CONSTRUCTION LIENS AND THE “SUBSTANTIAL PERFORMANCE” DOCTRINE

In a recent case dealing with a construction lien, the driving issue was whether the air conditioning contractor “substantially performedbefore recording its construction lien against residential property. The importance here pertains to the substantial performance doctrine with respect to construction liens. The Third District Court of Appeal explained, with relevant citations, this doctrine as follows:

Under Florida law, a contractor is entitled to a mechanic’s lien if he complies with all provisions of Chapter 713, governing construction liens, and “has substantially performed the contract.” Grant v. Wester, 679 So. 2d 1301, 1307 (Fla. 1st DCA 1996) (quotation omitted); Langley v. Knowles, 958 So. 2d 1149, 1151 (Fla. 5th DCA 2007) (“The substantial performance doctrine recognizes that a contactor who complies with all of the provisions of the contactor’s lien statute is entitled to enforce a lien if he has substantially, but not completely, performed his contractual obligations.”). Substantial performance is performance “so nearly equivalent to what was bargained for that it would be unreasonable to deny the promisee the full contract price subject to the promisor’s right to recover whatever damages may have been occasioned him by the promisee’s failure to render full performance.” Ocean Ridge Dev. Corp. v. Quality Plastering, Inc., 247 So. 2d 72, 75 (Fla. 4th DCA 1971).

Contactor, LLC v. Allbrite Elec. Contractors, Inc., 780 So. 2d 963, 965 (Fla. 5th DCA 2001) (“[W]hether a subcontractor has substantially performed is a question of fact” and “should not be decided as a matter of law.”); Grant, 679 So. 2d at 1307 (“Substantial performance is a question of fact.”).

Torres v. A&P Air Conditioning Corp., 2026 WL 602664 (Fla.3d DCA 2024).

In this case, an owner hired an air conditioning contractor to install two air conditioning units. After the units were installed, the owner claimed one of the units was installed incorrectly and refused to pay the contract balance. The contractor claimed the units passed final inspection and recorded a construction lien. Thereafter, the contractor replaced the unit claimed to be incorrectly installed. The owner argued the lien was premature because the contractor did not “substantially perform” at the time it recorded its construction lien because one of the units was not installed correctly. While the trial court granted summary judgment in favor of the contractor, this was reversed on appeal with a reason being that substantial performance is a question of fact.

If you are recording or defending against a construction lien, please work with construction counsel.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

MAKE SURE YOU UNDERSTAND WHAT TO INCLUDE AND NOT INCLUDE IN A LIEN

If you need a construction lien prepared, please work with a construction counsel in doing so. Don’t use a service that’s going to charge you less but isn’t going to analyze the information or ask you questions based on the information you provide them to include in the lien. You are selling yourself short if you prepare a lien “down and dirty” or “half-assed”. Also, using construction counsel can allow you to assert, if you wanted, an advice of counsel defense in furtherance of defending against the invariable fraudulent lien claim.

In a recent case, a truss fabricator was hired by an owner to design, manufacture, and deliver trusses. The contract required the owner to pay 50% upon completion of the shop drawings. The shop drawings were prepared but the owner did not make payment. The truss fabricator then liened for the non-payment. The problem was that the property was not improved, i.e., there was no permanent benefit to the property:

Section 713.01(15), Florida Statutes….defines “improvement” as “any building, structure, construction, demolition, excavation, solid-waste removal, landscaping, or any part thereof existing, built, erected, placed, made, or done on land or other real property for its permanent benefit.” Here, no permanent benefit occurred upon the property in this case because the trusses were never delivered. Thus, appellee was not entitled to a lien on the property

JM Properties of W. Palm Beach, Inc. v. Fort Dallas Truss Company, LLC, 51 Fla.L.Weekly D325a (Fla. 4th DCA 2026).

Interestingly, there was no discussion as to whether the trusses were fabricated. Probably not because the shop drawings were not paid for. But if they were, then there would be an argument they are specially fabricated, in which case they should be lienable, and should be identified in the lien as specially fabricated. But since there was no discussion, this was apparently a non-issue in the case.

Bottom line: make sure you understand what to include and not include in a lien.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CAN FORECLOSURE SALE BE OVERTURNED BECAUSE SALE PRICE IS GROSSLY INADEQUATE?

Foreclosure actions are equity actions. See Verzura Construction, Inc. v. Hotel La Petitite Muse, LLC, 50 Fla.L.Weekly D2500a (Fla. 3d DCA 2025).  Can a sale price at a foreclosure auction sale be set aside because the foreclosed party believes the sale price is grossly inadequate? A recent case discusses this question and, as you will see, the argument that the sale price is grossly inadequate is not enough to overturn a sale.

In Verzura Construction, an owner hired a general contractor to renovate its hotel. A dispute arose and the contractor recorded a construction lien, filed a lien foreclosure lawsuit, and obtained a judgment of foreclosure. The contractor purchased the property in the foreclosure sale auction. The foreclosed hotel owner objected and move to set aside the sale arguing its attorneys failed to notify it of the sale and it was deprived of an opportunity to bid at the sale. However, the hotel’s attorney knew about the auction and attended the auction. Nevertheless, the trial court agreed to set aside the sale finding the sale price at the auction was grossly inadequate and the hotel owner was not notified of the sale by its counsel.  The appellate court reversed and, in doing so, discussed the burden of overturning a foreclosure sale under a grossly inadequate sale price argument:

A court ruling on post-sale objections to judicial foreclosure sales must assure that “no wrong has been accomplished in and by the manner in which [the sale] was conducted.”  But an inadequate sale price, even a grossly inadequate one, cannot alone justify setting aside an otherwise proper foreclosure saleThis is because the amount of the bid is “conclusively presumed to be sufficient consideration for the sale.” So an objecting party must raise an additional factor, like a “mistake, accident, surprise, fraud, misconduct, or irregularity” that impacted the sale and caused the price to be grossly inadequate.  Only then may the sale be set aside. 

Here, the court ruled that the sale price was grossly inadequate. But the only additional factor that the court cited aside from the price was the fact that [the foreclosed owner] was “deprived of an opportunity to bid,” …. And the only reason it concluded that [the foreclosed owner] was “deprived of an opportunity to bid” is because [its] attorneys failed to “inform” it. … [A]s a matter of law: (1) [it] had notice of the sale, and (2) [it] was not “deprived of an opportunity to bid.” The trial court abused its discretion in concluding otherwise.

***

Although such notice would end the inquiry, the record here reflects more than constructive notice – [the foreclosed owner’s counsel] attended the sale. And “there is a presumption that an attorney, as an officer of the court, is duly authorized to act for a client whom he professes to represent. In the absence of some pleading questioning the attorney’s acts . . . the presumption is conclusive.” 

Verzura Construction, Inc., supra (internal citations omitted).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

DON’T ASSERT AS A COUNTERCLAIM TO A LIEN FORECLOSURE LAWSUIT AN ORDER TO SHOW CAUSE CLAIM

If there is a construction lien on your property and you don’t like the lien, here are options to deal with the lien:

1. You negotiate a resolution a get a satisfaction of lien to record in the public records. Or, you can transfer the lien to the security of a lien transfer bond, but that just means the lienor would need to foreclose against the bond instead of the real property. In other words, the lien is collateralized by the lien transfer bond and not the real property so it does not resolve the lien.

2. You record a Notice of Contest of Lien to shorten the lienor’s statute of limitations to foreclose on the construction lien to 60 days. (See here.) If the lienor does not timely foreclose, then the lien is of no effect as a matter of law.  However, this does force the issue, meaning the lienor may file a lien foreclosure lawsuit sooner than later. (But, if they file the lawsuit sooner, then the lienor was always going to file the lawsuit later.)

3. You can file a lawsuit for an Order to Show Cause under Fla. Stat. s. 713.21(4) and force the lienor to file a lien foreclosure counterclaim within 20 days from service of the show cause summons. (See here.) The only time you’d really do this is if you want to initiate a lawsuit that you’d probably initiate no matter what. Otherwise, the Notice of Contest of Lien is more cost effective and more efficient.

In a recent case, Custom Homes By Triumph, LLC v. Sverdlow, 50 Fla.L.Weekly D1946a (Fla. 2nd DCA 2025), a lienor filed a lien foreclosure lawsuit.  The owner asserted a counterclaim that included the Order to Show Cause. The lienor didn’t timely respond to the counterclaim as the lienor was the one that initiated the lawsuit by filing the lien foreclosure lawsuit.  The trial court therefore dismissed the lien. Shocking outcome! The lienor appealed and prevailed for a couple of big reasons.

First, with the Order to Show Cause complaint, a lienor’s 20 days to respond is based on the receipt of a specifically worded show cause summons. Here, there was no summons because the owner asserted a counterclaim because, again, the lienor initiated the lawsuit.  Without the service of the summons, there is nothing that starts the 20-day clock.

Second, the lienor had already foreclosed. There was nothing for it to do. In response to an Order to Show Cause Complaint, a lienor needs to foreclose on the construction lien within the 20 days. But, here, the lienor already did so. (“The lienor’s obligation is to show cause “why his or her lien should not be enforced by action or vacated and canceled of record,” and the lien must be discharged only “[u]pon failure of the lienor to show cause why his or her lien should not be enforced or the lienor’s failure to commence such action before the return date of the summons.” [The lienor’s] complaint included a cause of action to foreclose its lien. And by seeking to foreclose its lien, [the lienor] was necessarily seeking to enforce it. So even if the clerk had issued a show-cause summons, [the lienor] had already completed one of the two alternative actions — “show cause . . . why [the] lien should not be enforced [by action]” or “commence such action” — that the summons would have directed it to accomplish, that is, commence an action to enforce its lien.” See Custom Homes By Triumph, supra (internal citations omitted))

Look, if you are considering the Order to Show Cause Complaint to deal with a construction lien, there is nothing to consider if the lien is already being foreclosed and you are not the plaintiff. You don’t get a “gotcha” after the lien is already foreclosed because the foreclosing lienor doesn’t respond to a needless claim. This was an appeal over an issue that should have never been an issue.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

OWNER CAN’T PURSUE STATUTORY SHOW CAUSE COMPLAINT TO CANCEL LIEN… FAIR OUTCOME?

If there is a payment dispute with a construction lienor — could be a contractor, a subcontractor, or supplier – it is possible, and more than likely, a construction lien may get recorded against real property. This scenario is not uncommon as the lien is the mechanism for the lienor to collateralize their claimed nonpayment.  Now, in reality, it does not take much money to record a lien. A lienor should utilize a lawyer to prepare their liens, but maybe they prepare liens in-house.  Regardless, the recording of the lien is a nominal cost and the clerk that dockets and records the lien does NOT analyze the merits of the lien.  That is not what the clerk is there to do; nor do you really want them the delve into the factual merits.

Well, what if a lien is facially invalid, meaning that the lien, on its face, includes information that demonstrates it is NOT properly perfected.  Or what if the lienor failed to properly preserve or perfect its lien rights before recording the lien. This happens!  Naturally, an owner of the real property wants the lien removed from the property. The owner does not want the encumbrance.

The owner could transfer the lien to a lien transfer bond under Florida’s Lien Law, but that is easier said than done. And this does not discharge the lien; it just removes the lien from the property to the security of the bond.

The owner could pay the lienor to record a satisfaction of lien but then the lienor wins by improperly leveraging its payment dispute with an invalid lien. (Frankly, sometimes this makes sense irrespective of the perceived “win.”)

The owner could record a notice of contest of lien under Florida’s Lien Law to shorten the lienor’s time period to foreclose on the lien from one year to sixty days.  This is generally the approach I suggest because if the lienor does foreclose within the sixty days there is the strong chance the lienor was always going to foreclose on the lien so why not bring the dispute to the head sooner than later.

Then, there is a statutory procedure under Florida’s Lien Law (Florida Statute s. 713.21(4)) oftentimes referred to as the “order to show cause” complaint where the lienor is given 20 days to show cause why its lien should not be enforced or cancelled of record (which is done by timely foreclosing the lien within 20 days after service of the summons):

By an order of the circuit court of the county where the property is located, as provided in this subsection. Upon filing a complaint by any interested party the clerk shall issue a summons to the lienor to show cause within 20 days after service of the summons why his or her lien should not be enforced by action or vacated and canceled of record. Upon failure of the lienor to show cause why his or her lien should not be enforced or the lienor’s failure to commence such action before the return date of the summons the court shall order cancellation of the lien.

An owner may do this because the owner has its own claims against the lienor. Or the owner may want to force the lienor to “make a move” or else lose the lien if the lienor does not timely foreclose. Strategically, it is an approach owners do pursue in certain contexts.

Unfortunately, a recent case adds uncertainty to the strategic value of this approach, or at least how the order to show cause complaint is pled.

In Calixte v. Coastal Building Contractors, LLC, 2024 WL 1896114 (Fla. 4th DCA 2024), an owner filed an order to show cause complaint against a lienor under Florida Statute s. 713.21.  The owner alleged the lienor was required to serve a notice to owner, and did not, and therefore its lien should be cancelled for being invalid. The lienor, which was required to file its lien foreclosure counterclaim within 20 days, did not. That should have been it. But it was not.  The lienor argued that s. 713.21 does not apply because the owner alleged that the lien was not properly perfected when it alleged the lienor failed to serve its notice to owner. The lienor made this argument because s. 713.21 is prefaced, “A lien properly perfected under this chapter may be discharged, or released in whole or in part, by and of the following methods…[(4) through the order to show cause complaint].”  In other words, because the owner alleged the lien was not properly perfected, the order to show cause complaint was not an option.  Sadly, the appellate court agreed: “As the complaint in this case specifically alleged [the lienor] had failed to perfect its lien by serving a “notice to owner” and therefore had no lien rights, [owners] could not avail themselves of this special statutory procedure authorized by section 713.21.” Calixte, supra, at *2.

This ruling, quite frankly, is unjust and somewhat ridiculous.  Here is why.  The lienor is still foreclosing the lien. Thus, the lienor does not agree its lien is not properly perfected.  The lienor believes it is properly perfected because it is still pursuing its lien foreclosure. Next, if you read s. 713.21, it talks about other procedures to discharge a lien including a satisfaction of lien, by a judgment, or by the lienor failing to timely foreclose the lien. These options are subject to the exact same prefatory language, “A lien properly perfected under this chapter may be discharged, or released…”  If the show cause complaint is not an option because of this prefatory language, what about these other standard options?  And lastly, this leaves the owner that disputes the merits of a lien with really only two options if it believes a lien is not properly perfected: (1) the notice of contest of lien (my preferred option), and (2) transferring a lien to a lien transfer bond, which does not discharge the lien but simply transfers the lien from the real property to the security of the bond. Meanwhile, the encumbrance created by the lien still exists simply because the owner implemented a statutory procedure on a lien the owner did not think was properly perfected, yet the lienor disagreed.   And here is what the case does not discuss.  What if the owner did not allege the lien was not properly perfected? But in reality it was not. In that context would the statutory procedure apply because if pursuing this option there is no value to allege the lien is not properly perfected in light of this ruling.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

FILING MOTION TO INCREASE LIEN TRANSFER BOND (BEFORE TRIAL COURT LOSES JURISDICTION OVER FINAL JUDGMENT)

If a construction lien is recorded against real property, the lien can be transferred to a lien transfer bond.  This transfers the security or collateral of the construction lien from the real property to the lien transfer bond. The lien transfer bond can be a bond posted by a surety company or it can be cash.  This is governed by Florida Statute s. 713.24.  The amount of the lien does not dictate the amount of the lien transfer bond.  Rather, the lien transfer bond needs to be in the amount of the lien, plus interest on that amount for three years, plus $1,000 or 25% of the amount of the lien (whichever is greater so factor in the 25%) to cover attorney’s fees. Fla. Stat. 713.24(1).

If you are looking to transfer a construction lien to a lien transfer bond, make sure to consult with counsel.

Keep in mind there is a statutory mechanism for a lienor to increase the lien transfer bond to cover attorney’s fees and costs and notice the word “must” in the statute below. Pursuant to Florida Statute s. 713.24(3):

Any party having an interest in such security or the property from which the lien was transferred may at any time, and any number of times, file a complaint in chancery in the circuit court of the county where such security is deposited, or file a motion in a pending action to enforce a lien, for an order to require additional security, reduction of security, change or substitution of sureties, payment of discharge thereof, or any other matter affecting said security. If the court finds that the amount of the deposit or bond in excess of the amount claimed in the claim of lien is insufficient to pay the lienor’s attorney’s fees and court costs incurred in the action to enforce the lien, the court must increase the amount of the cash deposit or lien transfer bond. Nothing in this section shall be construed to vest exclusive jurisdiction in the circuit courts over transfer bond claims for nonpayment of an amount within the monetary jurisdiction of the county courts.

In a recent case, Edmondson v. Tri-County Electrical Services, Inc., 2023 WL 2995420 (Fla. 4th DCA 2023), a lien was transferred to a cash bond by the real property owner.  The contractor-lienor moved to have the court increase the amount of the cash security to better cover attorney’s fees and costs accrued in the litigation. The court deferred ruling on the motion. Subsequently, the court had a bench trial and the contractor prevailed. The court entered final judgment in favor of the contractor and reserved ruling on attorney’s fees, interest, and court costs. The court thereafter entered an amended final judgment that included attorney’s fees, interest, and court costs.  The court then conducted a hearing to increase the cash bond and granted the contractor’s motion for the cash bond to be increased.  The issue was that the court no longer had jurisdiction to require the owner to increase the cash bond:

The action here was not ‘pending’ under section 713.24(3). The general rule is that an action remains pending in the trial court until after a final judgment and such time as an appeal is taken or time for an appeal expires. By the time the trial court had ruled on the motion to increase the bond, the time for an appeal had passed. Therefore, because the matter was no longer pending, the trial court lacked authority to consider the motion.

The trial court was without jurisdiction to grant Contractor’s motion to increase the bond.

Edmondson, supra, at *2 (internal citations omitted).

Here, the contractor should have requested the trial court rule on the deferred motion to increase the cash bond BEFORE the amended final judgment was entered. Or, at a minimum, the contractor should have timely filed a motion for rehearing as to the amended final judgment to address this deferred motion to increase the cash bond. Once the rehearing period expired, “the trial court no longer has jurisdiction over a final judgment.” Edmondson, supra, at *1 (“Contractor did not file a timely motion for rehearing, which would have been the time to raise the bond increase issue.”). Id.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

HUH? ACTION ON CONSTRUCTION LIEN “RELATES BACK” DESPITE NOTICE OF CONTEST OF LIEN

Not every case law you read makes sense. This sentiment goes to the uncertainty and grey area of certain legal issues.  It is, what you call, “the nature of the beast.”  You will read cases that make you say “HUH?!?” This is why you want to work with construction counsel to discuss procedures and pros / cons relative to construction liens.

An example of a case that makes you say “HUH” can be found in Woolems, Inc. v. Catalina Capstone Creations, Inc., 2023 WL 2777506 (Fla. 3d DCA 2023) dealing with a construction lien foreclosure dispute.

Here, a contractor filed a lawsuit against a subcontractor with a summons to show cause why the subcontractor’s construction lien should not be discharged.  This is a specific complaint filed under Florida Statute s. 713.21(4). This statute requires the lienor to essentially foreclose on its construction lien within 20 days after it was served with a “show cause” summons.  The subcontractor filed its answer and counterclaim but did NOT assert a claim to foreclose its construction lien.

Around the time of subcontractor’s answer and counterclaim, the contractor transferred the subcontractor’s lien to an all-cash lien transfer bond in accordance with Florida Statute s. 713.24. Once the lien transfer bond was recorded, the owner recorded a notice of contest of lien under Florida Statute s. 713.22. The notice of contest of lien shortens the limitations period to foreclose on a lien to 60 days.

The subcontractor did NOT timely foreclose its lien against the lien transfer bond and the general contractor moved to have its all-cash lien transfer bond returned, as it should do. The subcontractor filed its lien foreclosure against the lien transfer bond AFTER the 60-day window expired. The trial court, and affirmed by the appellate court, denied the general contractor’s request to have the lien transfer bond returned and allowed the subcontractor to assert its (dilatory) claim against the lien transfer bond claiming it related back in time to the subcontractor’s initial counterclaim.  HUH?!?

ISSUES GIVING RISE TO THE HUH

Here are the issues with this ruling:

  1. The subcontractor should have foreclosed its construction lien with the 20-day time period from receiving the summons to show cause. The case reflected the subcontractor asserted claims, but not the lien foreclosure claim subject to the summons to show cause. (The appeal did not discuss this point for reasons currently unknown.)
  2. Regardless of (1), the lien was transferred to a bond and a notice of contest of lien was recorded shortening the time period to foreclose the lien (as to the bond) to 60 days. There is case law referencing this procedure. Yet, the subcontractor still did not timely assert its claim against the lien transfer bond.
  3. The trial court applied the relation back doctrine which does nothing but completely water down the statutory purpose of a notice of contest of lien (not to mention the summons to show cause complaint).

RECOMMENDATIONS IN LIGHT OF RULING

In light of this ruling, here are my recommendations:

  1. If you are going to transfer a lien to a lien transfer bond, do it from the get-go. Then, record the notice of contest or pursue the summons to show cause complaint.
  2. If filing the summons to show cause complaint, wait for the 20-day time period to expire. If the time period expires, move to have the lien discharged before making the decision to transfer the lien to a lien transfer bond.
  3. If recording a notice of contest of lien, wait for the 60-day time period to expire before taking action.

The reality is that the procedure implemented in this case should have been fine but for the application of the relation back doctrine that makes you say HUH?!?

As mentioned, if dealing with a lien, please make sure to discuss strategic considerations with a construction counsel that can help navigate the process and advise on the pros and cons.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

UNPREDICTABLE OPINION REGARDING CONSTRUCTION LIEN (REINSTATEMENT??)

Here comes the discussion of an appeal I was intimately involved in dealing with a construction lien. See Suntech Plumbing and Mechanical Corp. v. Bella Isla, LLC, 2022 WL 14672765 (Fla. 3d DCA 2022).  Unfortunately, it was a losing result on my end but not a losing result to the issue at-hand.  You should ask what in the world does this mean.  I will tell you.

Here is the fact pattern.  A subcontractor files a construction lien foreclosure lawsuit against an owner for unpaid contract balance.  In the same lawsuit, the subcontractor sues the general contractor for breach of contract and unjust enrichment associated with an approximate three-year delay on a construction project.  The project was scheduled to be completed in 2019.  It was not.  The project was pushed into COVID and into 2022.  (The subcontractor did not sue the general contractor for amounts subject to the lien foreclosure claim.) The general contractor, assuming the defense of the owner, moved to stay the lawsuit pending the outcome of arbitration based on an arbitration provision in the subcontract.  The subcontractor did not dispute the arbitration provision, but argued that arbitration provision should not extend to the owner that was (a) not bound by the subcontract, (b) would not be a party to the arbitration, and (c) the amounts pled against the general contractor did not include the amounts subject of the lien foreclosure lawsuit.  At a minimum, the lawsuit should be stayed, not dismissed. Nevertheless, the trial court dismissed the entire lawsuit in an order that states that it is a final order with language that the lien may be “reinstated” after the outcome of the arbitration (that the owner is not a party to).

This is a big deal.  Construction liens are creatures of statute. And, a construction lien, no different than a mortgage, is only as good as its lien priority.  (The priority of a lien is critical!). Well, there is NO statutory procedure to reinstate a construction lien. None. There is also no authority that even contemplates such a procedure.  Thus, what happens to the priority of the lien and what happens to the corresponding lis pendens?  I have no clue other than the best recourse was to immediately appeal on two fronts: (1) appeal the trial court’s ruling as a final order based on language in the order stating it is a final order, and (2) in an abundance of caution, move for a petition of writ of certiorari due to the irreparable harm posed by the dismissal of a lien foreclosure lawsuit (regardless of the unheard-of reinstatement language).  This is the recourse pursued with the appeals consolidated.  The sentiment was that, at worst case, the appellate court would remand for the lawsuit to be stayed, not dismissed, so as not to impact the integrity (priority) of the lien and lis pendens.  The worst thought was that if the appeal was lost, there was not really a loss in this case because a loss would ultimately mean the lien and lis pendens are still in play where an argument cannot be made otherwise.  Although, honestly, a loss was not really considered here because there is no such thing as reinstating a lien.

Welcome to the unpredictability of the law.

First, the appellate court ruled that the trial court’s order, despite saying it was a final order, was not really a final order subject to an automatic appeal. “Because the trial court’s order of dismissal, however, is neither a final order nor an appealable nonfinal order we lack jurisdiction to consider [subcontractor’s] appeal of the dismissal order.”  See Suntech, supra, at *1.

Second, the appellate court ruled that the reinstatement language did not constitute irreparable harm to support the basis of certiorari relief.

[Subcontractor] alternatively seeks certiorari review of the trial court’s order of dismissal; however, the trial court’s order expressly retained jurisdiction to enforce any arbitration award and to reinstate [subcontractor’s] lien foreclosure claim against [owner] should arbitration not resolve the matter. [Subcontractor] has therefore failed to establish irreparable harm necessitating exercise of our certiorari jurisdiction.

Suntech, supra, at *1.

Ok.  So, the lien (and lis pendens) should remain in effect.  But what about their priority?  How do you reinstate a dismissed construction lien (and how does this effect lien priority)? Why is the lien even dismissed when the owner is not a party to the arbitration and not bound by any arbitration award?  How is a dismissed lien not irreparable harm when the lien serves as the collateral for nonpayment? What happens to the lis pendens? Does this mean that a general contractor can always move to dismiss a lien foreclosure claim from a subcontractor based on an arbitration provision that the owner is not bound to or an arbitration the owner is not a party to?

I don’t know the answers to any of these questions. Do you?  The continued lack of answers prompted a motion for rehearing seeking clarity because the ruling, frankly, benefits no one in the construction industry and extends to buyers, sellers, title companies, etc. You can’t ignore the lien and lis pendens based on the appellate court’s ruling. But how do you treat the lien from a priority standpoint (including the lis pendens) and how the lien gets reinstated is another thing.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

And, again, welcome to the law! In my view, this is a bad opinion for the construction industry as a whole.  It will be used in the wrong fashion to create a situation where the lien and lis pendens are in some unknown legal purgatory with an undefined outcome.

 

RECORDING A LIS PENDENS IS CRUCIAL

If you are in a construction dispute where you are pursuing a construction lien foreclosure action, recording a lis pendens is crucial. Did I say crucial? “[O]ne purpose of a notice of lis pendens is to alert all others that title to the property is involved in litigation and that ‘future purchasers or encumbrancers of that property’ are at risk of being bound by an adverse judgment.” Henry v. AIM Industries, LLC, 47 Fla.L.Weekly D653b (Fla. 2d DCA 2022).  There really is never a reason not to record a lis pendens when pursing a construction lien foreclosure. Please remember that – don’t forget to record the lis pendens!

There are times a lis pendens is recorded when the lis pendens is NOT based on a duly recorded instrument (e.g., construction lien or mortgage).  A lis pendens, however, is recorded because the dispute is tied to the property in which the lis pendens is being recorded. The lis pendens is recorded to best safeguard the plaintiff’s interest in the real property without fear that the real property will be sold impacting the purpose (and, of course, security) of the lawsuit.

“When an action is not founded on a duly recorded instrument or chapter 713 lien [construction lien], but alleges a nexus between the real property and the claims set forth, an evidentiary hearing is required on a motion to discharge lis pendens.”  Henry, supra.

“[T]he supreme court held that a lis pendens could not be dissolved if, ‘in the evidentiary hearing on request for discharge, the proponent [of the lis pendens] can establish a fair nexus between the apparent legal or equitable ownership of the property and the dispute embodied in the lawsuit.’ ” Discharging a notice of lis pendens without affording the proponent notice and an opportunity to be heard is a departure from the essential requirements of law. 

Henry, supra (internal citations omitted).

If you are involved in a dispute where there is  a fair nexus between the dispute and the real property, discuss with your counsel the pros/cons of recording a lis pendens.  Yes, the other side will and should move to discharge the lis pendens which should be subject to an evidentiary hearing.  However, if your lawsuit hinges on the security of the real property, this strategically will presumably be the needed avenue during the pursuit of the litigation.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

MOVING FOR CERTIORARI RELIEF IF THE TRIAL COURT IMPROPERLY DISMISSES / DISCHARGES YOUR LIEN

Your construction lien oftentimes is your leverage to secure payment because the lien collateralizes the amount you are owed against real property, a leasehold interest, or alternative security if the lien is transferred to alternate security.  Having a court dismiss or discharge your construction lien claim is no good.  This is true even if a court dismisses or discharges a construction lien transferred to alternative security such as a lien transfer bond.  Without the lien, there is nothing securing the nonpayment—not the real property, not the leasehold interest (as discussed below), and not the alternative security if the lien is transferred.   But there is valuable recourse–moving for a petition for a writ of certiorari in the appellate court.  “Losing the benefit of a recovery under a bond on a claim to enforce a lien constitutes the type of irreparable harm necessary to entitle a party to certiorari relief.”  James B. Pirtle Construction, Co., Inc. v. Warren Henry Automobiles, Inc., 46 Fla.L.Weekly D2290a (Fla. 3d DCA 2021).

In James B. Pirtle, a contractor recorded a construction lien against a leasehold interest.   The property was owned by the City of Miami (public property) and the City leased the property to an entity, which in turn, entered into a ground lease with the defendant to construct and operate a car dealership. A dispute arose between the contractor and the defendant-tenant regarding the construction of the car dealership and the contractor recorded a construction lien against the leasehold interest.  The defendant transferred the contractor’s lien to a lien transfer bond and the contractor moved to foreclose its lien against the bond.

The defendant-tenant came up with an argument that the contractor could not even foreclose its lien against the leasehold interest because the real property was public property which is NOT lienable.  The trial court bought this argument (not sure why because the reasoning does not seem all that logical!) and the contractor’s lien was discharged.  This was reversed on appeal without a lengthy discussion because the contractor’s lien was NOT against the real property owned by the public body, but against the defendant-tenant’s leasehold interest.

The appellate court explained:

At common law, a leasehold interest was considered a type of personal property, not realty. This concept is incorporated into section 713.11, Florida Statutes, titled, ‘Liens for improving land in which the contracting party has no interest.’ In this section, Florida’s construction lien law explicitly states that ‘[w]hen the person contracting for improving real property has no interest as owner in the land, no lien shall attach to the land….

***

States and municipalities lease public property to private tenants in order to operate their facilities (e.g., parks, airports), and contractors doing work for those tenants have lien rights not on the property, but on the leasehold interest of that tenant.

James B. Pirtle, Inc., supra (internal citations omitted).

The trial court’s ruling would have ultimately meant that contractors performing work for tenants of publicly owned real property have no lien rights or ability to collateralize their nonpayment.  This naturally does not make much sense as it would simply dilute the fundamental purpose of being able to lien the tenant’s leasehold interest.  Recognizing this huge loss, the tenant moved for certiorari relief and the appellate court reversed the discharge of the lien keeping this important right alive — the lien against the defendant-tenant’s leasehold interest!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.