BAILOUT FOR AN IMPROPERLY DRAFTED INDEMNIFICATION PROVISION

shutterstock_1060051475A recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact.  In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect). 

 

This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts.  Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06.  The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06.  (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.) 

 

The trial court held that because the indemnification clause was unenforceable under Florida Statute s. 725.06, the general contractor’s contractual indemnification claims fail.   But, the appellate court reversed providing a bailout to an unenforceable indemnification clause by simply severing out the unenforceable portion. Thus, while a subcontractor would be required to indemnify the general contractor for its own negligence, it would not be required to indemnify the general contractor for any partial negligence caused by the general contractor.  

 

This case leads to a couple of very important takeaways:

 

  • Make sure the indemnification clauses in your construction contracts comply with Florida Statute s. 725.06.  Have a construction attorney review the indemnification provision.  Do not, and I mean, do not, bank on this ruling that even if the indemnification provision is noncompliant, only the unenforceable part will be severed.  That is not good practice.

 

  • Include a severability provision in your contract. Always.  Even though this case did not discuss such a clause, the clause will bolster the argument that only the unenforceable aspect of the provision should be severed. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE INDEMNIFICATION LIMITATION IN SECTION 725.06 DOES NOT APPLY TO UTILITY / HORIZONTAL-TYPE PROJECTS

shutterstock_486800107One of the most important provisions in construction contracts is the indemnification provision.  Appreciating contractual indemnification obligations are critical and certainly should not be overlooked.  Ever!

 

Florida Statute s. 725.06 (written about here and here) contains a limitation on contractual indemnification provisions for personal injury or property damage in construction contracts.   There should always be an indemnification provision in a construction contract that addresses property damage or personal injury.  Always!

 

Section 725.06 pertains to agreements in connection with “any construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance, including moving and excavating associated therewith…” If the contract requires the indemnitor (party giving the indemnification) to indemnify the indemnitee (party receiving the indemnification) for the indemnitee’s own negligence, the indemnification provision is unenforceable unless it contains a “monetary limitation on the extent of the indemnification that bears a reasonable commercial relationship to the contract and is part of the project specifications or bid documents, if any.”   It is important to read the statute when preparing and dealing with a contractual indemnification provision.

 

A common defense from an indemnitor in a case dealing with contractual indemnification on a construction project is that the provision is unenforceable because it does not comport with s. 725.06.  

 

In a recent case, Blok Builders, LLC v. Katryniok, 43 Fla. L. Weekly D253b (Fla. 4th DCA 2018), the indemnitor argued the indemnification provision was not enforceable. Here, a utility company hired a contractor to improve its telecommunications services. Part of the work required the contractor to provide access to preexisting underground telecommunication lines located in neighborhood easements.  The contractor hired a subcontractor to perform the required excavation to access the preexisting underground lines.   This work resulted in a personal injury action where the injured person sued the contractor, subcontractor, and utility company.

 

The contractor’s subcontract with the subcontractor required the subcontractor to indemnify the contractor and its directors, officers, employees, and agents, from loss caused wholly or partially by the subcontractor.  Thus, the indemnification provision required the subcontractor to indemnify the contractor for losses that were caused partially by the contractor’s own negligence (otherwise, the indemnification provision would be limited to losses solely attributable to the subcontractor). 

 

The contractor and utility owner both claimed that the subcontractor was responsible for contractually indemnifying them for all losses including attorney’s fees.  The subcontractor argued that the indemnification provision should be deemed unenforceable because it did not contain a monetary limitation on the extent of the indemnification. 

 

Indemnification as to the Contractor

 

The appellate court affirmed the trial court that the indemnification provision as to the contractor was enforceable because the statute (s. 725.06) did not apply.  What?  That is right, the statute did not apply because the statute does not apply to utility contracts.  What?  That is right, the appellate court held that the statute applies to “any construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance” so if the excavation is not connected to a building, structure, appurtenance, or appliance, it does not apply.  Since the project dealt with underground utility lines, s. 725.06 did not apply so the contract did not need to contain a monetary limitation on the indemnification provision.

 

Of course, in my opinion, it is hard to truly reconcile the distinction between a vertical project of a building or structure and a horizontal project, such as the project at-issue.  In other words, why would a limitation on indemnification provisions apply to one type of project but not the other?  I do not know the answer to this other than to say the court reading s. 725.06 noticed that it mentions nothing about applying to horizontal type projects that do not involve a building or structure.

 

Indemnification of Utility Owner

 

The appellate court however reversed the trial court as to the application of the indemnification provision extending to the owner.  The indemnification provision mentioned nothing about the utility owner.   That is true.  The contractor argued that because the prime contract was incorporated into the subcontract, the subcontractor’s duty to indemnify the utility owner arose from the prime contract.  But, the prime contract required the contractor to indemnify the utility owner; it mentioned nothing about subcontractors being required to indemnify the owner.

 

Interestingly, if this contract were governed by s. 725.06, this perhaps would be an issue because s. 725.06 provides that contractors may not require the indemnitor to indemnify the indemnitee for damage to persons or property caused in whole or in part by any person other than the (a) indemnitor, (b) the indemnitor’s contractors, subcontractors, sub-subcontractors, materialmen, agents, or their employees, or (c) the indemnitee’s officers, directors, agents, or employees.   Thus, the indemnification provision would not permissibly authorize the subcontractor to indemnify the owner for the owner’s own negligence. 

 

Ultimately, what this means is that the owner can pursue contractual indemnity from the contractor based on the indemnification provision in the prime contract.  The contractor would owe this indemnification (since any negligence attributable to the subcontractor would be attributable to the contractor that hired the subcontractor). This would get resolved (or play out at trial) and the contractor, based on this loss, would sue the subcontractor for indemnification for the loss connected with the subcontractor’s negligence.

 

Please read this article for an update / follow-up on this issue and this case.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CONSTRUCTION DEFECT INDEMNITY OBLIGATIONS – COVERED VS. NON-COVERED CGL CLAIMS

If you are a contractor or subcontractor and a construction defect claim is asserted against you, then you have tendered such claim to your commercial general liability (CGL) insurer.  No doubt about it.  In doing so, you have wondered whether your CGL insurer will indemnify you for the damages asserted against you by the third-party.  You have wondered whether the damages asserted against you are covered by your CGL policy.   If you have not wondered and asked these questions, then you should!  Below is a portion of a presentation I recently put on regarding construction defect indemnity obligations under CGL policies and, particularly, covered claims versus non-covered claims.  

 

Download (PDF, 195KB)

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

INDEMNIFICATION PROVISIONS AND “IN WHOLE OR IN PART” LANGUAGE

imagesIf you negotiate or prepare construction contracts, then you should be familiar with Florida Statute s. 725.06.  This statute contains requirements for indemnification provisions in construction contracts and is a must-know and must-read for all construction participants responsible for negotiating and preparing construction contracts, especially those that contain indemnification provisions for bodily injury and property damage (and all such contracts do and should contain such indemnification language!).   For more on Florida Statute s. 725.06, please check out these articles:

 

  1. Make Sure Indemnification Provisions Clearly Reflect the Required Scope of the Indemnification;
  2. The Scope of a Release in a Settlement and Contractual Indemnification; and
  3. Buttoning-Up Contractual Indemnification Language.

 

Although not a construction case, the opinion in ATC Logistics Corporation v. Southeast Toyota Distributors, LLC, 41 Fla. L. Weekly D816b (Fla. 1st DCA 2016), demonstrates the importance of drafting clear indemnification language.    This case contained the following indemnification provision:

 

(a) ATC [Carrier] shall indemnify and hold harmless SET from and against any and all losses, liabilities, damages, costs, fines, expenses, deficiencies, taxes and reasonable fees and expenses of counsel and agents, including any costs incurred in enforcing this Agreement, that SET may sustain, suffer or incur arising from (i) Carrier’s failure or alleged failure to comply, in whole or in part, with any of its obligations hereunder; (ii) any loss of or damage to a Vehicle while loaded onto, transported on or unloaded from a Car Carrier; (iii) any damage to any property of SET caused by the maintenance or operation of any Car Carrier or the loading or unloading of any Car Carrier; (iv) any claims by any third person with respect to death, injury or property damage caused by the maintenance or operation of any Car Carrier or the loading, transportation or unloading of Vehicles on or from a Car Carrier and (v) any claims resulting from or arising out of injury or death of any employee, agent of contractor of Carrier including claims alleging that SET failed to provide a safe place to work.

 

The indemnity obligation was broken into five (i – v) sections. 

 

In this case, SET sued ATC (the named Carrier in the indemnification provision) to recover amounts it paid out in a settlement.  SET argued that ATC was responsible for indemnifying it for its (SET’s own) negligence based on the language in section (i) that required ATC to indemnify SET for “Carrier’s failure or alleged failure to comply, in whole or in part, with any of its obligations hereunder.”

 

The issue, however, was that SET was really seeking indemnification relating to section (iv) which did NOT contain any “in whole or in part” language.  In other words, section (iv) did not require ATC to indemnify SET for its actions whether caused “in whole or in part” by ATC’s negligence.  Had section (iv) contained this “in whole or in part” language, then ATC would have likely been required to fully indemnify SET for its actions even if the damages were partially caused by the negligence of SET.  While SET wanted the “in whole or in part” language included in section (i) to be read into the language in section (iv), this was NOT how this clause was written and the court is not there to rewrite parties’ contracts.  Accordingly, the First District held that ATC was not required to indemnify SET for SET’s negligence.

 

Importantly, if the indemnification provision pertained to a construction contract and required the indemnitee (e.g., subcontractor) to indemnify the indemnitor (e.g., contractor), it would need to include certain language for it to be enforceable under s. 725.06Such indemnification provisions that require the indemnitee to indemnify the indemnitor for “liability for damages to persons or property caused in whole or in part by any act, omission, or default of the indemnitee arising from the contract or its performance, shall be void and unenforceable unless the contract contains a monetary limitation on the extent of the indemnification that bears a reasonable commercial relationship to the contract and is part of the project specifications or bid documents, if any.” Fla. Stat. s. 725.06.   

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.