When a party is preserving their construction lien rights, the party will look to the recorded Notice of Commencement. This is the recorded document that provides the lienor with the information for purposes of preserving construction lien rights. A Notice to Owner company will typically rely on the Notice of Commencement to serve Notices to Owners from lower tiers not in contract with the owner. However, when it comes to preparing the lien, a lienor should look beyond just the Notice of Commencement and also look to the property appraiser’s website as a backstop.
In a recent case, a window company had the homeowner sign the Notice of Commencement and then filled in the information. The company naturally did this for the convenience of the homeowner that probably was unfamiliar with the Notice of Commencement process. Regardless, information in the Notice of Commencement was inaccurate. It failed to include all the real property owners. Thus, when a payment dispute arose and a construction lien was prepared, it did not identify all of the real property owners. All of the real property owners were added later during the pendency of a lien foreclosure lawsuit. The trial court denied the lien because of the defective / insufficient Notice of Commencement — the lienor assumed the risk of error by filling out the information in the Notice of Commencement. The trial court further denied the lien holding that because the work did not commence within 90 days of the Notice of Commencement, the Notice of Commencement is void.
On appeal, the appellate court agreed that the lienor assumed the risk of errors in the Notice of Commencement by taking the lead in filling out the information in it. There was nothing to reflect the lienor even asked the homeowner when there were other real property owners.
However:
Even if the notice of commencement was insufficient, the trial court nonetheless erred, because the insufficient notice of commencement does not invalidate a properly recorded and served claim of lien, and [the window company] strictly complied with the conditions precedent to foreclose on the claim of lien as to [the homeowner that signed the contract], who was an owner in privity with [the [lienor]. Additionally, the defective notice of commencement merely affected the lien’s start date. Generally, all construction liens relate back to the recording of the notice of commencement. A defective notice of commencement does not invalidate the recorded claim of lien; instead, it simply means the effective date of the attachment of the lien is the date the claim of lien is recorded in the public records (a potential loss of priority of lien).
James B. Martin, Inc. v. Moore, 2026 WL 1884372 (Fla. 4th DCA 2026) (internal citations omitted).
Finally, the appellate court sidestepped the argument regarding the Notice of Commencement being void because work did not commence within 90 days of its recording by finding that the lienor’s measurements of the windows and ordering windows was sufficient work to keep the Notice of Commencement active.
Here is why this opinion is noteworthy.
First, the risk of loss in errors with the Notice of Commencement is assumed by the person filling out the information. This makes sense, but if the owner was the one to make the errors, that shouldn’t impact a lienor’s priority. That’s unclear based on this opinion.
Second, if a property owner signs the contract and the property owner is owned by multiple people, shouldn’t the person that signed the contract be deemed the agent for the other owners? A Notice of Commencement shouldn’t need to be signed by every single property owner if the person signing the contract is representing that they have authority. In other words, it shouldn’t be a lienor’s responsibility to confirm that authority, or that the lienor needs to serve a Notice to Owner on the non-signing owners (as this was an issue in this case but not properly preserved for appeal when one of the owners got the lien dismissed and recovered attorney’s fees because she didn’t receive a Notice to Owner).
Third, while Florida Statute s. 713.13(2) states that, “If the improvement described in the Notice of Commencement is not actually commenced within 90 days after the recording thereof, such notice is void and of no further effect,” this would not and should not impact the viability of a lien. It should impact the priority of a lien such that it would not relate back to the Notice of Commencement. But it should not mean there are no lien rights.
Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.



If you are an unpaid contractor in direct contract with the owner of real property, you should be serving a
A subcontractor or supplier not in direct contract with an owner must serve a 
