose period started when their contract was completed which occurred after the certificate of occupancy date.  The appellate court found this was a question of fact and reversed summary judgment:

Additionally, the fact that [the homebuilder] may have made payments to [the stucco subcontractor] after completion of each unit does not establish that the payment constituted “final payment”…. Quite simply, the summary judgment evidence presented below was insufficient, as a matter of law, to determine the number of contracts that may have existed between [the homebuilder] and [stucco subcontractor] or to determine the completion date of the contract(s).

In the absence of competent evidence as to the date of occurrence for each of the four triggering events set forth in section 95.11(c)(3), or evidence that one or more statutory events is inapplicable, there is no way to determine which event occurred last.  Therefore, without sufficient evidence to determine the contract completion date, a genuine issue of material fact remains as to the commencement date of the repose period. Accordingly, we conclude that the trial court erred in granting [the stucco subcontractor’s] motion for partial final summary judgment.

Spiring Isle Community Association, supra (internal citations omitted).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

ECONOMIC LOSS RULE BARS CLAIMS AGAINST MANUFACTURER

The economic loss rule lives to bar a claim against a product manufacturer in a real estate transaction.  In a products liability action, there needs to be personal injury or property damage, other than to the property itself, in order to recover economic damages.  Otherwise, the economic loss rule will bar the recovery of such economic losses when the economic losses deal to the product itself.  This is important to keep in mind in any product liability action against a manufacturer.

In a recent case, 2711 Hollywood Beach Condominium Ass’n, Inc., v. TRG Holiday, Ltd., 45 Fla. L. Weekly D2179a (Fla. 3d DCA 2020), a condominium association purchased the condominium from the developer.  Subsequently, it noticed leaks with the fire suppression system in the condominium and sued multiple parties for damages for repairs due to the leaks and the replacement of the fire suppression system.  One of the parties sued in negligence and strict liability was a manufacturer of pipe fittings used in the fire suppression system.  The manufacturer moved for summary judgment based on the economic loss rule and relying on the 1993 Florida Supreme Court opinion in Casa Clara Condominium Ass’n v. Charley Toppino & Sons, Inc., 620 So.2d 1244 (Fla. 1993), holding “the economic loss rule limited a defendant’s tort liability for allegedly defective products to injuries caused to persons or damage caused to property other than the defective product itself.”  2711 Hollywood Beach Conominium Ass’n, supra.  The trial court agreed with the manufacturer and granted summary judgment.  On appeal, the Third District affirmed based on the economic loss rule:

The Association bargained for, purchased and received a building; [the manufactuer’s] fittings were only a component of the FSS [fire suppression system], incorporated into the building. Applying the rule set forth in Casa Clara, the Association purchased a completed building from the developer. [The manufactuer’s] fittings were “an integral part of the finished product and, thus, did not injure ‘other’ property.”  Injury to the building itself is not injury to “other” property because the product purchased by the Association was the buildingSee Casa Clara, 620 So. 2d at 1247. The economic loss rule therefore bars the Association’s recovery as to [the manufacturer] to the extent that it sought damages to replace the FSS [fire suppression system] and repair damage to the building.

2711 Hollywood Beach Conominium Ass’n, supra (internal citations omitted).

Notably, in Casa Clara, homeowners sued a concrete supplier for supplying defective concrete that caused the reinforcing steel in the concrete in their homes to rust.  The concrete supplier, in an action that went up to the Florida Supreme Court, prevailed based on the economic loss rule because there was no personal injury or damage to property other than the property itself, which was the completed building.  As the Florida Supreme Court held:

The homeowners also argue that [the supplier’s] concrete damaged “other” property because the individual components and items of building material, not the homes themselves, are the products they purchased. We disagree. The character of a loss determines the appropriate remedies, and, to determine the character of a loss, one must look to the product purchased by the plaintiff, not the product sold by the defendant.  Generally, house buyers have little or no interest in how or where the individual components of a house are obtained. They are content to let the builder produce the finished product, i.e., a house. These homeowners bought finished products—dwellings—not the individual components of those dwellings. They bargained for the finished products, not their various components. The concrete became an integral part of the finished product and, thus, did not injure “other” property.

We also disagree with the homeowners that the mere possibility that the exploding concrete will cause physical injury is sufficient reason to abrogate the economic loss rule. This argument goes completely against the principle that injury must occur before a negligence action exists. Because an injury has not occurred, its extent and the identity of injured persons is completely speculative. Thus, the degree of risk is indeterminate, with no guarantee that damages will be reasonably related to the risk of injury, and with no possibility for the producer of a product to structure its business behavior to cover that risk. Agreeing with the homeowners’ argument would make it difficult “to maintain a realistic limitation on damages.”

Casa Clara, supra, at 1247 (internal citations omitted)

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

ALLEGING PROPERTY DAMAGE IN CONSTRUCTION DEFECT LAWSUIT

When there is a construction defect lawsuit, there is an insurance coverage issue or consideration.  As I have said repeatedly in other articles, it is all about maximizing insurance coverage regardless of whether you are the plaintiff prosecuting the construction defect claim or the contractor(s) alleged to have committed the construction defect and property damage.  It is about triggering first, the insurer’s duty to defend, and second, the insurer’s duty to indemnify its insured for the property damage.   

The construction defect claim and lawsuit begins with how the claim and, then, lawsuit is couched knowing that the duty to defend is triggered by allegations in the lawsuit (complaint).  Thus, preparing the lawsuit (complaint) is vital to maximize the insurer’s duty to defend its insured.

In a recent opinion out of the Eleventh Circuit, Southern-Owners Ins. Co. v. MAC Contractors of Florida, LLC, 2020 WL 4345199 (11th Cir. 2020), a general contractor was sued for construction defects in the construction of a custom home.  A dispute arose pre-completion and the owner hired another contractor to complete the house and remediate construction defects.   The contractor’s CGL insurer originally provided a defense to the general contractor but then withdrew the defense and filed an action for declaratory relief asking for the declaration that it had no duty to defend the contractor because the underlying lawsuit did NOT allege property damage.  The trial court agreed with the contractor and granted summary judgment in its favor finding that the underlying complaint did not allege property damage beyond defective work.  But, on appeal, the Eleventh Circuit reversed.

Among other allegations, the owner’s underlying complaint against the contractor asserted that the contractor committed defects through chipped pavers in the driveways and walkways, inconsistent paint finish, marks on ceilings, damage to exterior doors, damage to the top stair tread, damage to hardwood floors, metal roof dents, scratches in granite, holes in ceilings, etc.  The owner sought its costs to repair and remediate the defects and damage from the contractor.  In looking at whether the  contractor’s CGL insurer had a duty to defend the contractor–the insured–the Eleventh Circuit (focusing on precedent out of the Eleventh Circuit) stated:

The operative amended complaint alleged that [the contractor] used subcontractors for work on the residence and that the residence was “replete with construction defects” and various damage. It did not further allege which subcontractors performed which work or how the damage occurred. Given these ambiguities, the complaint’s allegations are broad enough to allow [the contractor] to prove that one subcontractor negligently damaged nondefective work performed by another subcontractor.  If [the contractxor] could establish that at least some of the damage arose in this way, there would be “damage apart from the defective work itself” and therefore “property damage.”

***

For these reasons, we conclude that the underlying operative complaint can fairly be construed to allege “property damage” within the meaning of the CGL policy and Florida law. Accordingly, the district court erred in granting summary judgment to [the CLG insurer] on this basis.

MAC Contractors of Florida, 2020 WL at *4 (internal citations omitted).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.