ATTORNEY’S FEES ENTITLEMENT AND APPLICATION UNDER SUBCONTRACT DEAULT PROVISION

Many subcontracts contain a provision in the default section that reads something to the effect:

 

Upon any default, Subcontractor shall pay to Contractor its attorney’s fees and court costs incurred in enforcing this Subcontract or seeking any remedies hereunder.” 

 

Oftentimes, a party may wonder as to the enforceability of the provision and how it is applied in the context of a dispute between a contractor and its subcontractor where both parties have asserted claims against the other.   

 

In an opinion out of the Middle District of Georgia, U.S. f/u/b/o Cleveland Construction, Inc. v. Stellar Group, Inc., 2019 WL 338887 (M.D.Ga. 2019), a subcontractor and prime contractor on a federal construction project each asserted claims against the other in the approximate amount of $4 Million, meaning there was a potential $8 Million swing in the dispute.

 

The subcontract contained a provision entitling the contractor to recover attorney’s fees incurred in enforcing the subcontract or seeking remedies under the subcontract upon any default, identical to the provision above. 

 

The case proceeded to a jury trial and a general verdict form was presented to the jury that did not differentiate between the claims each party sought.  The jury found the contractor was liable to the subcontractor for approximately $2.5 Million and the subcontractor was liable to the contractor for approximately $1.3 Million, leaving a net verdict in favor of the subcontractor for approximately $1.2 Million.

 

The contractor, however, sought its attorney’s fees (and costs) pursuant to the default provision since the jury found the subcontractor was liable to it for approximately $1.3 Million.   The subcontract provided that upon a default, the contractor is entitled to attorney’s fees incurred in (i) enforcing the subcontract or (ii) seeking remedies under the subcontract.  But, to be entitled to fees, there had to be a subcontractor default. 

 

The trial court found the subcontract was unclear as to the actual connection that needed to exist between the default and what is actually recoverable at trial.  In other words, it was unclear whether there needed to be a relationship between the default and the recoverable attorney’s fees or whether the contractor could recover attorney’s fees upon any default regardless of whether the attorney’s fees incurred related to that specific default.  The trial court did not interpret the default attorney’s fees provision that broadly and held the contractor must show a causal connection between the default, the enforcement of the subcontract or remedies sought under the subcontract, and the attorney’s fees incurred.  “Under the [subcontract] enforcement prong, [Contractor] would be expected to show that the fees it incurred related to the successful pursuit of the claim for default.  Similarly, under the remedies [sought under the subcontract] prong, [Contractor] would only be entitled to fees incurred in the actual obtaining of a remedy for [Subcontractor’s] default.”  Stellar Group, 2019 WL at *2.  

 

This is not an easy feat, and here lies the problem.    Based on a general jury verdict form, the jury was not asked to make specific findings as to facts that could support the issues relating to the default or the claims prevailed on.  Thus, allocating those attorneys’ fees incurred to the default and enforcement of the subcontract it prevailed on is taking a shot in the dark.

 

Notwithstanding, there are lessons learned from this case.  First, the trial court did not find the attorney’s fees provision unenforceable even through the net judgment went in favor of the subcontractor,  That is promising.  Second, for purposes of a jury trial, had the contractor objected to a general verdict form and requested special interrogatories in the verdict form relating to this issue, the contractor may have been able to allocate certain attorney’s fees incurred to the claims or issues it prevailed on at trial.  And, third — perhaps the most important — this subcontract language can be revisited to make the entitlement and application of attorney’s fees more clear in favor of the contractor.   With that said, the trial court’s interpretation that the fees incurred should have a causal connection to the default and enforcement / remedies under the subcontract prevailed on is not an unreasonable application by any means. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

GENERAL CONTRACTOR’S ABILITY TO SUPPLEMENT SUBCONTRACTOR PER SUBCONTRACT

shutterstock_142349770As a subcontractor, you need to appreciate that the subcontract you (more than likely) sign is going to have you bear risk associated with furnishing manpower to maintain the prime contractor’s schedule and progress.   A subcontractor can factor some of this risk into the lump sum amount it agrees to in the subcontract.  But, from the general/prime contractor’s perspective, it is very important that this risk is borne by the subcontractor because there is no such thing as a schedule written in stone.  The baseline schedule, whether attached to the subcontract or not, will change.  Activities will be re-sequenced.  Activities will be added.  Activities will overlap.  Activity start dates and finish dates will change.  It is the nature of construction.  As a subcontractor, you know all of this because it is the same no matter the project. Schedules are never written in stone — they change on a regular basis.

 

The subcontract will include a number of provisions that address the schedule, the prime contractor’s discretion to adjust the schedule and supplement the work, and the subcontractor’s requirement to maintain progress.  These are provisions that shift risk to the subcontractor including:

 

  • The subcontractor will furnish all manpower to complete its scope of work;
  • Time is of the essence with respect to the subcontractor’s performance of its work;
  • The prime contractor has the right to decide the time and order of various portions of the subcontractor’s work;
  • The subcontractor must prosecute its work in a prompt and diligent manner and at such times as the prime contractor directs;
  • The subcontractor must keep itself thoroughly informed as to the overall progress of the project;
  • The subcontractor must not delay, hinder, or interfere with the progress of the project;
  • The subcontractor must notify the prime contractor within “X” days after the occurrence of the circumstances giving rise to a change (or delay) or else waive such claim for additional time or compensation;
  • If the subcontractor fails to furnish sufficient manpower or prosecute the work with promptness and diligence, which is not corrected after “X” days after receiving notice, the prime contractor can declare the subcontractor in default, supplement the subcontractor, terminate the subcontract in whole or in part, and/or complete the subcontract work at the expense of the subcontractor;
  • The prime contractor can withhold payments if the subcontractor is unable to comply with subcontractual obligations, perform its work, or is delaying or is in reasonable danger of delaying the work; and
  • The subcontractor is required to indemnify the prime contractor for damages resulting from its breaches of the subcontract (which may be an indemnification provision separate from an indemnification for personal injury or property damage claims).

 

These types of provisions are crafted a number of different ways, are perhaps more onerously drafted, but the intent is the same relating to the subcontractor assuming risk and ensuring the prime contractor has recourse against the subcontractor associated with that risk.   (An example of such risk-shifting provisions in a subcontract can be found here.)  Again, these are important provisions for prime contractors to include in subcontracts.  They are also important provisions for subcontractors to factor in the risk associated with the subcontract amount.

 

In a recent bench trial, MWH Constructors, Inc. v. Brown and Brown Electric, Inc., 2018 WL 2087687 (S.D.Fla. 2018), a prime contractor sued its electrical subcontractor for breach of subcontract and contractual indemnification associated with the subcontractor’s inability to maintain progress during the construction of a water treatment project.  The subcontractor counter-sued for its contract balance.  The subcontract at-issue contained all of the provisions discussed above.

 

During the subcontractor’s scope of work, its president and qualifier died.  Thereafter, it began to fall behind schedule and was not furnishing sufficient manpower. There were numerous discussions between the prime contractor and subcontractor regarding the subcontractor’s inability to timely complete its work.  It was discussed that the subcontractor needed additional manpower and needed to work on Saturdays to recover lost time.   The subcontractor, however, was unable to abide by its commitments.  Further meetings were held and notifications were sent to the subcontractor. The public owner notified the prime contractor the job was delayed, the electrical subcontractor was behind schedule, and was threatening to assess liquidated damages.  Finally, after the subcontractor was unable to improve its progress, the prime contractor declared the subcontractor in default and supplemented its work with another electrical subcontractor and back-charged the subcontractor for such costs.

 

Due to the supplementation, the prime contractor paid the supplemental electrical subcontractor in excess of the defaulted subcontractor’s contract balance.  The prime contractor also had to pay the defaulted subcontractor’s lower tiered subcontractors and suppliers because the defaulted subcontractor did not pay them (likely because it did not have the cash flow due to the prime contractor withholding contract balance). 

 

The trial court entered judgment in favor of the prime contractor against the subcontractor finding that the prime contractor was justified supplementing the subcontractor in accordance with the numerous contractual provisions.  The prime contractor put on evidence at trial supporting the justification in conjunction with its rights under the prime contract. 

 

Of importance, the trial court was not going to rewrite the subcontract or the risks the subcontractor assumed in the subcontract:

 

Contracts are voluntary undertakings, and contracting parties are free to bargain for-and specify-the terms and conditions of their agreement.  That freedom is a constitutionally protected right.

***

Thus, [i]t is not the function of the courts to rewrite a contract or interfere with the freedom of contract or substitute their judgment for that of the parties thereto in order to relieve one of the parties from the apparent hardship of an improvident bargain.

***

Rather, the court’s task is to apply the parties’ contract as-written, not rewrite it under the guise of judicial construction.

 

MWH Constructors, Inc., 2018 WL at *6 (internal citations and quotations omitted).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

HURDLES WITH TRIGGERING A SUBCONTRACTOR PERFORMANCE BOND

shutterstock_523359034There have been a couple of decisions as of late, particularly in federal court, that have gone in favor of a performance bond surety and against a general contractor’s claim against a subcontractor’s performance bond.   These decisions have been so unfavorable that they may be swaying certain internal decisions to move to subcontractor default insurance with, perhaps, subcontractors that pose less risk.    From the general contractor’s perspective, if they have to stop the management of the job and progress to jump through hoops to trigger the performance bond’s obligations, rightfully or wrongfully, the bond may not provide them the value they need.  Performance bonds are an appropriate product in many instances, but there should be more consistency regarding the actual trigger of a subcontractor’s performance bond obligations.  Project teams need to absolutely understand what efforts they need to take, and how they need to take such efforts, in order to properly trigger a performance bond’s obligations.  This is a must (and I have presented many seminars on this very issue).  Or, the general contractor should move away from the traditional AIA /standard performance bond form, which is the direction I always go when I am involved in the drafting of a performance bond.

 

To discuss the consternation with triggering subcontractor performance bond obligations, one just has to look at the recent decision in International Fidelity Ins. Co. v. Americabe-Moriarty JV, 2017 WL 766912 (11th Cir. 2017).   This appellate decision dealt with the fundamental issue of whether the contractor properly triggered a subcontractor’s performance bond.  The appellate court found that it did not.  This meant that the general contractor breached the terms of the performance bond, discharging the bond’s obligations, and the surety was off the hook for any subcontractor default.   This is clearly not what the general contractor intended when it wanted its subcontractor to be bonded. 

 

In this case, the subcontract provided that if the subcontractor failed to cure a default after a three-day notice to cure period, the general contractor was at liberty to terminate the subcontract upon an additional three day notice to the subcontractor, which it could  then take possession of materials and employ others to complete the work.

 

The performance bond incorporated the subcontract.  (Every performance bond will incorporate the applicable contract.)  The performance bond further contained the following routine language applicable to standard-form bonds:

 

§ 3 If there is no Owner Default under the Construction Contract, the Surety’s obligation under this Bond shall arise after

.1 the Owner first provides notice to the Contractor and the Surety that the Owner is considering declaring a Contractor Default. Such notice shall indicate whether the Owner is requesting a conference among the Owner, Contractor and Surety to discuss the Contractor’s performance….

.2 the Owner declares a Contractor Default, terminates the Construction Contract and notifies the Surety; and

.3 the Owner has agreed to pay the Balance of the Contract Price in accordance with the terms of the Construction Contract to the Surety or to a contractor selected to perform the Construction Contract.

§ 5 When the Owner has satisfied the conditions of Section 3, the Surety shall promptly and at the Surety’s expense take one of the following actions:

§ 5.1 Arrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract;

§ 5.2 Undertake to perform and complete the Construction Contract itself, through its agents or independent contractors;

§ 5.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract …; or

§ 5.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:

.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, make payment to the Owner; or

.2 Deny liability in whole or in part and notify the Owner, citing the reasons for denial.

§ 6 If the Surety does not proceed as provided in Section 5 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond, and the Owner shall be entitled to enforce any remedy available to the Owner.

 

On August 17, 2015, the general contractor issued a notice of default to the subcontractor and surety.  This was sent per the subcontract and section 3 of the bond.  On August 20, 2015, the surety responded that it needed more information and directed the contractor not to take any steps without the written consent of the surety.  A conference call was held on September 2, 2015.  Thereafter, on September 21, 2015, the contractor sent the subcontractor and surety a letter terminating the subcontractor and notifying the surety that it will pay the surety the balance of the subcontract amount consistent with section 3 of the bond.  On October 1, 2015, the contractor sent the surety the additional notice required by section 6 of the bond, which started the 7-day clock. 

 

However—and this is a HUGE however per the court—on September 16, 2015 the contractor got a cost proposal from a completion subcontractor relating to completing the defaulted subcontractor’s scope.  The completion subcontractor sent a schedule reflecting a start state of September 21, 2015.  By September 23, 2015, the completion subcontractor had begun certain work at the project.

 

Thus, after the surety got the October 1, 2015 letter, it sent the contractor a letter on October 8, 2015 advising the contractor that its actions engaging a completion subcontractor discharged its obligations on the bond.  The contractor responded that the surety was in default of the bond by not acting with reasonable promptness per section 5 of the bond.    This lawsuit was then initiated. 

 

As mentioned, the Eleventh Circuit held that the contractor breached the terms of the performance bond discharging the surety’s obligations under the bond.  In other words, the performance bond was never properly triggered: 

 

Here, both the bond and subcontract required Americaribe [contractor] to provide notice to Fidelity [performance bond surety] when terminating CPM [subcontractor]. Americaribe did provide notice on September 21. However, the subcontract required the contractor give three-days notice before undertaking to complete the work. And the bond gave Fidelity time to choose among four options for undertaking the work itself, after Americaribe sent the termination notice. This undefined period of time was then followed by another requirement for Americaribe to provide seven-days notice before Fidelity would be in default. Neither the bond nor the contract allowed Americaribe to immediately hire Dillon to complete the work.

 ***

Before Americaribe sent the termination notice on September 21, Dillon [completion subcontractor] had already sent Americaribe a proposal for completing the work remaining on the subcontract, as well as a schedule with a presumed start date of September 21. Then, on September 22, Americaribe sent vendors of CPM a letter, copying Fidelity, informing them of CPM’s termination and that “[Americaribe] intends to award the subcontract to complete the remaining work … to Dillon.” As of September 23, Dillon had commenced some work required for the project. Thus, the question is whether these actions breached the notice provisions of the bond and subcontract.

***

Americaribe did not comply with the subcontract’s three-day notice requirement. It had already hired Dillon, which began remedying the defaulted work during that three-day period. Neither did Americaribe comply with the bond’s requirements, which expressly afforded Fidelity time to elect among options for completing the defaulted work. Americaribe’s immediate hiring of Dillon to complete the project and the costs Dillon incurred completing CPM’s work thwarted Fidelity’s ability to choose among the options it had for remedying CPM’s default under § 5 of the bond. Therefore, Fidelity is not liable on the bond.

 

This is a very, very harsh outcome.   Although I mentioned this above, it is imperative that the project team understand the steps it needs to take to properly default a subcontractor and trigger the subcontractor’s performance bond.  Not doing so will render the value of the performance bond useless to the general contractor that is relying on the security of that bond.  

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.