BAILOUT FOR AN IMPROPERLY DRAFTED INDEMNIFICATION PROVISION

shutterstock_1060051475A recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact.  In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect). 

 

This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts.  Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06.  The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06.  (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.) 

 

The trial court held that because the indemnification clause was unenforceable under Florida Statute s. 725.06, the general contractor’s contractual indemnification claims fail.   But, the appellate court reversed providing a bailout to an unenforceable indemnification clause by simply severing out the unenforceable portion. Thus, while a subcontractor would be required to indemnify the general contractor for its own negligence, it would not be required to indemnify the general contractor for any partial negligence caused by the general contractor.  

 

This case leads to a couple of very important takeaways:

 

  • Make sure the indemnification clauses in your construction contracts comply with Florida Statute s. 725.06.  Have a construction attorney review the indemnification provision.  Do not, and I mean, do not, bank on this ruling that even if the indemnification provision is noncompliant, only the unenforceable part will be severed.  That is not good practice.

 

  • Include a severability provision in your contract. Always.  Even though this case did not discuss such a clause, the clause will bolster the argument that only the unenforceable aspect of the provision should be severed. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

INDEMNIFICATION PROVISIONS DO NOT CREATE RECIPROCAL ATTORNEY’S FEES PROVISIONS

shutterstock_121868692In a good, recent decision, the Eleventh Circuit in International Fidelity Insurance Co. v. Americabe-Moriarity, JV, 2018 WL 5306683 (11th Cir. 2018), held that Florida Statute s. 57.105(7) cannot be used to shift attorney’s fees in a contractual indemnification clause in a dispute between a general contractor and subcontractor’s performance bond surety, when the dispute does not involve an actual indemnification claim stemming from a third-party.

 

In this case, a prime contractor terminated a subcontractor and looked to the subcontractor’s performance bond surety to pay for the completion work.  The subcontractor had a standard AIA A312 performance bond that requires the prime contractor to comply with the terms of the bond, as well as the incorporated subcontract, in order to trigger the surety’s obligations under the bond.  The surety filed an action for declaratory relief against the prime contractor arguing that the prime contractor breached the terms of the performance bond through non-compliance thereby discharging the surety’s obligations.  The trial court agreed and the surety moved for attorney’s fees. 

 

The surety’s argument for attorney’s fees was threefold: (1) the indemnification provision requiring the subcontractor to indemnify the prime contractor required the subcontractor to indemnify the prime contractor for, among other things, attorney’s fees; (2) Florida Statute s. 57.105(7) provides that one-sided contractual attorney’s fees provisions must apply to both parties (and treated reciprocally), hence the inclusion of attorney’s fees in the indemnification provision means that the surety should be entitled to attorney’s fees; and (3) since the subcontract was incorporated into the performance bond, the surety should be entitled to attorney’s fees since it steps in the shoes of the subcontractor under principles of surety law.

 

Surprisingly, the trial court agreed with the surety.  However, thankfully, the Eleventh Circuit held that the indemnity provision in the subcontract was an indemnity clause that applies only to third-party claims and not suits between the general contractor and subcontractor.  Thus, the requirement of reciprocity for attorney’s fees provisions pursuant to Florida Statute s. 57.105 does not apply.  The Eleventh Circuit, however, did not enter a ruling as to whether even if s. 57.105 did apply such that attorney’s fees must be reciprocal in an indemnification clause, whether such rationale would allow the performance bond surety to recover attorney’s fees under principles of surety law. 

 

This decision is useful for a few reasons:

 

(1)  If a contractor, subcontractor, etc. is trying to create an argument for attorney’s fees based on an indemnification clause, this decision is helpful to put that issue to bed since the indemnification provision applies in the context of third-party claims, and is not related to independent claims between the contracting parties;

(2) A party looking to take advantage of a performance bond must, and I mean, must, make sure to properly comply with the terms of the bond.  Certain sureties will raise any argument to avoid obligations under a performance bond hoping that the beneficiary of the bond undertakes an act that allows the surety to discharge its obligations; and

(3) General (prime) contractors should explore subcontractor default insurance, which is a first-party insurance policy, as an alternative to performance bonds to avoid the issues associated with delays and other arguments a surety may raise in furtherance of avoiding obligations under the bond.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

UPDATE: DOES FLORIDA STATUTE s. 725.06 APPLY TO (HORIZONTAL) UTILITY CONTRACTS?

shutterstock_486800107In a prior article, I discussed a recent case that held that Florida Statute s. 725.06–the statute that governs indemnification provisions where the indemnitor is required to indemnify the indemnitee for personal injury or property damage caused wholly or partially by the indemnitee–does not apply to a horizontal, utility project as it only applies to the “construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance” per the wording of the statute.  (Please refer to the article regarding the facts of the case.)  From a logic standpoint, the case did not make a whole lot of sense as there would be restrictions on indemnification provisions for vertical projects but not a horizontal project such as underground utility improvements.  The reason this was an important issue in the case is because if s. 725.06 did govern the indemnification provision, it was not in compliance with the requirements of the statute.  If it was not in compliance, then it was not an enforceable indemnification provision.  The enforceability of an indemnification provision is a BIG deal!

 

Recently, the Fourth District substituted a new opinion, Block Builders, LLC v. Katryniok, 2018 WL 194095 (Fla. 4th DCA 2018), although I cannot say it is that helpful.  The appellate court still maintained that Florida Statute s. 725.06 did not apply to the contract at-issue since the contract involved underground utility improvements and the wording of s. 725.06 only applied to the “construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance.”  However, in this substituted opinion, the appellate court held that while s. 725.06 did not apply to the contract at-issue, this does not mean it can never apply to a utility contract.  Whatever that specifically means is unknown.     

 

Indemnification is a very importation provision in any construction contract. Very important.   It is a provision that should never be overlooked and it should be drafted with an eye towards the requirements of s. 725.06.  Parties need to understand the application of the indemnification provision, particularly in light of the liability insurance they maintain for purposes of the project.  Irrespective of this appellate court’s opinion, parties really should make sure their indemnification provision complies with s. 725.06.  Banking on the hopeful position that s. 725.06 does not govern their construction contract seems overly optimistic and quite unnecessary since a ruling that the provision is unenforceable can be damaging.  

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THERE ARE TIMES AN EQUITABLE SUBROGATION CLAIM IS THE MOST PRACTICAL RECOURSE FOR REIMBURSEMENT

shutterstock_627721505Equitable subrogation is a claim that can be pursued when a party (referred to as the subrogee) pays for damages to protect its interest–perhaps to mitigate its own exposure–seeks reimbursement from another party primarily liable for the damages.  There are times a party seeking reimbursement for purely economic losses is best able to pursue an equitable subrogation claim, as opposed to a common law indemnification or negligence claim.

 

Equitable subrogation is generally appropriate where: (1) the subrogee made the payment to protect [its] own interest, (2) the subrogee did not act as a volunteer, (3) the subrogee was not primarily liable for the debt, (4) the subrogee paid off the entire debt, and (5) subrogation would not work any injustice to the rights of a third party.

Tank Tech, Inc. v. Valley Tank Testing, L.L.C., 43 Fla.L.Weekly D868a (Fla. 2d DCA 2018) quoting Dade Cty. Sch. Bd. v. Radio Station WQBA, 731 So.2d 638, 646 (Fla. 1999).

 

Equitable subrogation is not dependent on a contract—it is simply an “equitable remedy for restitution to one [the subrogee] who in the performance of some duty has discharged a legal obligation which should have been met, either wholly or partially, by another.”  Tank Tech, Inc., supra, quoting W. Am. Ins. Co. v. Yellow Cab Co. of Orlando, Inc., 495 So.2d 204, 206 (Fla. 5th DCA 1986).

 

As shown in the recent decision below, there are times an equitable subrogation claim will generate more traction for purposes of a reimbursement claim than a negligence claim or common law indemnification claim, because an equitable subrogation claim does not require the party seeking reimbursement to show a duty is owed to it by the party it is seeking reimbursement from.

  

The recent decision of Tank Tech, Inc. involved damage to underground petroleum storage tanks at Circle K locations.  Company “A,” the subrogee, had been hired by Circle K to retrofit existing tanks by adding an interior wall inside of the tanks.  Company “B” was separately hired by Circle K to test the interstitial space between the new interior wall installed by Company “A” and the existing tank wall.  There was no contractual relationship between Company “A” and Company “B.”

 

After the tanks were retrofitted, Circle K notified Company “A” that the modified tanks were damaged and failing.  Although Company’s “A” investigation revealed the failure was the result of Company’s “B’s” testing methodology, Company “A” nevertheless repaired the damage to the tanks because its contract with Circle K required it to do so regardless of whether the damage was caused by a third party, such as Company “B.”

 

Company “A” then sued Company “B” for reimbursement of its repair costs under various claims, one of which was equitable subrogation.  Each party had expert opinions that pointed to the other for the cause of the tanks’ failure and damage.  The trial court granted a motion for summary judgment in favor of Company “B” finding that equitable subrogation did not apply.  This summary judgment was reversed on appeal as the Second District maintained that there were factual issues supporting the basis of the equitable subrogation claim:

 

Tank Tech’s [Company “A”] contract with Circle K obligated it to repair damages to the USTs [tanks]. But Tank Tech’s contractual obligation to Circle K did not convert Tank Tech into a “volunteer” to pay for damages caused by a third party and thus did not prevent the application of the equitable subrogation doctrine. Instead, Tank Tech was merely fulfilling its legal obligation to Circle K which was a necessary means of protecting itself from liability to Circle K. And Tank Tech, by virtue of Dr. Cignatta’s affidavit [expert opinion establishing Company “B” caused failure to tanks], established a genuine issue of material fact regarding whether Tank Tech or Valley Tank [Company “B”] was primarily liable for the damages. If Tank Tech is ultimately successful in proving that Valley Tank caused the damage to the USTs, then it would be entitled to seek any damages it incurred as a result of having to repair the damaged USTs.  To hold that Tank Tech is precluded from pursuing a claim for subrogation would leave Tank Tech without a remedy, a “most unfair and inequitable result.” 

Tank Tech, Inc., supra (internal citations omitted).

 

Negligence and Common Law Indemnification

 

Relatedly, Company “A” also sued Company “B” for negligence and common law indemnification for repairing tanks it claimed were caused by Company “B’s” testing methodology.  The trial court also granted summary judgment in favor of Company “B” on these claims.  Unlike the equitable subrogation claim, the Second District affirmed the summary judgment in favor of Company “B” on these claims. 

 

For Company “A” to sustain a negligence claim, it would have to establish that Company “B” owed it a duty.  Without a duty owed, there is no negligence claim.  Whether there is a duty is a question of law for the court.   In this case, when dealing with only economic losses, the relationship between the parties—Company “A” and Company “B”—needs to be examined to determine whether a special relationship exists to warrant creating a duty to protect the economic interests of another.  “[I]n order to proceed on a common law negligence claim based solely on economic loss, there must be some sort of link between the parties or some other extraordinary circumstance that justifies recognition of such a claim.”  Tank Tech, Inc., supra.   Here, the Second District agreed that Company “B” did not owe Company “A” a duty to support a negligence claim:

 

The reason why the negligence claim fails here is because there is neither a special relationship between Valley Tank [Company “B”] and Tank Tech [Company “A”] nor any extraordinary circumstance that would require imposition of a duty. Tank Tech’s injury did not flow from Valley Tank’s testing of the USTs [tanks]. Instead, Tank Tech seeks to recover the money it spent in repairing the USTs, an expense that was the result of a negotiated contract between Tank Tech and Circle K. There was no contract between Valley Tank and Tank Tech obligating Valley Tank to repair any USTs it damaged during testing or otherwise obligating Valley Tank to repay Tank Tech for the expenses incurred pursuant to Tank Tech’s contract with Circle K. And Valley Tank’s testing did not cause any personal injury or property damage to Tank Tech, the types of injuries for which the common law of negligence has historically permitted recovery.

***

This is simply a case of a party attempting to bring a tort claim to recover monies that it spent as a result of a contractual obligation to a third party. But negligence claims cannot proceed based on a party’s desire to relieve itself from a bad bargain.

Tank Tech, Inc., supra.

 

 

Likewise, regarding the common law indemnification claim, “actions for indemnity have been restricted to situations involving either a duty, an express contract, or the existence of active and passive negligence.”  Tank Tech, Inc., supra, quoting Hiller Grp., Inc. v. Redwing Carriers, Inc., 779 So.2d 602, 603 (Fla. 2d DCA 2001).  Since the Second District already agreed there was no special relationship between Company “A” and Company “B” and, thus, no duty owed, the common law indemnification claim failed for the same reasons as the negligence claim.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE INDEMNIFICATION LIMITATION IN SECTION 725.06 DOES NOT APPLY TO UTILITY / HORIZONTAL-TYPE PROJECTS

shutterstock_486800107One of the most important provisions in construction contracts is the indemnification provision.  Appreciating contractual indemnification obligations are critical and certainly should not be overlooked.  Ever!

 

Florida Statute s. 725.06 (written about here and here) contains a limitation on contractual indemnification provisions for personal injury or property damage in construction contracts.   There should always be an indemnification provision in a construction contract that addresses property damage or personal injury.  Always!

 

Section 725.06 pertains to agreements in connection with “any construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance, including moving and excavating associated therewith…” If the contract requires the indemnitor (party giving the indemnification) to indemnify the indemnitee (party receiving the indemnification) for the indemnitee’s own negligence, the indemnification provision is unenforceable unless it contains a “monetary limitation on the extent of the indemnification that bears a reasonable commercial relationship to the contract and is part of the project specifications or bid documents, if any.”   It is important to read the statute when preparing and dealing with a contractual indemnification provision.

 

A common defense from an indemnitor in a case dealing with contractual indemnification on a construction project is that the provision is unenforceable because it does not comport with s. 725.06.  

 

In a recent case, Blok Builders, LLC v. Katryniok, 43 Fla. L. Weekly D253b (Fla. 4th DCA 2018), the indemnitor argued the indemnification provision was not enforceable. Here, a utility company hired a contractor to improve its telecommunications services. Part of the work required the contractor to provide access to preexisting underground telecommunication lines located in neighborhood easements.  The contractor hired a subcontractor to perform the required excavation to access the preexisting underground lines.   This work resulted in a personal injury action where the injured person sued the contractor, subcontractor, and utility company.

 

The contractor’s subcontract with the subcontractor required the subcontractor to indemnify the contractor and its directors, officers, employees, and agents, from loss caused wholly or partially by the subcontractor.  Thus, the indemnification provision required the subcontractor to indemnify the contractor for losses that were caused partially by the contractor’s own negligence (otherwise, the indemnification provision would be limited to losses solely attributable to the subcontractor). 

 

The contractor and utility owner both claimed that the subcontractor was responsible for contractually indemnifying them for all losses including attorney’s fees.  The subcontractor argued that the indemnification provision should be deemed unenforceable because it did not contain a monetary limitation on the extent of the indemnification. 

 

Indemnification as to the Contractor

 

The appellate court affirmed the trial court that the indemnification provision as to the contractor was enforceable because the statute (s. 725.06) did not apply.  What?  That is right, the statute did not apply because the statute does not apply to utility contracts.  What?  That is right, the appellate court held that the statute applies to “any construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance” so if the excavation is not connected to a building, structure, appurtenance, or appliance, it does not apply.  Since the project dealt with underground utility lines, s. 725.06 did not apply so the contract did not need to contain a monetary limitation on the indemnification provision.

 

Of course, in my opinion, it is hard to truly reconcile the distinction between a vertical project of a building or structure and a horizontal project, such as the project at-issue.  In other words, why would a limitation on indemnification provisions apply to one type of project but not the other?  I do not know the answer to this other than to say the court reading s. 725.06 noticed that it mentions nothing about applying to horizontal type projects that do not involve a building or structure.

 

Indemnification of Utility Owner

 

The appellate court however reversed the trial court as to the application of the indemnification provision extending to the owner.  The indemnification provision mentioned nothing about the utility owner.   That is true.  The contractor argued that because the prime contract was incorporated into the subcontract, the subcontractor’s duty to indemnify the utility owner arose from the prime contract.  But, the prime contract required the contractor to indemnify the utility owner; it mentioned nothing about subcontractors being required to indemnify the owner.

 

Interestingly, if this contract were governed by s. 725.06, this perhaps would be an issue because s. 725.06 provides that contractors may not require the indemnitor to indemnify the indemnitee for damage to persons or property caused in whole or in part by any person other than the (a) indemnitor, (b) the indemnitor’s contractors, subcontractors, sub-subcontractors, materialmen, agents, or their employees, or (c) the indemnitee’s officers, directors, agents, or employees.   Thus, the indemnification provision would not permissibly authorize the subcontractor to indemnify the owner for the owner’s own negligence. 

 

Ultimately, what this means is that the owner can pursue contractual indemnity from the contractor based on the indemnification provision in the prime contract.  The contractor would owe this indemnification (since any negligence attributable to the subcontractor would be attributable to the contractor that hired the subcontractor). This would get resolved (or play out at trial) and the contractor, based on this loss, would sue the subcontractor for indemnification for the loss connected with the subcontractor’s negligence.

 

Please read this article for an update / follow-up on this issue and this case.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

GENERAL CONTRACTORS: CONSIDER IMPORTANCE OF “PRIMARY AND NONCONTRIBUTORY” LANGUAGE

UnknownIn prior articles, I reinforced the importance of general contractors including “primary and noncontributory” language in subcontracts and requiring the subcontractor to provide an analogous “primary and noncontributory” endorsement.   As a general contractor this is important, particularly since you are going to require the subcontractor to (i) indemnify you for claims relating to personal injury, property damage, or death, and (ii) identify you as an additional insured under its commercial general liability (CGL) policy for claims arising out of the subcontractor’s scope of work.   The “primary and noncontributory” language in your subcontracts allows you to maximize the value of your additional insured status.  

 

A recent opinion explains why I reinforced the importance of this language.

 

The case of Zurich American Insurance Co. v. Amerisure Ins. Co., 2017 WL 366232 (S.D. Fla. 2017) involved an underlying construction defect lawsuit where a condominium association sued a general contractor.    The general contractor hired subcontractors and required them to identify the general contractor as an additional insured.   This is all routine, right?  A few of the subcontractors had CGL policies issued from the same insurer (Amerisure).  They contained the same additional insured endorsement that included the following “other insurance” clause:

 

Any coverage provided in this endorsement is excess over any other valid and collectible insurance available to the additional insured whether primary, excess, contingent, or on any other basis unless the written contract, agreement, or certificate of insurance requires that this insurance be primary, in which case this insurance will be primary without contribution from such other insurance available to the additional insured.

 

When the general contractor was sued it, as it should, tendered the defense of the lawsuit to the responsible subcontractors as an additional insured under their policies demanding both a defense and indemnification from the association’s claims.  The insurer, however, refused to defend the general contractor.  The general contractor’s insurer (Zurich) defended the general contractor in the action. 

 

Thereafter, the general contractor’s CGL insurer sued the subcontractors’ CGL insurer.  (The general contractor had also assigned its additional insured rights under the policies to its CGL insurer.)  The general contractor’s CGL insurer was seeking reimbursement for the attorney’s fees and costs expended in the defense of the general contractor in the underlying construction defect lawsuit.  The subcontractors’ CGL insurer moved to dismiss the claims based on the clause above—that the subcontractors’ CGL insurance operated as excess insurance over the general contractor’s CGL insurance.  In other words, the subcontractors’ CGL insurance was not primary and noncontributory.  There was no allegation that the subcontract included language requiring the subcontractor’s CGL insurer to be primary and noncontributory. 

 

The first reason this is an important point is because “when an insurance policy defines its coverage as secondary or “excess” to a primary policy, the excess insurer has no duty to defend the insured—so long as the primary policy provides for a defense and its coverage has not been exhausted.”  Zurich American Ins. Co., supra, at *4.    If the subcontractors’ CGL policy is excess, then than their CGL insurer does not have a duty to defend if the primary policy is not exhausted.   This means they have no duty to defend the additional insured – not very helpful to a general contractor tendering the defense of the claim to responsible subcontractors. 

 

The second reason this is an important point is because of what is known between liability insurers as the anti-contribution rule:

 

Florida courts have consistently held that, once the duty to defend is activated, every subject insurer assumes it on a personal and indivisible basis. That means that when an insured tenders a claim to multiple insurance providers, the entity that actually engages in the defense and incurs the fees and costs associated with it cannot subsequently seek contribution or equitable subrogation from the fellow insurer who “lagg[ed] behind.”

Zurich American Ins., Co., supra, at *5 (internal citations omitted).

 

Since the general contractor’s CGL insurer bore the costs of the general contractor’s defense in the construction defect lawsuit, it cannot now divvy up the defense fees and costs to other insurers that may have had a similar obligation unless an exception to this rule applies (see below).

 

The third reason this is an important point is because there is an exception to this anti-contribution rule:

 

A “responsive” insurer who complied with its insured’s tender for defense can extract reimbursement from the “nonresponsive” insurer when the insured had separately contracted with another entity, itself an insured of the nonresponsive carrier, to indemnify the first insured. The logic of the exception is that the insured parties’ express decision to “shift[ ] exposure” from one to the other is imputed to the insurer relationship and overcomes the general anti-contribution principle.

Zurich American Ins., Co., supra, at *8 (internal citations omitted). 

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

FLOWING DOWN LIABILITY IN CONSTRUCTION DEFECT LAWSUITS

unknownIn construction defect lawsuits, third-party (or fourth-party) claims are routine to flow-down liability downstream.  Right, a general contractor sued by an owner will want to flow-down its liability to the subcontractors.  And, subcontractors will want to flow down their liability to sub-subcontractors and suppliers.   Common, and appropriate, flow-down claims are indemnification and contribution claims

 

In an appellate opinion with little factual discussion, Gozzo Development, Inc. v. Esker, 2016 WL 2908442 (Fla. 4th DCA 2016), the trial court entered summary judgment in favor of subcontractors dismissing the contractor’s indemnification and contribution claims.  The owner sued the contractor for a violation of building code (and corresponding defects and damage) and the contractor, in turn, sued subcontractors for indemnification and contribution.  The contractor was seeking indemnity for the statutory building code violations as well as contractual breaches that caused the construction defects and damage. 

 

On appeal, the Fourth District reversed the trial court’s summary judgment as to the indemnification claim, but affirmed the trial court’s dismissal of the contribution claim (as Florida abolished joint and several liability in negligence-based actions):

 

Further, as appellant [contractor] sought indemnity for violations of both statutory and non-statutory building standards, it was error to grant summary judgment on the indemnity claim under a provision that applies only to statutory liability. The statutory building code does not preclude liability for violating a contractual duty to adhere to local building standards.

However, we affirm the trial court’s summary judgment on the contribution claim, as appellant’s right to contribution had not arisen by the effective date of the revised statute barring joint and several liability.

Gozzo Development, 2016 WL at *1. 

  

It is important to understand the manner in which liability is flowed downstream (passed-through) in construction defect lawsuits.  It is generally this reason why construction defect lawsuits contain many parties, from the general contractor hired by the owner to the subcontractors, sub-subcontractors, and suppliers implicated by the defective work.   These articles on indemnification (common law and contractual) and contribution explain these very important flow-down claims in more detail. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONTRACTUAL INDEMNIFICATION LIMITATION ON FLORIDA PUBLIC PROJECTS

imagesConstruction contract indemnification provisions are governed under Florida Statute s. 725.06.  This is a very important statute to know if you are drafting indemnification provisions for any type of construction contract.  (There is also Florida Statute s. 725.08 that discusses indemnification provisions applicable to design professionals that is also worth knowing.) 

 

Contained within s. 725.06, is a limitation on indemnification provisions applicable to public construction projects:

 

(2) A construction contract for a public agency or in connection with a public agency’s project may require a party to that contract to indemnify and hold harmless the other party to the contract, their officers and employees, from liabilities, damages, losses and costs, including, but not limited to, reasonable attorney’s fees, to the extent caused by the negligence, recklessness, or intentional wrongful misconduct of the indemnifying party and persons employed or utilized by the indemnifying party in the performance of the construction contract.

(3) Except as specifically provided in subsection (2), a construction contract for a public agency or in connection with a public agency’s project may not require one party to indemnify, defend, or hold harmless the other party, its employees, officers, directors, or agents from any liability, damage, loss, claim, action, or proceeding, and any such contract provision is void as against public policy of this state.

 

The key to this contractual indemnification limitation on public projects is the bolded language “to the extent caused by….”  This language is comparative fault language meaning the indemnitor (party giving indemnification) is only responsible for indemnifying the indemnitee (party receiving the indemnification) “to the extent caused by the negligence, recklessness, or intentional wrongful misconduct” of the indemnitee.  The language “to the extent caused by” is more limiting than an intermediate or broad form of indemnification provision that expands the scope of the indemnitor’s obligation to indemnify the indemnitee (for example, for negligence acts caused by the indemnitee).   Stated differently, this limitation would certainly seem to preclude the indemnitor from indemnifying the indemnitee for the indemnitee’s negligence.

 

But, there is not yet a Florida case that truly discusses the application of this contractual indemnification limitation on public projects. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

INDEMNIFICATION PROVISIONS AND “IN WHOLE OR IN PART” LANGUAGE

imagesIf you negotiate or prepare construction contracts, then you should be familiar with Florida Statute s. 725.06.  This statute contains requirements for indemnification provisions in construction contracts and is a must-know and must-read for all construction participants responsible for negotiating and preparing construction contracts, especially those that contain indemnification provisions for bodily injury and property damage (and all such contracts do and should contain such indemnification language!).   For more on Florida Statute s. 725.06, please check out these articles:

 

  1. Make Sure Indemnification Provisions Clearly Reflect the Required Scope of the Indemnification;
  2. The Scope of a Release in a Settlement and Contractual Indemnification; and
  3. Buttoning-Up Contractual Indemnification Language.

 

Although not a construction case, the opinion in ATC Logistics Corporation v. Southeast Toyota Distributors, LLC, 41 Fla. L. Weekly D816b (Fla. 1st DCA 2016), demonstrates the importance of drafting clear indemnification language.    This case contained the following indemnification provision:

 

(a) ATC [Carrier] shall indemnify and hold harmless SET from and against any and all losses, liabilities, damages, costs, fines, expenses, deficiencies, taxes and reasonable fees and expenses of counsel and agents, including any costs incurred in enforcing this Agreement, that SET may sustain, suffer or incur arising from (i) Carrier’s failure or alleged failure to comply, in whole or in part, with any of its obligations hereunder; (ii) any loss of or damage to a Vehicle while loaded onto, transported on or unloaded from a Car Carrier; (iii) any damage to any property of SET caused by the maintenance or operation of any Car Carrier or the loading or unloading of any Car Carrier; (iv) any claims by any third person with respect to death, injury or property damage caused by the maintenance or operation of any Car Carrier or the loading, transportation or unloading of Vehicles on or from a Car Carrier and (v) any claims resulting from or arising out of injury or death of any employee, agent of contractor of Carrier including claims alleging that SET failed to provide a safe place to work.

 

The indemnity obligation was broken into five (i – v) sections. 

 

In this case, SET sued ATC (the named Carrier in the indemnification provision) to recover amounts it paid out in a settlement.  SET argued that ATC was responsible for indemnifying it for its (SET’s own) negligence based on the language in section (i) that required ATC to indemnify SET for “Carrier’s failure or alleged failure to comply, in whole or in part, with any of its obligations hereunder.”

 

The issue, however, was that SET was really seeking indemnification relating to section (iv) which did NOT contain any “in whole or in part” language.  In other words, section (iv) did not require ATC to indemnify SET for its actions whether caused “in whole or in part” by ATC’s negligence.  Had section (iv) contained this “in whole or in part” language, then ATC would have likely been required to fully indemnify SET for its actions even if the damages were partially caused by the negligence of SET.  While SET wanted the “in whole or in part” language included in section (i) to be read into the language in section (iv), this was NOT how this clause was written and the court is not there to rewrite parties’ contracts.  Accordingly, the First District held that ATC was not required to indemnify SET for SET’s negligence.

 

Importantly, if the indemnification provision pertained to a construction contract and required the indemnitee (e.g., subcontractor) to indemnify the indemnitor (e.g., contractor), it would need to include certain language for it to be enforceable under s. 725.06Such indemnification provisions that require the indemnitee to indemnify the indemnitor for “liability for damages to persons or property caused in whole or in part by any act, omission, or default of the indemnitee arising from the contract or its performance, shall be void and unenforceable unless the contract contains a monetary limitation on the extent of the indemnification that bears a reasonable commercial relationship to the contract and is part of the project specifications or bid documents, if any.” Fla. Stat. s. 725.06.   

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

STATUTE OF LIMITATIONS AND REPOSE FOR INDEMNIFICATION CLAIMS (STEMMING FROM CONSTRUCTION DEFECT)

images-1I have written articles regarding the statute of limitations and statute of repose relating to construction disputes governed under Florida Statute s. 95.11(3)(c):

 

Within Four Years.  An action founded on the design, planning, or construction of an improvement to real property, with the time running from the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest; except that, when the action involves a latent defect, the time runs from the time the defect is discovered or should have been discovered with the exercise of due diligence. In any event, the action must be commenced within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.

 

In the construction defect context, a claimant has four years to sue from the date they knew or reasonably should have known with the exercise of due diligence the defect (e.g, the latent defect).  This is the statute of limitations.  Nonetheless, a claimant must sue no matter what on a latent defect within ten years from the project’s completion (see statute above).  This is the statute of reposeA construction defect lawsuit cannot be initiated after the expiration of the statute of repose.

 

Let’s assume the following dates:

 

            Project completion (start of limitations)                                          2005

            First discovery of water intrusion                                                   2008

            General contractor completes repairs                                            2011

            General contractor sues subcontractor for indemnification            2013

 

In this scenario, the subcontractor may argue that the general contractor’s statute of limitations to sue the subcontractor for the defect and damage is barred by the statute of limitations since the first discovery of water intrusion was in 2008 and the general contractor waited to sue until 2013 (five years later).

 

But, wait…the general contractor is going to sue the subcontractor for indemnification (preferably, contractual indemnification based on the terms of the subcontract). In this scenario, the general contractor is suing after it completed repairs and established its liability to the owner for repairing the defects and damage. 

 

The statute of limitations for an action seeking indemnity does not being running until the litigation against the third-party plaintiff [general contractor] has ended or the liability [against the third-party plaintiff], if any, has been settled or discharged by payment.” Castle Constr. Co. v. Huttig Sash & Door Co., 425 So.2d 573, 575 (Fla. 2d DCA 1982) (finding general contractor’s indemnity claim against subcontractor did not accrue until the owner’s litigation against the general contractor ended or the general contractor’s liability determined).  Stated differently, the statute of limitations for the general contractor’s indemnification claim did not begin to start running until 2011 when its liability to the owner for the defects was discharged / settled.

 

Now, let’s assume the following dates:

 

     Project completion (start of limitations)                                          2005

            First discovery of water intrusion                                                   2008

            General contractor completes repairs                                            2013

            General contractor sues subcontractor for indemnification            2016

 

In this instance, the subcontractor may argue that the statute of repose expired because the general contractor waited until 2016 or eleven years after the statute of limitations started to accrue in 2005.  Guess what?  The subcontractor would be right.  See Dep’t of Transp. V. Echeverri, 736 So.2d 791 (Fla. 3d DCA 1999) (explaining that the statute of repose for construction defect claims still applies to claims for indemnity).  Stated differently, even though the general contractor sued the subcontractor for indemnification within three years of establishing its liability, it was still bound by the ten year statute of repose that started accruing in 2005, meaning such lawsuits were barred after 2015.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.