UNDERSTAND THE DISPUTE RESOLUTION PROVISION YOU ARE AGREEING TO

When negotiating a contract, do not overlook the dispute resolution provision.  It is one of the more important provisions in your construction contract.   This provision will come into play and have ramifications if there is a dispute, which is certainly not uncommon on a construction project.

In dispute resolution provisions in subcontracts on federal projects, it is not unusual for that provision to include language that requires the subcontractor to STAY any dispute that concerns actions or inactions of the owner pending the resolution of any dispute between the owner and prime contractor relating to that action or inaction.   A provision to this effect should be included for the benefit of the prime contractor.  For instance, the provision may say the subcontractor agrees to stay any such claim against the prime contractor or prime contractor’s surety pending the outcome of any pass-through claim (or otherwise) submitted under the Contract Disputes Act.

For example, in U.S.A. f/u/b/o Ballard Marine Construction, LLC v. Nova Group, Inc., 2021 WL 3174799 (W.D. Wash. 2021), a prime contractor hired a subcontractor to perform a scope of work at a naval shipyard.  A differing site condition was encountered and the subcontractor was directed to continue performance and track its costs.  The subcontractor completed its work and submitted its approximate $13 Million claim from the prime contractor and its Miller Act payment bond surety.  The prime contractor and surety refused to pay until the resolution of the pass-through differing site conditions claim to the federal government.  The prime contractor had submitted a claim under the Contract Disputes Act to the federal government.  The subcontractor was not interested in waiting until the resolution of the Contract Disputes Act claim and filed suit against the prime contractor and Miller Act payment bond surety.  The prime contractor and surety moved to stay pending the outcome of the Contract Dispute Acts claim.  The trial court agreed with the prime contractor explaining, “It is not fruitful to require [the prime contractor] to fend off [the subcontractor’s] claim against it, and the [Miller Act] sureties [the prime contractor] agreed to indemnify, while simultaneously advancing [the subcontractor’s] claim for additional payment from the government through the ongoing CDA process.  [The subcontractor] agreed to such a dispute resolution procedure, and it does not claim that the increased costs were [the prime contractor’s] fault.”  Nova Group, supra, at *8.

A subcontractor with such a provision is still required to timely perfect and preserve its rights by timely filing a lawsuit against the Miller Act payment bond surety.  However, the subcontractor is now beholden to the Contract Dispute Act procedure which requires an initial decision by the contracting officer and, then, certain appeal rights.   This is not what the subcontractor wanted because it elongates any potential resolution.  However, this is what the subcontractor agreed to in the dispute resolution provision and benefits the prime contractor so that it does not have to fight the fight on two fronts, particularly when it is supporting the pass-through claim under the Contract Disputes Act claim process.

Remember, the dispute resolution provision in your contract is important and should not be overlooked; the provision has ramifications as shown in the above case!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

Spread the love
Posted in Contract Disputes Act, Miller Act and tagged , , , , , .