MILLER ACT PAYMENT BOND SURETY BOUND TO ARBITRATION AWARD

Here is an interesting case binding a Miller Act payment bond surety to an arbitration award against its prime contractor (bond principal) that it received sufficient notice of.  Notice is the operative word.  The surety could have participated in the arbitration, elected not to, and when its prime contractor (bond principal) lost the arbitration, it was NOT given another bite out of the apple to litigate facts already been decided.

In BRC Uluslararasi Taahut VE Ticaret A.S. v. Lexon Ins. Co., 2020 WL 6801933 (D. Maryland 2020), a prime contractor was hired by the federal government to make security upgrades and interior renovations to a United States embassy in the Czech Republic.  The prime contractor hired a subcontractor to perform all of the installed contract work.   The prime contractor terminated the subcontractor for default during the course of construction.

The subcontractor demanded arbitration in accordance with the subcontract claiming it was wrongfully terminated.  The subcontractor also filed a lawsuit asserting a Miller Act payment bond claim against the prime contractor’s surety (as well as a breach of contract action against the prime contractor). The subcontractor made clear it intended to pursue its claims in arbitration and hold the payment bond surety jointly and severally liable.  The parties agreed to stay the lawsuit since the facts were identical to those being arbitrated. The arbitration went forward and an award was entered in favor of the subcontractor and against the prime contractor for approximately $2.3 Million.

The subcontractor moved to lift the stay entered in the lawsuit to confirm the arbitration award against the prime contractor and Miller Act payment bond surety.  The prime contractor moved to vacate the award.

Beginning with the prime contractor’s motion to vacate the arbitration award, the Federal Arbitration Act gives limited grounds to support vacating an arbitration award.  The grounds the prime contractor raised will not be discussed. They were all denied because it is difficult to vacate an arbitrator’s final award and that is the important take-away message.  In support of this (and contained in a noteworthy, lengthy discussion by the Court), the Court stated: “The FAA [Federal Arbitration Act] creates a ‘strong presumption in favor of confirming arbitration awards,’ and ‘judicial review’ of such awards ‘must be an extremely narrow exercise.’BRC Uluslararasi Taahut, supra, at *4.

Of significance here, the subcontractor moved to enforce the arbitration award against the Miller Act payment bond surety, as it should.  Even though the surety was not a party to the arbitration, it was on notice of the arbitration, was notified the subcontractor would look to hold it jointly and severally liable, and the surety consented to the stay of the lawsuit pending the outcome of the arbitration. The Court noted, “[s]uch notice is sufficient to bind [the surety] to the arbitration award.” BRC Uluslararasi Taahut, supra, at *9 (citing cases showing that if the surety has notice of the proceedings against its principal, it can be bound by an arbitration award against the principal).  Further, the Court intuitively stated:

[The surety] clearly knew that the arbitration would occur.  Now dissatisfied with the outcome, [the surety] wishes not to be bound by the very proceeding [the surety] averred would avoid duplicative litigation.  The Court suspects that had [the prime contractor] prevailed in arbitration, [the surety] would be singing a different tune.  [The surety] will not be afforded a second bite at the litigation apple simply because it must now honor its obligations as the surety on the project.

Id.

Remember, if you are arbitrating rights, do not neglect to timely file your Miller Act payment bond lawsuit, or for that matter, any statutory payment bond lawsuit.  Give the surety NOTICE that you intend to hold it jointly and severally liable for any arbitration award entered against its prime contractor (bond principal).   Whether the surety elects to participate in the arbitration is within its discretion, but the key is to give the surety notice so that if you do prevail, you find yourself in same shoes as the subcontractor discussed in this case—binding the payment bond surety to the award entered against the prime contractor.  The prime contractor and its surety should also recognize this likely outcome.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: DO YOUR HOMEWORK WHEN IT COMES TO SELECTING YOUR ARBITRATOR

imagesMany construction contracts contain arbitration provisions.  Instead of litigating a dispute arising out of the contract, the parties will arbitrate the dispute per the arbitration provision.  There are advantages to arbitration and certain disputes bode well for arbitration.  The key is you want to make sure you select the RIGHT arbitrator or arbitrators.  Do your homework regarding the arbitrator list presented to you by, say, the American Arbitration Association.  Strike out those on the list that either do not have the requisite experience you need to decide the dispute or you believe they are not going to be impartial.  For instance, if you want an arbitrator that you think will specifically follow the letter of the law or the precise terms of a contract, select those on the list that meet this requirement; strike out others that do not.  The same philosophy would apply if you want an arbitrator to have specific factual knowledge or a factual understanding regarding a driving issue in the dispute.  Do not neglect the homework required to select –or try to select — the arbitrator you believe is the most qualified to understand the issues.

 

Now, why is this important?  It is important because you need to arbitrate a dispute with the understanding that the arbitrator’s award (decision) is FINAL.  There are no appellate rights.  None.  Vacating an arbitrator’s award is very challenging and the bases to vacate an award are limited and, most of the time, will NOT apply.

 

In a recent decision, a party tried to vacate an arbitration award.  One of the arguments was that the arbitration panel failed to follow  Florida law.   Well, guess what?  An arbitrator does not necessarily have to comply with Florida law.  Legal error by an arbitration panel is not a basis to vacate an arbitration award.  See Managed Care Ins. Consultants, Inc. v. United Healthcare Ins. Co., 42 Fla. L. Weekly D1599b (Fla. 4th DCA 2017).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

APPRECIATING THE RISKS OR FRUSTRATIONS OF ARBITRATION

arbArbitration, just like litigation, can come with its own risks and frustrations. Once an arbitration award is rendered, the prevailing party will usually file an action or move to compel a circuit court to confirm the arbitrator’s award so that the award is turned into a judgment. However, a party that does not like the arbitrator’s award, will try to move to modify or vacate the award in accordance with Florida’s Arbitration Code (Florida Statutes Chapter 682). Although there are specific statutory grounds in order to move to modify or vacate an arbitrator’s award (and the motion must be filed within a specific window of time – typically, 90 days after delivery of the award), non-prevailing parties will still make an effort to vacate or modify the award with the circuit court within their required time parameters. The bases to modify or vacate an award are different than appellate rights afforded to litigants in court because an arbitration award is not supposed to be vacated or modified if an arbitrator erred as to the law.

 

The case of Wells v. Castro, 38 Fla. L. Weekly D1509a (Fla. 3d DCA 2013), illustrates certain frustrations. Without going into the factual details of the dispute, an arbitrator entered an award in favor of a claimant (party demanding arbitration) against one respondent (party responding to the demand for arbitration) and against the claimant as to another respondent. All of the parties agreed that the arbitrator is vested with the authority to determine the prevailing party for purposes of being entitled to attorneys’ fees. The respondent that prevailed as to the claimant’s claim wanted to be the prevailing party in order to recover its attorneys’ fees. However, the arbitrator found that neither party was the prevailing party meaning neither the respondent nor claimant would be entitled to recover their attorneys’ fees (as to the claimant’s claim against the prevailing respondent). Notably, under the Florida Supreme Court’s decision in Trytek v. Gale Indus., Inc., 3 So.3d 1194 (Fla. 2009), a court is to look at which party prevailed on the significant issues in the case for purposes of determining the prevailing party and has discretion to determine that there is not a prevailing party; stated differently, there is now uncertainty as to whether a party will be deemed the prevailing party and be entitled to their attorneys’ fees under the “significant issues” standard.

 

The respondent that prevailed moved the circuit court to essentially modify the arbitration award arguing that the arbitrator erroneously concluded that neither party was the prevailing party and that the respondent should have been deemed the prevailing party because it prevailed as to the claimant’s claims. The trial court granted the motion and deemed the respondent the prevailing party for purposes of being entitled to attorneys’ fees.

 

On appeal through a petition for a writ of mandamus (in this case, an appeal for the appellate court to order the trial court to confirm the arbitrator’s award), the Third District reversed the trial court maintaining: (a) the parties agreed to have the arbitrator determine the issue of prevailing party for purposes of attorneys’ fees (and need to live by that determination) and (b) an arbitrator’s error of law is not a basis to vacate or modify an award.   Thus, if the arbitrator erred in determining the prevailing party under Florida caselaw, the parties need to live with that determination because they agreed to have the arbitrator determine this issue in their arbitration.

 

While there are certain benefits to arbitration, it can come with its own risks and frustrations.  Again, the reasons to modify or vacate the award are limited under Florida statute and not designed to correct an arbitrator’s potential errors in law.  Also, if the parties want the arbitrator to determine the prevailing party for purposes of attorneys’ fees (which makes sense since the arbitrator will be the most familiar with the factual nature of the dispute), the parties will more than likely have to live by that determination.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.