QUICK NOTE: NOT IN CONTRACT WITH THE OWNER? SERVE A NOTICE TO OWNER.

A subcontractor or supplier not in direct contract with an owner must serve a Notice to Owner within 45 days of initial furnishing to preserve construction lien rights.  Of course, the notice of commencement should be reviewed to determine whether the subcontractor or supplier has construction lien or payment bond rights so that it knows how to best proceed in the event of nonpayment.   Serving a Notice to Owner should be done as a matter of course — a standard business operation; no exceptions.  

 

However, if a supplier specially manufactures or fabricates material for purposes of a construction project, it must serve the Notice to Owner within 45 days from the actual start of fabrication, and not from when the materials are delivered to the site.  A reason for this is that a supplier of specially fabricated material can lien for the unpaid material even if the material is NOT incorporated into the construction project.  This is different than a supplier liening for other material which does require the material to be incorporated into the project.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

TERMINATING NOTICE OF COMMENCEMENT WITHOUT CONTRACTOR’S FINAL PAYMENT AFFIDAVIT

shutterstock_399902515Prior to construction work being performed on your property, a Notice of Commencement should be recorded.  Among other things, construction liens will relate back in time to an effective Notice of Commencement (meaning it has not expired).  For this reason, lenders or others will want the Notice of Commencement to be terminated when the job is complete by recording in the official records a Notice of Termination of the Notice of Commencement.  There is a statutory procedure to terminate a Notice of Commencement pursuant to Florida Statute 713.132.  

 

Frequently, a clerk will want the Notice of Termination of the Notice of Commencement to be accompanied with a Contractor’s Final Payment Affidavit because 713.132 says, in material part:

 

(2) An owner has the right to rely on a contractor’s affidavit given under s. 713.06(3)(d), except with respect to lienors who have already given notice, in connection with the execution, swearing to, and recording of a notice of termination. However, the notice of termination must be accompanied by the contractor’s affidavit.

 

Notwithstanding, the Fifth District in Lasalle Bank National Ass’n v. Blackton, Inc., 59 So.3d 329, 331 (Fla. 5th DCA 2011) in interpreting this subsection stated:

 

We interpret this subsection to grant an owner the right to rely on the a contractor’s affidavit as an alternative to giving a sworn statement in its notice of termination that “all lienors have been paid in full.”  Here, the contractor’s affidavit attached to the notice of termination was superfluous because Independence, as owner, had already averred in the notice of termination that all lienors had been fully paid. 

 

 

It is always beneficial for an owner to obtain and rely on the Contractor’s Final Payment Affidavit since the contractor would be the one to hire the subcontractors  and know whether all lienors (including itself) have been fully paid and, if not, those that are still owed money.  However, there are times an owner may not be able to get that affidavit for a host of reasons (for example, if the job never actually commenced or the contractor is uncooperative in this regard).   In these circumstances, the owner should be able to record the Notice of Termination of the Notice of Commencement absent the Contractor’s Final Payment Affidavit by averring in the Notice of Termination that all lienors have been paid.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

RECOMMENCING CONSTRUCTION ON A PROJECT DUE TO A CESSATION OR ABANDONMENT

shutterstock_733809610There are instances where the owner of a construction project terminates its general contractor prior to the completion of the project.  There are instances where the owner suspends the work prior to the completion of the project, meaning there is a cessation in the construction.  And, there are instances where the project is simply abandoned.  I have been involved in all instances, and the owner’s reasons vary…from an owner claiming a termination for default, termination for convenience, or a suspension or abandonment due to the market or financial factors. Regardless of the owner’s reasoning, at some point—hopefully—the owner will want to resume or, more properly stated, recommence construction and complete the project. 

 

Based on the length of the cessation, when the owner finally recommences construction, oftentimes the right approach is for the owner to strictly comply with the recommencement procedure set forth in Florida Statute s. 713.07(4):

 

 

If construction ceases or the direct contract is terminated before completion and the owner desires to recommence construction, he or she [1] may pay all lienors in full or pro rata in accordance with s. 713.06(4) prior to recommencement in which event all liens for the recommenced construction shall take priority from such recommencement; or [2] the owner may record an affidavit in the clerk’s office stating his or her intention to recommence construction and that all lienors giving notice have been paid in full except those listed therein as not having been so paid in which event 30 days after such recording, the rights of any person acquiring any interest, lien, or encumbrance on said property or of any lienor on the recommenced construction shall be paramount to any lien on the prior construction unless such prior lienor records a claim of lien within said 30-day period. A copy of said affidavit shall be served on each lienor named therein. Before recommencing, the owner shall record and post a notice of commencement for the recommenced construction, as provided in s. 713.13.  [Per Florida Statute s. 713.13(5)(a), if an owner changes contractors, the owner must record either a new notice of commencement or notice of recommencement.]

 

Under this statute, when the owner wants to recommence construction, the owner has two options. 

 

First, the owner can pay all lienors in full or pro rata pursuant to Florida Statute s. 713.06(4), which lists the priority of payments to lienors.  I like the idea of getting final releases or a release through the date of payment with no carve-out (for retainage or otherwise).

 

Second, the owner can record an affidavit stating his/her intention to recommence construction and that all lienors giving notice (the contractor and those that served a notice to owner) have been paid in full except those specifically listed.   Thirty days after the affidavit is recorded, the rights of any person that acquires an interest in the property or liens the property is superior to any lien on the prior construction (before construction ceased) unless such lienor records a claim of lien within the 30-day window.   If the lienor already recorded a lien, the lienor would need to re-record the lien within this 30-day window to preserve its lien priority (although, importantly, the re-filing does not extend the one year period for the lienor to foreclose on its lien).   See Foy v. Mangum, 528 So.2d 1331 (Fla. 5th DCA 1988) (re-filing the lien ensures the lienor has priority over lienors performing recommenced work, but it does not delay the lienor’s requirement to timely foreclose the original recorded lien).  Any lienor identified in the affidavit would get served with a copy of the affidavit.

 

The owner also records a new notice of commencement / notice of recommencement for the recommenced work where any liens relating to the recommenced work would relate back, from a lien priority standpoint, to this notice of commencement.

 

A value to the owner complying with this procedure is that it can apply the remaining contract balance to the recommenced work and if the funds are expended the total amount the owner will be liable for liens recorded before the cessation could be reduced or eliminated (i.e., the proper payments defense). See Alton Towers, Inc. v. Coplan Pipe & Supply Co., 262 So.2d 671 (Fla. 1972) (if owner complies with the recommencement procedure, the owner’s liability is limited to original direct contract price, thus where completion costs exceeded defaulting contractor’s direct contract amount, supplier was not entitled to recover from owner).

 

If you are an owner or contractor involved in a ceased project, or a project where construction will be recommencing, it is in your interests to engage legal counsel familiar with the recommencement procedure.  It is important that you understand construction lien priority, how the recommencement can impact lien priority, and the owner’s potential liability if it properly complies with the recommencement procedure.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

TERMINATING THE NOTICE OF COMMENCEMENT (WITH A NOTICE OF TERMINATION)

shutterstock_259385300The notice of commencement is important for purposes of construction lien priority.   Stock Bldg. Supply of Florida, Inc. v. Soares Da Costa Const. Services, LLC, 76 So.3d 313, 317 (Fla. 3d DCA 2011) (“[A] notice of commencement serves to determine the priority of liens under the Construction Lien Law.”).   A lien relates back in time to the date the notice of commencement was recorded assuming the notice of commencement is still in effect when the lien is recorded (or an amended noticed of commencement is recorded).  Lien priority is very important and the reason why a contractor should always want to ensure there is an effective notice of commencement in place rather than an expired notice of commencement.

 

For the same reasons why a contractor wants to ensure there is an effective notice of commencement, there are times an owner wants to terminate a notice of commencement.  An owner may want to terminate the potential priority of a construction lien.  For instance, say the owner is refinancing or obtaining a construction loan in the midst of construction.  A lender will want to ensure its mortgage maintains first priority and certainly priority over a potential construction lien.  Otherwise, why would a lender finance the construction if it does not maintain first priority. It generally will not.  Thus, an owner needs to terminate the notice of commencement so that the closing occurs on the loan and the mortgage recorded before a new notice of commencement is recorded and construction continues.

 

Florida Statute s. 713.132 allows an owner to statutorily terminate the effectiveness of a notice of commencement by recording a notice of termination.  It is a statutory procedure that must be followed and it is important that an owner and contractor seek the assistance of counsel in following this procedure.  The statute contains in relevant part:

 

(3) An owner may not record a notice of termination except after completion of construction, or after construction ceases before completion and all lienors have been paid in full or pro rata in accordance with s. 713.06(4). If an owner or a contractor, by fraud or collusion, knowingly makes any fraudulent statement or affidavit in a notice of termination or any accompanying affidavit, the owner and the contractor, or either of them, as the case may be, is liable to any lienor who suffers damages as a result of the filing of the fraudulent notice of termination; and any such lienor has a right of action for damages occasioned thereby.

 

(4) A notice of termination is effective to terminate the notice of commencement at the later of 30 days after recording of the notice of termination or the date stated in the notice of termination as the date on which the notice of commencement is terminated, if the notice of termination has been served pursuant to paragraph (1)(f) on the contractor and on each lienor who has a direct contract with the owner or who has served a notice to owner.

 

If a notice of termination of a notice of commencement is recorded as a result of the cessation of construction, a new notice of commencement must be recorded before completion of the improvement may be recommenced.”  Stock Bldg. Supply of Florida, 76 So.3d at 317-18.    

 

From a lienor’s perspective, it is important that they understand that when a new notice of commencement is recorded, the lienor must re-serve any required notices to preserve lien or bond rights (such as a notice to owner or notice of intent to look to the contractor’s bond).  Stock Bldg. Supply of Florida, 76 So.3d at 318 (when owner recorded new notice of commencement, the project began anew and lienor was required to re-serve notices under Florida’s Construction Lien Law).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

PRESERVING YOUR RIGHTS TO SECURE PAYMENT ON CONSTRUCTION PROJECTS (WITH EXAMPLES)

shutterstock_330137966All participants across the construction industry should understand what efforts they should take to maximize and collateralize payment.  No one wants to work for free and, certainly, no one in the construction industry wants to work without ensuring there is some mechanism to recover payment in the event they remain unpaid.   Being proactive and knowledgeable can go a long way when it comes to recovering your money.

 

Your Contract – It starts with the contract.  You should understand those risks that are allocated to you and those that are allocated to another party.  And, you should understand the contractual mechanism to resolve claims and disputes and whether your contract has a prevailing party attorney’s fees provision. In addition to contractual rights, there are tools for you to maximize your collection efforts.

 

Construction Liens – Construction liens apply to private projects, not public projects.  This is a very valuable tool as they allow you to collateralize nonpayment against real property.  It is really important you know what you need to do to preserve your construction lien rights.  Construction liens are a creature of statute and the failure to properly preserve and perfect your construction lien rights can be fatal to your lien claim.  

 

Example 1.   I am a general contractor on a private condominium project.  I am owed $1,000,000 from the developer.    As the general contractor, I can record a construction lien within 90 days from my final furnishing on the project exclusive of punchlist and warranty work.   (This is good for one year from recording unless the developer takes steps to shorten the limitations period to foreclose the lien.)  I serve a copy of the lien on the developer (and others that may be listed in the Notice of Commencement) within 15 days of the recording of the lien.  At least 5 days before filing suit to foreclose on the lien, I need to serve a Contractor’s Final Payment Affidavit on the developer.

***

Example 2.  I am a subcontractor on a private condominium project.  I am owed $1,000,000 from the general contractor.   Since I am not in privity with the owner/developer, I need to serve a Notice to Owner within 45 days of my initial furnishing on the owner and general contractor (and others listed in the Notice of Commencement).  I need to record my construction lien within 90 days from my final furnishing and furnish a copy on the owner within 15 days from the recording of the lien.  Also, since I am not in privity with the owner/developer, I do not need to serve a Contractor’s Final Payment Affidavit.  I need to sue on the lien within 1 year from the recording of the lien (unless efforts are taken to shorten the limitation period).

 

Payment Bonds (Private Projects) – There can be statutory payment bonds on private projects.   The Notice of Commencement will attach a copy of the payment bond, if one exists.  If one is not referenced and attached, then that means the claimant has lien rights.  It is really important you know what you need to do to preserve your payment bond rights on private projects – they are not necessarily the same as preserving payment bond rights on public projects.   Preserving your bond rights allows you to pursue your claim for nonpayment against a surety bond.

 

Example 3.  I am a subcontractor on a private condominium project. I am owed $1,000,000 from the general contractor.  I know from the Notice of Commencement that the general contractor furnished an unconditional payment bond.  Since I am in privity with the general contractor, I do not need to serve a Notice of Intent to look to the Bond on the contractor.   But, within 90 days of final furnishing, I need to serve the general contractor and payment bond surety with a Notice of Non-Payment.  I then need to sue on the payment bond within 1 year from my final furnishing.

  

Payment Bonds (Public Projects)—There are statutory payment bonds on Florida public projects and Federal projects.  There are different procedures to preserve rights depending on the type of public project and it is important to know what steps you need to take to preserve your rights.  Preserving your bond rights allows you to pursue your claim for nonpayment against a surety bond.

  

Example 4.  I am a subcontractor on a Florida school public project. I am owed $1,000,000 from the general contractor.  I know that since I am in privity with the general contractor, I do not need to serve a Notice of Intent to look to the Bond on the contractor.  I also know since I am in privity with the general contractor, I do not need to serve a Notice of Non-Payment on the general contractor and surety.  (Note, this is different than if this were a private project).   I need to sue on the payment bond within 1 year from my final furnishing. 

 ***

Example 5.  I am a supplier to a subcontractor on a Florida school public project.  I am owed $1,000,000 from the subcontractor. Since I am not in privity with the general contractor, I need to serve a Notice of Intent to look to the Bond within 45 days of my initial furnishing.  Also, since I am not in privity with the general contractor, I need to serve a Notice of Non-Payment on the general contractor and surety within 90 days of my final furnishing.  I need to sue on the payment bond within 1 year from my final furnishing.

 ***

Example 6.  I am a sub-subcontractor on an FDOT public transportation project.  I am owed $1,000,000 from the subcontractor.  Since I am not in privity of contract with the general contractor, I need to serve a Notice of Intent to look to the Bond on the general contractor within 90 days of my initial furnishing. (Note, this is different than other public projects.)   Also, since I am not in privity with the general contractor, I need to serve a Notice of Non-Payment within 90 days of my final furnishing on the general contractor and surety. I then need to sue on the payment bond within 365 days of the final acceptance of the contract and work by the FDOT.  (Note, this is different than other public projects.)

 ***

Example 7.  I am a subcontractor to a prime contractor on a federal project.  I am owed $1,000,000 from the prime contractor.   Since this is a federal project, there is no preliminary notice requirement.  (Note, this is different than other public projects.)  Since I am in privity with the general contractor, I do not need to serve a Notice of Non-payment on the prime contractor within 90 days of my final furnishing. I need to sue on the payment bond within 1 year from my final furnishing.

 ***

Example 8.  I am a supplier to a subcontractor on a federal project.  I am owed $1,000,000 from the subcontractor.  Since this is a federal project, there is no preliminary notice requirement.   Also, since I am not in privity with the prime contractor, I need to serve a Notice of Non-Payment only on the prime contractor within 90 days of my final furnishing.  (Note, this is different than other public projects.)  I need to sue on the payment bond within 1 year from my final furnishing.

 

 

As reflected from the examples, preserving and perfecting construction lien and payment bond rights is nuanced and depends on the type of project.   Know your rights.  Be proactive when it comes to preserving and perfecting your rights.  And, make sure to utilize the services of a construction attorney that can help you maximize your collection efforts correctly

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

PROPERLY TERMINATING A NOTICE OF COMMENCEMENT

unknownIn prior postings I have discussed the importance of the notice of commencement, particularly when it comes to notifying lienors of applicable information regarding their construction lien or payment bond rights and the priority of construction liens.

 

In certain circumstances, it may be in an owner’s best interest to terminate the effectiveness of the notice of commencement by recording a notice of termination of the notice of commencement.   This is governed by Florida Statute s. 713.132 set forth at the bottom of this article.

 

An owner cannot record a notice of termination of the notice of commencement as a “gotcha” tactic simply because it does not want to pay lienors or wants to lessen the value of potential liens by impacting the priority of those liens.  If this were the case, owners may regularly try to employ this tactic as a means to reduce payment obligations or pay cents on the dollar (since a construction lien is only as good as the priority of that lien and the equity in the real property).   To this point, s. 713.132(3) specifies those occasions when an owner can record a notice of termination of a notice of commencement:

 

An owner may not record a notice of termination except after completion of construction, or after construction ceases before completion and all lienors have been paid in full or pro rata in accordance with s. 713.06(4). If an owner or a contractor, by fraud or collusion, knowingly makes any fraudulent statement or affidavit in a notice of termination or any accompanying affidavit, the owner and the contractor, or either of them, as the case may be, is liable to any lienor who suffers damages as a result of the filing of the fraudulent notice of termination; and any such lienor has a right of action for damages occasioned thereby.

 

In a nutshell, an owner may terminate the notice of commencement by:

 

  1. Recording a notice of termination that references the OR BK and PG of the notice of commencement and contains the same information in the notice of commencement;
  2. Identifying the date in the notice of termination that the notice of commencement will be terminated, but the termination cannot be less than 30 days after the notice of termination is recorded (meaning the notice of commencement will NOT be terminated until at least 30 days after it is recorded);
  3. Stating that ALL lienors have been paid in full;
  4. Stating that before recording the notice of termination of the notice of commencement, the owner served a copy of the notice of termination on its contractor, anyone directly hired by the owner, and on anyone that served a notice to owner UNLESS the owner received a final waiver and release of lien upon final payment from that lienor; and
  5. Including the contractor’s payment affidavit identifying the amount it is owed and that it owes lienors, which the owner can rely on in preparing the notice of termination. 

 

Once the notice of termination of the notice of commencement is recorded, construction liens recorded after the termination will NOT relate back to the notice of commencement (thus, impacting the priority of the liens).  This is why it is important to record any construction lien within 30 days once you receive a notice of termination of the notice of commencement if you have NOT been paid in full or there is a payment dispute.

 

For example, in Lasalle Bank National Association v. Blackton, Inc., 9 So.3d 329 (Fla. 5th DCA 2011), the home-builder recoded a notice of termination of the notice of commencement that terminated the notice of commencement 30 days from its recording.  Attached to the notice of termination was the homebuilder’s payment affidavit.  There were no liens within this 30-day window.   After homeowners moved into the house and their mortgage was recorded, they notified the homebuilder of certain defects/warranty items, and the homebuilder engaged a new subcontractor to fix the defects/warranty items.  The subcontractor was not paid and recorded a lien.  The issue was whether the subcontractor’s lien related back to the notice of commencement and took priority over the homeowners’ mortgage.   The Fifth District Court of Appeal held that the mortgage had priority since the notice of commencement was terminated and the lien was recorded after the notice of commencement had been terminated.  This meant the lien was inferior to the mortgage

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: PERFECT PRIVATE PROJECT PAYMENT BOND RIGHTS IF NOT IN PRIVITY WITH GENERAL CONTRACTOR

imagesRemember, if you are not in privity of contract with the general contractor on a private project where the general contractor furnished the owner with a payment bond (e.g., sub-subcontractor or supplier), you NEED to perfect your payment bond rights by initially serving a notice of intent to look to the bond on the general contractor.  (Or, serve a notice to owner but make sure you serve a copy on the general contractor).  Not serving the general contractor with this initial notice can deprive you of payment bond rights.  How do you know if there is a payment bond in place?  Pull up the notice of commencement recorded in the official records where the property is located which should identify if there is a payment bond and will attach a copy of the payment bond.  

 

For more information on payment bond rights, check out this chart.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

WHAT TO DO IF THE PAYMENT BOND IS NOT RECORDED WITH THE NOTICE OF COMMENCEMENT

UnknownThere is an unconditional payment bond for the project but it was not recorded with the Notice of Commencement.  Now there are subcontractor construction liens recorded against the property.  What do I do?  I thought the point of the payment bond was to exempt the real property from subcontractor and supplier liens.

 

No need to worry!  Liens can be transferred to the payment bond even though the payment bond was not recorded with the Notice of Commencement.

 

The payment bond operates to “secure every lien under the direct contract accruing subsequent to its execution and delivery.”  Fla.Stat. s. 713.23(2).  Even though the payment bond was not recorded with the Notice of Commencement as required, the owner or contractor can record a Notice of Bond with a copy of the payment bond that will operate to transfer the lien to the security of the payment bond. 

 

To this point, Florida Statute s. 713.13(1)(e) states in relevant part:

 

[I]f a payment bond under s. 713.23 exists but was not attached at the time of recordation of the notice of commencement, the bond may be used to transfer any recorded lien of a lienor except that of the contractor by the recordation and service of a notice of bond pursuant to s. 713.23(2). The notice requirements of s. 713.23 apply to any claim against the bond; however, the time limits for serving any required notices shall, at the option of the lienor, be calculated from the dates specified in s. 713.23 or the date the notice of bond is served on the lienor.

 

Stated differently, just because the payment bond was not recorded with the Notice of Commencement does not mean the payment bond is worthless.  Rather, it can still be used to transfer construction liens to the security of the bond. 

 

Further, if discovered early enough, and within the effective period of the Notice of Commencement,  an Amended Notice of Commencement can be recorded which attaches a copy of the payment bond.  The Amended Notice of Commencement needs to be served by the owner “upon the contractor and each lienor who serves notice before or within 30 days after the date the amended notice is recorded.”  Fla.Stat. s. 713.13(5)(b). But, the Amended Notice of Commencement can be used to clarify the omission of the payment bond in the original Notice of Commencement.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

RECORDING THE NOTICE OF BOND TO TRANSFER THE CONSTRUCTION LIEN TO THE PAYMENT BOND

imagesIf a contractor furnishes a payment bond for a private project (per Florida Statute s. 713.23), a copy of that bond should be recorded with the Notice of Commencement recorded in the official records of the county where the project is located. A contractor furnishes a payment bond on a private project in order to exempt the owner’s real property from construction liens.

 
There are times, though, where a subcontractor or a supplier will still go ahead and record a lien against the owner’s real property even though there is a payment bond that was recorded with the Notice of Commencement. This is a frustrating scenario because the point of paying for the payment bond and furnishing the bond is to prevent this very scenario from occurring. No worries, however, because Florida’s Lien Law efficiently addresses this scenario by allowing the contractor or owner to record in the official records and serve on the lienor a verified Notice of Bond (attaching a copy of the payment bond) that will operate to transfer the lien to the payment bond. Fla. Stat. s. 713.23(2). A copy of the Notice of Bond form is provided below.

 
Moreover, this Notice of Bond procedure would apply even if the contractor furnished a payment bond, but for whatever reason, that payment bond was not recorded with the Notice of Commencement. When this happens, and it does happen, the subcontractor or supplier may honestly not know that the contractor actually furnished a payment bond and will move forward and record a lien. Again, no worries, because the contractor or owner should implement the same procedure by recording and serving the lienor with a Notice of Bond. Every lien recorded AFTER the execution and delivery of the payment bond will be transferred to the payment bond through the recording of the Notice of Bond (attaching a copy of the payment bond).

 

Now, if the contractor did NOT furnish a payment bond BEFORE the lien was recorded, the contractor could move to transfer the lien to a lien transfer bond pursuant to Florida Statute s. 713.24. This is different than a payment bond. The lien transfer bond is simply a mechanism where a contractor through a statutory procedure procures and records a lien transfer bond that is designed to transfer a specific lien to the security of the bond. (When a contractor procures a lien transfer bond, the bond must be for the principal amount of the lien, plus the greater of $1,000 or 25% of the principal amount to cover potential attorney’s fees and court costs, plus three years worth of interest on the principal amount at the prevailing statutory rate.)

 

 

NOTICE OF BOND

To (Name and Address of Lienor)
You are notified that the claim of lien filed by you on ___, ___, and recorded in Official Records Book ___ at page ___ of the public records of ___ County, Florida, is secured by a bond, a copy being attached.
Signed: (Name of person recording notice)

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.