EXAMPLES OF (RISK SHIFTING & ACCEPTING) PROVISIONS IN A SUBCONTRACT


In reading articles posted in this blog, I hope it is impressed upon you to understand the risks you are accepting in your contract and what to do if you encounter a risk, as well as those risks you are flowing down or allocating to your subcontractors.   Construction is inherently risky so you want to know what to do when you encounter certain situations or occurrences, and in certain circumstances, you want to factor the costs associated with certain accepted risks in your contract amount. 

 

When it comes to subcontracts, there are provisions that contractors want to include in their subcontracts that subcontractors need to note:

  1. The schedule – the contractor will want to include provisions that any baseline schedule is not written in stone and that it has the discretion to resequence the progress of the work.  This is an understood event since the contractor is responsible for managing the work so subcontractors should account for this contingency.
  2. No damage for delay – the contractor will want to include a no-damage-for-delay provision that provides it is not responsible for any delay-related damages and that the subcontractor’s only recourse for a delay will be an extension of time.  The provision may also state that the contractor’s liability for any delay will be limited by the amount it receives by the owner associated with the delay.
  3. Change orders – There will be a change order issue at some point.  The subcontractor needs to understand the change order procedure so proper notice is given regarding the change order work before proceeding with that work.  And, if the subcontractor is directed to proceed with work (through a change order directive) or there is a dispute as to the amount or time associated with the change, the subcontractor needs to understand that it needs to track and itemize its costs associated with the change.
  4. Claims – If a subcontractor is delayed / impacted or there is an event triggering change order work, as mentioned above, the subcontractor needs to submit timely notice of the event or occurrence.  Otherwise, there may be an argument that this event or occurrence is waived.  The contractor will argue that the notice provision is important so that it can ensure it timely submits notice to the owner pursuant to the prime contract and a subcontractor’s failure to comply with the notice provision prejudiced the contractor.

Provided below is an example of contractual provisions that fit within the above four categories.  These provisions may be analogous to provisions in the subcontract you are working under or, if you are a general contractor, may be provisions you want to consider including in your subcontract.  Remember, the objective is to know those risks you are accepting, those risks to flow down or allocate to the subcontractor, and, importantly, what to do if you encounter a risk!!

Also, please share any examples of contractual provisions that you have come across that fit within these categories. The more examples the merrier when it comes to understanding the types of risks that are frequently dealt with and allocated between a contractor and subcontractor.

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2015/08/Copy-of-subk-contract-considerations.pdf”] 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

CHALLENGES OF AN ORAL CONTRACT OR THE “HANDSHAKE DEAL”


An oral contract is a contract that is not reduced to writing.  In certain circumstances, and every disputed circumstance involving an oral contract, it becomes a “he said, she said” as to whether a contract was created and what the terms of the contract entailed.  This is why it is always good practice to memorialize contractual terms in writing instead of accepting the “handshake deal” as the manner in which to do business.

 

Also, with oral contracts, the party being sued may argue that the statute of frauds bars the enforcement of the oral contract.  The statute of frauds is a legal doctrine that states that an oral contract is unenforceable if it is not performed (or cannot be performed) within one year of the contract’s makingSee Fla. Stat. s. 725.01.    The statute of frauds does not apply if the oral contract is capable of being performed or accomplished within one year of the contract’s making.  However, if there is a lawsuit concerning an oral contract, there is a strong chance that the defendant (or party the contract is being enforced against) will assert the statute of frauds as an affirmative defense.

 

The case of Loper v. Weather Shield Manufacturing, Inc., 40 Fla. L. Weekly D1492a (1st DCA 2015) illustrates an oral contract scenario.

 

In this case, a house was constructed facing the ocean in 2001-2002.  The house was constructed with large double-paned windows that came with a 10-year warranty.  The owner noticed water intrusion started to occur between the panes of glass and windows began to develop a fogging affect.  The contractor tried to correct the issue to no avail.  In 2005, a representative from the window manufacturer inspected the windows and some of the windows were replaced.  However, the water intrusion and window-fogging issues continued.  In 2010, a meeting was conducted with the owner, window manufacturer, window installer, and contractor. During the meeting, the owner separately spoke with the representative from the window manufacturer.   The representative explained that if the owner had a lawyer he was not going to be able to help the owner to which the owner replied he did not have a lawyer but plans to seek legal action if the problem does not get resolved.  The owner stated that he wanted the defective windows replaced and wanted a new 10-year warranty (the original warranty was set to expire at the end of 2011).  The representative responded that he would relay the request to his bosses;  he subsequently contacted the owner to confirm there was a deal.  The owner asked for the terms to be put in writing and the representative said his company’s legal department would prepare the agreement.

 

The owner never heard back from the representative.  After calling many, many times, he discovered that the representative had been laid off.  The owner then spoke with another representative that told the owner that he approved the deal and he would check on the status of the settlement agreement with his company’s legal department and get back to the owner.  Of course, this did not occur.  The owner followed-up with this representative and never received a call back.

 

By August 2011, and with the original warranty set to expire, the owner was still following-up with the manufacturer to reach a longstanding resolution to his window issues. Finally, approximately a month before the owner’s original 10-year warranty was set to expire, the owner received an e-mail from the manufacturer saying it will not extend the 10-year warranty and, thus, was reneging on the terms of the oral agreement between the parties. 

 

The owner filed a lawsuit against the manufacturer claiming that the manufacturer breached an oral contract where windows would be replaced and a new 10-year warranty furnished.

 

After a jury trial, the jury returned a verdict in favor of the owner finding that there was an oral contract.  However, the judge directed judgment in favor of the window manufacturer finding (1) there was insufficient consideration for the oral agreement between the owner and manufacturer and (2) even if there was consideration, the statute of frauds barred the enforcement of the oral contract because the contract required a new warranty that extended beyond one-year.

 

On appeal, the First District Court of Appeal reversed directing entry of judgment in favor of the owner on the breach of oral contract claim consistent with the jury’s verdict. 

 

Regarding the trial court’s finding of insufficient consideration, the Court held that the owner’s forbearance from pursing legal rights, specifically in the context of an expiring 10-year warranty and a manufacturer’s overt run-around, was sufficient consideration.  (“Viewed in a light favorable to Dr. Loper [owner], the parties had a deal that could be readily and promptly effectuated, but which languished — not due to Dr. Loper’s actions — but because of dawdling by Weather Shield [manufacturer]. The jury specifically answered ‘yes’ to the question of whether Dr. Loper ‘reasonably rel[ied] in good faith on Weather Shield Manufacturing, Inc., to reduce this oral agreement to writing,’ and could have readily concluded that the time period of Dr. Loper’s forbearance was expected to be brief, but ultimately was prolonged due to Weather Shield’s dithering….” Loper, supra.) 

 

Regarding the trial court’s finding that the statute of frauds barred the enforcement of the oral contract, the Court held that the statue of frauds makes an oral contract unenforceable if it cannot be performed within one year of the contract’s making.   But, if the oral contract is capable of performance within one year, it is enforceable.  Here, the trial court focused on the fact that the contract could not be performed within one year because it contemplated a ten-year warranty (extending beyond one year).  But, the issuance of the warranty could have been accomplished within one year and the issuance of the warranty, and not the length of the warranty, is what the trial court should have focused on. (“The record evidence supports the conclusion that Dr. Loper [owner] and Weather Shield [manufacturer] both intended that their oral agreement be effectuated promptly; no evidence supports that they intended that the issuance of the warranty was intended or required to occur beyond a year’s time. Because issuance of replacement policy could have, indeed should have, occurred in less than a year, the statute of frauds issue is inapplicable.”  Loper, supra.)

 

Take-Aways

  • Although the owner prevailed on his breach of oral contract claim, it is always good to reduce the terms of an agreement (any agreement) to writing. The owner prevailed because he was probably a good witness that told a persuasive story to the jury that the jury found to be credible.  It is the owner’s story of events the Court focused on since the owner received a jury verdict in his favor (and was the party appealing).   Hence, having a credible, persuasive witness always helps!
  • Here, the owner’s counsel was creative.  The owner’s counsel knew the owner could not sue the contractor or even the window installer because the statute of limitations expired.  But, there was a colorable claim that could be asserted against the window manufacturer based on the outcome of a meeting that took place involving the owner and manufacturer.  While this oral contract claim is certainly a difficult and probably expensive claim to prove, the owner prevailed on this claim (although, it is uncertain as to what expense meaning did the owner recover more than he incurred in legal fees and/or did he create an argument to recover attorney’s fees by serving a proposal for settlement).
  • It is uncertain why it took the owner so long to retain counsel to deal with a persistent water intrusion and window-fogging problem.  The owner should have retained counsel earlier to best preserve his rights.  Although the owner was able to show that his wiliness not to retain counsel supported the consideration for the oral contract, forbearance from pursuing legal rights should not come across as unreasonably indefinite or illusory.  Here, the Court found that the forbearance was intended to be brief but was simply extended based on the run-around given by the manufacturer up until the point that the manufacturer knew the original warranty was expiring.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

RESIDENTIAL CONSTRUCTION – SHOULD BOTH HUSBAND & WIFE SIGN THE CONTRACT?


It is always good practice for residential contractors to get both husband and wife to sign the residential construction contract.   But, even if only one spouse signs the contract, Florida’s Lien Law doesn’t really punish the contractor when its comes to construction liens.

 

Florida Statute s. 713.12 provides:

 

When the contract for improving real property is made with a husband or wife who is not separated and living apart from his or her spouse and the property is owned by the other or by both, the spouse who contracts shall be deemed to be the agent of the other to the extent of subjecting the right, title, or interest of the other in said property to liens under this part unless such other shall, within 10 days after learning of such contract, give the contractor and record in the clerk’s office, notice of his or her objection thereto.

 

In other words, one spouse is deemed the agent of the other spouse when it comes to subjecting the other to construction liens.  This makes sense because generally when one spouse signs a contract for construction at his/her property, the other spouse has knowledge and is on board of the construction project.   But, assuming the other spouse wasn’t aware, Florida’s Lien Law allows that spouse to provide the contractor an objection to the contract and record that objection in the public records in order for any construction lien not to impact that spouse’s interest in the property.

 

However, the statute only applies to real property and doesn’t apply to personal liability relating to the non-signing spouse.  See Mullne v. Sea-Tech Const. Inc., 84 So.3d 1247, 1249 (Fla. 4th DCA 2012); Meadows Southern Const. Co. v. Pezzaniti, 108 So.2d 499, 502 (Fla. 2d DCA 1959).  This is why it is good practice for the contractor to get both spouses so sign the contract because while the contractor may be able to lien the non-signing spouse’s interest, that will be about it because it will not be able to impose personal liability against the non-signing spouse.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

THE VALUE OF A WELL-WRITTEN SUBCONTRACT TO FORECLOSE SUBCONTRACTOR’S INEFFICIENCY / LOST PRODUCTIVITY DAMAGES


I have previously discussed the challenges a subcontractor has in proving a lost productivity / inefficiency claim.  Besides being difficult to prove, subcontractors generally enter into subcontracts that include onerous provisions that foreclose a subcontractor’s right to pursue lost productivity / inefficiency claims.   General contractors try to account for these types of delay-related claims by including provisions in their subcontracts that require subcontractors to fully bear this risk.  An example of this ocurrence can be found in the opinion entered in Electrical Contractors, Inc. v.  Fidelity & Deposit Co. of Maryland, 2015 WL 1444481 (D. Con. 2015) where the trial court precluded a subcontractor from recovering lost productivity / inefficiency costs based on the language in the subcontract that precluded such claims. Additionally, and importantly, the trial court found that that the subcontractor failed to timely notify the general contractor of its claims under the strict notice provisions of the subcontract.

 

In this case, the general contractor was hired by a state agency to construct a laboratory building and furnished the state a public payment bond.  The prime contract contained a construction schedule (which is not an uncommon exhibit in a prime contract).  The general contractor then entered into subcontracts with trade subcontractors including the electrical subcontractor.  An exhibit to the electrical subcontract was a schedule that simply reproduced dates applicable to the electrical subcontractor’s scope of work that were included in the construction schedule attached to the prime contract.

 

No different than any baseline construction schedule on any construction project, it was not written in stone. This meant there were updates to the schedule that were furnished to the state agency and the state agency unsurprisingly challenged or opposed numerous schedule updates. The general contractor did not keep its electrical subcontractor apprised of the back-and-forth between it and the state agency involving schedule updates (nor was the general contractor under any real obligation to do so).

And, as we all know, the schedule of the project is really driven in the field.  So, as the construction progressed, the general contractor’s superintendents directed the electrical subcontractor to perform work in a piecemeal and unsystematic manner. This was due to work areas not being ready for the electrical scope due to delays on the project.  The electrical subcontractor notified the general contractor that it was being impacted and forced to work unproductively. Thereafter, the electrical subcontractor sued the general contractor and the general contractor’s payment bond sureties for damages that included lost productivity / inefficiency damages. 

However, the subcontract that the electrical subcontractor signed posed problems with its claims, particularly the following contractual provisions:

 

“Subcontractor agrees to … complete the work in such sequence and order and according to such schedules as Contractor shall establish from time to time … time being of the essence…. If Contractor determines that the Subcontractor is behind schedule or will not be able to maintain the schedule, Subcontractor … shall work overtime, shift work, or work in an altered sequence, if deemed necessary, in the judgment of the Contractor to maintain the progress of the work. Any such … altered sequence work required to maintain progress or to complete the work on a timely basis shall be at Subcontractor’s expense and shall not entitle Subcontractor to … additional compensation.”

***

“To the fullest extent permitted by applicable law, Contractor shall have the right at any time to delay or suspend the work or any part thereof without incurring liability therefore. An extension of time shall be the sole and exclusive remedy of Subcontractor for any delays or suspensions suffered by Subcontractorand Subcontractor shall have no right to seek or recover from Contractor any damages or losses, whether direct or indirect, arising from or related to any delay or acceleration to overcome delay, and/or any impact or effect of such delays on the Work.”

***

“In the interest of the overall project, W–T [Contractor] reserves the right to alter the sequencing of activities in order to accommodate project conditions and/or Owner requirements. It is understood that the Subcontractor shall be obligated to complete its activities [timely] … regardless of the actual start date.”

***

There is no guarantee of continuous work. Subcontractor shall work in all areas as they become available and as directed by Whiting–Turner [Contractor]. Subcontractor shall include the inefficiencies, supervision and manpower necessary to run separate and independent crews as necessary.”

Electrical Contractors, Inc., supra, at *6 and *7.

 

Additionally, the electrical subcontractor needed to timely notify the general contractor of its claims:

“Article 6(d) requires timely written notice as a precondition for making such claims: [N]otice in writing shall be given to the Contractor no later than seven (7) days following the occurrence on which such claim is based…. Any claim not presented within such time period shall be deemed waived by Subcontractor. The notice must describe the dispute, controversy or claim in detail so as to allow Contractor to review its merits … [and] provide detailed information to substantiate such claim including supporting documentation and calculations.”

Electrical Contractors, Inc., supra, at *8 (internal citations omitted).

 

While the 7-day claim notice requirement may seem unfair, the court explained that the electrical contractor was a sophisticated entity that knowingly assumed this notice obligation.

Of Significance: 

These subcontract provisions recited above are not uncommon provisions.  They are rather commonplace with sophisticated contractors–there is no real shock value when looking at these provisions, right?

 

If you are a general contractor that includes such provisions in your subcontracts, this case gives you reassurance as to those contractual provisions that are aimed to insulate you from a subcontractor’s delay-related damage and require the subcontractor to give you timely notification of a claim (so that you are not prejudiced by the late submission of a subcontractor claim).  These are important provisions for a general contractor to include in a subcontract and the provisions referenced above are certainly well-written provisions to model.  It is understood that a schedule is never going to be written in stone and there will be logic and sequence changes in the schedule, so protect yourself by including such provisions (including the no-damage-for-delay provision). As you can see, there is value in doing so.

 

On the other hand, if you are a subcontractor, if you accept these provisions, you need to either account for these risks in your subcontract price and/or bear the risk that these provisions may be appropriately enforced against you as shown in this case.  Alternatively, and as the court alluded to, as a sophisticated party, you have the option of not signing the subcontract or trying to negotiate the best subcontract for you with an understanding as to those onerous provisions and risks that you choose to accept.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

BECOMING A PERSONAL GUARANTOR BY EXECUTING THE PERSONAL GUARANTEE


Suppliers are not ill advised.  When they have a contractor execute a credit application so the contractor can procure materials on credit, they generally include a personal guarantee in the credit application.  This way they have both the company that ordered the materials and the personal guarantor jointly and severally liable in the event they are not paid for the materials.  Suppliers want this personal guarantee as added security because they oftentimes supply materials on credit (to a job site) through an ongoing account so that their contractor customer can have the materials ordered to perform a scope of work.

 

Personal guarantors sometimes try to be clever with the way they sign the personal guarantee in order to avoid any personal liability through the personal guarantee.  But, not so fast…“Florida law is clear that an individual who executes a guarantee as an officer of a corporation by inserting his corporate title after his name on a document cannot defeat the purpose of the guarantee when, by its terms, the document contains provisions for individual liability.” Great Lakes Products, Inc. v. Wojciechowski, 878 So.2d 418, 419 (Fla. 3d DCA 2004); see also Nelson v. Ameriquest Technologies, Inc., 739 So.2d 161, 164 (Fla. 3d DCA 1999) (“The fact that Nelson added the letters “V.P.” after his signature could not defeat the obvious and clear purpose of the guaranty agreement; that is, to impose individual liability upon him as the signor.”).

 

When signing a personal guarantee, make sure you understand its implications, particularly that of personal liability in the event the company does not pay or otherwise honor the terms of the agreement. You are agreeing to become jointly and severally liable with the company to pay for any potential outstanding debt. 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONFLICT BETWEEN A SUBCONTRACTOR’S MILLER ACT PAYMENT BOND CLAIM AND A PRIME CONTRACTOR’S CONTRACT DISPUTES ACT CLAIM


The recent opinion in U.S. f/u/b/o Marenalley Construction, LLC v. Zurich American Insurance Co., 2015 WL 1137053 (E.D.Pa. 2015) is a great example as to what could happen when a prime contractor submits a Contract Disputes Act claim to the federal government that includes subcontractor amounts and then a subcontractor simultaneously pursues the same amounts from the prime contractor’s Miller Act payment bond surety. The question becomes should the subcontractor’s lawsuit against the Miller Act payment surety be dismissed or stayed pending the outcome of the resolution of the prime contractor’s Contract Disputes Act claim.  The ruling in this case held that the subcontractor’s Miller Act claim could proceed, and would not be dismissed or stayed, pending the outcome of the prime contractor’s Contract Disputes Act claim.  This was a great ruling for the subcontractor and obviously puts the prime contractor in an uncomfortable position, to say the least, since it becomes hard to dispute a subcontractor’s claim when the merits of that claim have been packaged (or passed through) to the federal government in a certified Contract Disputes Act claim.

In this case, both the prime contractor and subcontractor agreed that the United States Department of Veterans Affairs (VA) caused additional work that increased the cost of the work.  As a result, the prime contractor submitted a Contract Disputes Act claim to the VA that included claims and amounts from subcontractors.  While the prime contractor’s claim was pending with the VA, a subcontractor sued the prime contractor’s Miller Act payment bond surety. This was a subcontractor that also had its claims and amounts packaged (or passed through) to the VA in the prime contractor’s Contract Disputes Act claim.

The prime contractor argued that the subcontractor’s Miller Act payment bond claim should be dismissed or stayed pending the resolution of the Contract Disputes Act claim.  In particular, the prime contractor argued that because the subcontract incorporated a dispute resolution clause (that incorporated the requirements of the Contract Disputes Act), the subcontractor was required to exhaust this administrative process before proceeding with a Miller Act payment bond claim.

Dismissal of  Miller Act Payment Bond Claim?

The ruling to deny the prime contractor and surety’s motion to dismiss the Miller Act payment bond claim was an easy decision.  To begin with, a Miller Act payment bond claim needs to be instituted within a year from the subcontractor’s last furnishing so if the court dismissed the claim it would potentially be depriving the subcontractor of its rights under the law without any certainty as to if the subcontractor re-filed the lawsuit it would be within the statute of limitations or the statute of limitations would otherwise be tolled.  And, pursuant to the Miller Act, a subcontractor cannot contractually agree to waive its Miller Act rights before the subcontractor performed any work.  A waiver of Miller Act payment bond rights is only enforceable if the waiver is: 1) in writing, 2) signed by the party waiving its payment bond rights, and 3) “executed after the person whose right is waived has furnished labor or material for use in the performance of the contract.  See 40 U.S.C. s. 3133.

Stay of Miller Act Payment Bond Claim?

The real determination was whether the subcontractor’s Miller Act payment bond lawsuit should be stayed until the completion of the prime contractor’s dispute resolution with the VA. The court held No!:

 

“The Miller Act entitles Marenalley [subcontractor] to bring suit ninety days after the completion of its work…not when and if Nason [prime contractor] recovers from the VA. Conditioning Marenalley’s right to recover from the [Miller Act] Payment Bond on the completion of Nason’s CDA [Contract Disputes Act] process would be inconsistent with the terms of the Miller Act.

***

Nason and Zurich [surety] protest that they will be prejudiced in the absence of a stay due to the costs of dual litigation and the risk of inconsistent decisions.  The Court is not overly troubled by these arguments.  Ordinarily the fact that a prime contractor has a claim for the same amount pending under the disputes clause of the [incorporated] prime contract, does not affect Miller Act cases.

***

The CDA process will determine the VA’s liability to Nason.  The VA, however, has no jurisdiction over the amount that Nason must pay Marenalley and no interest in how that amount is determined. Thus, a stay would subject Marenalley to a substantial, indefinite delay as Nason’s claim passes through the administrative process and court review, only to be left at the end of that process to begin again here to litigate its rights against Nason.”

 

Marenalley, supra, at *6 (internal citations and quotations omitted).

How Does a Prime Contractor Account for this Risk?

So, based on this ruling, how does a prime contractor account for this business risk? And, this is a business risk because there may be value to a subcontractor to pursue the Miller Act payment bond claim rather than wait an indefinite period of time for the Contract Disputes Act process to resolve itself and then hope that the prime contractor pays the subcontractor the portion of the subcontractor’s claim that was passed through to the federal government.

 

Well, there is authority that would entitle the prime contractor to a stay of a subcontractor’s Miller Act payment bond lawsuit.  But, this authority is predicated on language in the subcontract that any action filed by the subcontractor will be stayed pending the exhaustion of administrative remedies.

 

For example, in U.S. f/u/b/o Trans Coastal Roofing Co. v. David Boland, Inc., 922 F.Supp. 597, 598 (S.D.Fla. 1996), the subcontract contained the following language:

 

“[s]ubcontractor shall first pursue and fully exhaust [the procedures set forth in the standard disputes clause of the primary contract] before commencing any other action against Contractor for any claims it may have arising out of its performance of the Work herein.”

***

“[Contractor shall] prosecute all claims submitted by Subcontractor under the contractual remedial procedure of the Prime Contract on behalf of and to the extent required by the Subcontractor.”

***

 “[Subcontractor] agree[d] to stay an action or claim against [the prime contractor’s Miller Act bond] pending the complete and final resolution of the Prime Contract’s contractual remedial procedure.”

 

Because the subcontractor failed to exhaust its administrative remedies, the court dismissed the subcontractor’s Miller Act payment bond claim.  Importantly, this case was decided before there were amendments to the Miller Act that now prevents a subcontractor from waiving a Miller Act payment bond claim prior to performing work.  Thus, if this case were decided today, the court likely would have stayed the Miller Act payment bond claim instead of dismissing it unless, of course, it was clear that the statute of limitations for pursuing a Miller Act payment bond claim would be tolled pending the exhaustion of the administrative remedies.

 

Similarly, in U.S. v. Dick/Morganti, 2007 WL 3231717 (N.D.Cal. 2007), the prime contractor and surety moved to stay a subcontractor’s payment bond claim based on the following subcontract language:

 

“If the Owner [GSA] and the Contractor [Dick/Morganti], pursuant to the General Contract or by agreement, submit any dispute, controversy, or claim between them to arbitration or some other dispute resolution procedure specified in the General Contract and such a matter involves or relates to a dispute, controversy, or claim between the Contractor and the Subcontractor, Subcontractor agrees …to stay any action filed by the Subcontractor until the dispute resolution and appeals process between the Contractor and the Owner is exhausted.”

 

The prime contractor argued it “intended” to submit a claim to the federal government [GSA] that will include the subcontractor’s amounts and, as such, the provision should operate to stay the subcontractor’s Miller Act payment bond claim.  The court agreed provided that the prime contractor did actually submit the claim.

 

Thus, a prime contractor should absolutely incorporate language in a subcontract consistent with the language in these decisions that reflects that any action filed by the subcontractor, including an action against the prime contractor’s Miller Act payment bond surety, will be stayed pending the complete resolution of any dispute resolution between the prime contractor and federal government that involves or includes the claims and amounts sought by the subcontractor. 

 

And a subcontractor, even if this language is included in the subcontract, should still move forward and timely file any Miller Act payment bond lawsuit.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

WAIVER OF CONSEQUENTIAL DAMAGES AND LOSS OF USE DAMAGES (IN CONSTRUCTION / DESIGN DEFECT DISPUTE)


In construction / design defect cases, a plaintiff (party proving defect) may assert a category of damages referred to as loss of use damages.  Importantly, if your contract includes a waiver of consequential damages, these types of damages will not be recoverable.  This is a significant issue to consider when entering into a construction contract, especially when you are the owner of the project, because if you do not want to waive a party you hire of consequential damages (such as loss of use damages), then you do not want to include a waiver of consequential damages in your contract or, at a minimum, you want to carve out exceptions to the waiver of consequential damages.  Stated differently, this is an issue and risk you want to consider on the front end because even though construction / design defects are not anticipated, they do occur.

 

In a construction / design defect scenario, an owner’s consequential damages would generally be those damages unrelated to repairing the defect.  For instance, loss of use of the property or lost rental income to an owner during the implementation of the repairs would be a consequential damage that would be waived by a waiver of consequential damages provision in an owner’s contract.

 

An example of a waiver of consequential damages provision found in the AIA A201 (general conditions of the construction contract between an owner and contractor) is as follows:

 

The Contractor and Owner waive Claims against each other for consequential damages arising out of or relating to this Contract. This mutual waiver includes

.1  damages incurred by the Owner for rental expenses, for losses of use, income, profit, financing, business and reputation, and for loss of management or employee productivity or of the services of such persons; and

.2  damages incurred by the Contractor for principal office expenses including the compensation of personnel stationed there, for losses of financing, business and reputation, and for loss of profit except anticipated profit arising directly from the Work.

This mutual waiver is applicable, without limitation, to all consequential damages due to either party’s termination in accordance with Article 14. Nothing contained in this Section 15.1.6 shall be deemed to preclude an award of liquidated damages, when applicable, in accordance with the requirements of the Contract Documents.

(See AIA A201-2007, s. 15.1.6)

 

Now, if loss of use damages are not contractually waived, the recent decision in Gonzalez v. Barrenechea, 40 Fla. L. Weekly D258a (Fla. 3d DCA 2015), illustrates how an owner can recover these types of damages when there is a construction / design defect.  In this case, an owner sued its architect for design errors with the HVAC system in a newly constructed home.  The owner was forced to engage a new design professional to address the deficiencies.  It took the owner 20 months to repair the deficiencies during which the owner claimed he could not live (or use) his new house.  Although the owner did not live in the house, there was evidence that the owner had some use of the house.  For instance, the owner’s son slept in the house on an intermittent basis, the owner docked his boat at the dock behind the house, furniture was stored in the house, and the owner had cars parked in the garage.

 

Notwithstanding some use of the house, the owner put on testimony of an expert real estate appraiser that testified that the owner incurred lost rental value of approximately $15,500 per month during the 20-month repair period.  The architect argued that this rate was flawed because the expert failed to factor in the use the owner had of the house during the 20-month period.  The trial court agreed and denied the owner the loss of use damages.

 

The Third District Court reversed the trial court finding that the owner was entitled to loss of use damages:

 

Under Florida law, a homeowner that loses the use of a structure because of delay in its completion is entitled to damages for that lost use. Florida courts have held that “[d]amages for delay in construction are measured by the rental value of the building under construction during the period of delay.”

Gonzalez, supra, quoting Fisher Island Holdings, LLC v. Cohen, 983 So.2d 1203, 1204 (Fla. 3d DCA 2008).

 

Furthermore, because the architect failed to put on any evidence as to what the rental value of the house should have been during the 20-month period factoring in the owner’s use of the house during this period, there was nothing to refute the owner’s rental rate.

 

This case touches upon important take-aways:

 

  • Consider the risk of a waiver of consequential damages provision on the front end, especially if you are an owner.  Likewise, if you are a contractor or design professional, you want to consider the risk of not having such a waiver of consequential damages.
  • Loss of use damages are recoverable in a construction / design defect case absent a contractual waiver of consequential damages.
  • An owner can introduce evidence of loss of use damages through an expert real estate appraiser that can testify as to the rental rate of the property during the repair period.
  • A contractor or design professional defending a loss of use damages claim should engage its own expert to counter an owner’s expert.  In this case, if the design professional had an expert real estate appraiser, it would have put on evidence of a rental rate much lower than the $15,500 per month factoring in the owner’s limited use of the house during this time period.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

VALIDITY OF NON-COMPETE AGREEMENTS


The validity of a non-compete agreement (also referred to as a restrictive covenant since it imposes a restriction on trade or commerce) will be governed by Florida Statute s. 542.335.  (A copy of this statute is set forth below).  Written and signed non-compete agreements or clauses are presumptively valid if they are reasonable in time (the non-compete time period), area (geographic limitation), and line of business; these clauses cannot be overbroad.

 

Even if the non-compete agreement is in writing and signed by the employee, it still needs to be supported by a proven legitimate business interest justifying its enforcement (e.g., learning of trade secrets or confidential business information, relationships with customers or clients, customer or client goodwill associated with the business). Stated differently, the employer seeking to enforce the non-compete agreement against a former employee still needs to establish that the enforcement of the non-compete is reasonably necessary to protect its legitimate business interests.

 

To enforce non-compete agreements, a party (typically, the former employer) moves for injunctive relief.

 

The case of Ankarli Boutique, Inc. v. Ortiz, 2014 WL 6674727 (4th DCA 2014) held that a two-year non-compete agreement, to the extent valid, applied from the time the former employee left the company.  The case also maintained that the non-compete period could not be “nullified because the non-compete period was devoured by the time it took to appeal an erroneous ruling on the interpretation of the [non-compete] clause.Ankarli Boutique, supra, at *1.   In other words, if there is a delay in entering a ruling (i.e., an injunction) enforcing the non-compete clause, or the non-compete time period is consumed during the pendency of an appeal, the employer or party enforcing the clause is still entitled to reap the benefit of a valid non-compete clause.  Thus, any delay tactic by litigating the issue or appealing the issue should not nullify an otherwise valid non-compete clause.

 

 Florida Statute s. 542.335

(1) Notwithstanding s. 542.18 and subsection (2), enforcement of contracts that restrict or prohibit competition during or after the term of restrictive covenants, so long as such contracts are reasonable in time, area, and line of business, is not prohibited. In any action concerning enforcement of a restrictive covenant:

(a) A court shall not enforce a restrictive covenant unless it is set forth in a writing signed by the person against whom enforcement is sought.

(b) The person seeking enforcement of a restrictive covenant shall plead and prove the existence of one or more legitimate business interests justifying the restrictive covenant. The term “legitimate business interest” includes, but is not limited to:

1. Trade secrets, as defined in s. 688.002(4).

2. Valuable confidential business or professional information that otherwise does not qualify as trade secrets.

3. Substantial relationships with specific prospective or existing customers, patients, or clients.

4. Customer, patient, or client goodwill associated with:

a. An ongoing business or professional practice, by way of trade name, trademark, service mark, or “trade dress”;

b. A specific geographic location; or

c. A specific marketing or trade area.

5. Extraordinary or specialized training.

Any restrictive covenant not supported by a legitimate business interest is unlawful and is void and unenforceable.

(c) A person seeking enforcement of a restrictive covenant also shall plead and prove that the contractually specified restraint is reasonably necessary to protect the legitimate business interest or interests justifying the restriction. If a person seeking enforcement of the restrictive covenant establishes prima facie that the restraint is reasonably necessary, the person opposing enforcement has the burden of establishing that the contractually specified restraint is overbroad, overlong, or otherwise not reasonably necessary to protect the established legitimate business interest or interests. If a contractually specified restraint is overbroad, overlong, or otherwise not reasonably necessary to protect the legitimate business interest or interests, a court shall modify the restraint and grant only the relief reasonably necessary to protect such interest or interests.

(d) In determining the reasonableness in time of a postterm restrictive covenant not predicated upon the protection of trade secrets, a court shall apply the following rebuttable presumptions:

1. In the case of a restrictive covenant sought to be enforced against a former employee, agent, or independent contractor, and not associated with the sale of all or a part of:

a. The assets of a business or professional practice, or

b. The shares of a corporation, or

c. A partnership interest, or

d. A limited liability company membership, or

e. An equity interest, of any other type, in a business or professional practice,

a court shall presume reasonable in time any restraint 6 months or less in duration and shall presume unreasonable in time any restraint more than 2 years in duration.

2. In the case of a restrictive covenant sought to be enforced against a former distributor, dealer, franchisee, or licensee of a trademark or service mark and not associated with the sale of all or a part of:

a. The assets of a business or professional practice, or

b. The shares of a corporation, or

c. A partnership interest, or

d. A limited liability company membership, or

e. An equity interest, of any other type, in a business or professional practice,

a court shall presume reasonable in time any restraint 1 year or less in duration and shall presume unreasonable in time any restraint more than 3 years in duration.

3. In the case of a restrictive covenant sought to be enforced against the seller of all or a part of:

a. The assets of a business or professional practice, or

b. The shares of a corporation, or

c. A partnership interest, or

d. A limited liability company membership, or

e. An equity interest, of any other type, in a business or professional practice,

a court shall presume reasonable in time any restraint 3 years or less in duration and shall presume unreasonable in time any restraint more than 7 years in duration.

(e) In determining the reasonableness in time of a postterm restrictive covenant predicated upon the protection of trade secrets, a court shall presume reasonable in time any restraint of 5 years or less and shall presume unreasonable in time any restraint of more than 10 years. All such presumptions shall be rebuttable presumptions.

(f) The court shall not refuse enforcement of a restrictive covenant on the ground that the person seeking enforcement is a third-party beneficiary of such contract or is an assignee or successor to a party to such contract, provided:

1. In the case of a third-party beneficiary, the restrictive covenant expressly identified the person as a third-party beneficiary of the contract and expressly stated that the restrictive covenant was intended for the benefit of such person.

2. In the case of an assignee or successor, the restrictive covenant expressly authorized enforcement by a party’s assignee or successor.

(g) In determining the enforceability of a restrictive covenant, a court:

1. Shall not consider any individualized economic or other hardship that might be caused to the person against whom enforcement is sought.

2. May consider as a defense the fact that the person seeking enforcement no longer continues in business in the area or line of business that is the subject of the action to enforce the restrictive covenant only if such discontinuance of business is not the result of a violation of the restriction.

3. Shall consider all other pertinent legal and equitable defenses.

4. Shall consider the effect of enforcement upon the public health, safety, and welfare.

(h) A court shall construe a restrictive covenant in favor of providing reasonable protection to all legitimate business interests established by the person seeking enforcement. A court shall not employ any rule of contract construction that requires the court to construe a restrictive covenant narrowly, against the restraint, or against the drafter of the contract.

(i) No court may refuse enforcement of an otherwise enforceable restrictive covenant on the ground that the contract violates public policy unless such public policy is articulated specifically by the court and the court finds that the specified public policy requirements substantially outweigh the need to protect the legitimate business interest or interests established by the person seeking enforcement of the restraint.

(j) A court shall enforce a restrictive covenant by any appropriate and effective remedy, including, but not limited to, temporary and permanent injunctions. The violation of an enforceable restrictive covenant creates a presumption of irreparable injury to the person seeking enforcement of a restrictive covenant. No temporary injunction shall be entered unless the person seeking enforcement of a restrictive covenant gives a proper bond, and the court shall not enforce any contractual provision waiving the requirement of an injunction bond or limiting the amount of such bond.

(k) In the absence of a contractual provision authorizing an award of attorney’s fees and costs to the prevailing party, a court may award attorney’s fees and costs to the prevailing party in any action seeking enforcement of, or challenging the enforceability of, a restrictive covenant. A court shall not enforce any contractual provision limiting the court’s authority under this section.

(2) Nothing in this section shall be construed or interpreted to legalize or make enforceable any restraint of trade or commerce otherwise illegal or unenforceable under the laws of the United States or of this state.

(3) This act shall apply prospectively, and it shall not apply in actions determining the enforceability of restrictive covenants entered into before July 1, 1996.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

A LETTER OF INTENT CAN FORM THE BASIS OF AN ENFORCEABLE CONTRACT


Just because there is not an executed subcontract, does not mean there is not an enforceable written contract between a contractor and subcontractor.   While it is good practice for there to be an executed contract in place, this does not always occur.  But, this lack of occurrence does not necessarily mean a performing subcontractor can escape contractual obligations merely because it never signed the subcontract.  Indeed, many times a subcontractor starts performing based on a letter of intent that it received from the contractor.  The letter of intent may indicate that a formal subcontract will be furnished to the subcontractor such as when the contractor is awarded the project or after the subcontractor starts performing under the letter of intent. If the subcontractor starts performing based on the letter of intent that it received, this letter of intent can certainly form the basis of an enforceable contract!

 

The decision in Sealevel Construction, Inc. v. Westcoast Corp., 2014 WL 3587264 (E.D.La. 2014) exemplifies how a letter of intent can form the basis of a written contract.  Here, a subcontractor on a federal project solicited bids from sub-subcontractors to perform aspects of its work based on the plans and specifications for the project.  The specifications, among other things, contained a liquidated damages section.  A sub-subcontractor submitted a bid to install concrete piles. The subcontractor accepted the bid and issued the sub-subcontractor a letter of intent. The letter of intent was signed by both the subcontractor and sub-subcontractor and referenced the specifications. The letter of intent further stated that a formal subcontract would be entered between the parties; however, a subcontract was never executed.

 


The sub-subcontractor started to perform its scope of piling work based on the letter of intent.  Thereafter, the subcontractor notified the sub-subcontractor of delays with the sub-subcontractor’s scope of work.  The sub-subcontractor was unable to cure the delays and the subcontractor hired another entity to supplement its sub-subcontractor’s work.  Nevertheless, as a result of delays to the sub-subcontractor’s scope of work, the government assessed liquidated damages against the prime contractor.  The prime contractor, in turn, withheld the amount of the liquidated damages from the subcontractor in addition to the prime contractor’s own extended general conditions.  The subcontractor then withheld this money from its sub-subcontractor in addition to its own extended general conditions. 

 

The Eastern District of Louisiana found that the letter of intent served as an enforceable contract between the subcontractor and sub-subcontractor and the sub-subcontractor breached the letter of intent through its delayed performance.  As a result, the subcontractor was entitled to withhold / back-charge the sub-subcontractor for (i) the costs spent on the supplemental entity to mitigate the sub-subcontractor’s delay and (ii) the portion of liquidated damages attributable to the sub-subcontractor’s delay.  The court did not, however, allow the subcontractor to back-charge the sub-subcontractor for other delay-related costs (such as the prime contractor’s and the subcontractor’s extended general conditions) since the sub-subcontractor never contractually agreed to these types of damages unlike the liquidated damages section that was included in the specifications referenced in the letter of intent.

 

 

Take-aways:

  • If a letter of intent is issued, the letter of intent should identify the subcontract amount, the applicable scope of work, and reference the plans and specifications.  The more detail in the letter of intent the better so that if the subcontractor starts performing based on the letter of intent there is a strong argument that the detailed letter of intent served as the contract between the parties (such as if the subcontractor refuses to sign the subcontract, the parties are unable to agree on the formal written subcontract, or if the subcontract is never issued).
  • It is good practice to have both the contractor and subcontractor sign the letter of intent.
  • An unexecuted contract does not mean there is not a written contract between the parties.  Parties need to consider this before taking an extreme position that a contract does not exist or that they are not bound by certain requirements.
  • It is  good practice for a party subcontracting work to be able to flow-down damages such as liquidated damages and their own extended general conditions.  In this case, the subcontractor would have been able to flow-down the prime contractor’s and its extended general conditions attributable to the sub-subcontractor’s delay had this been identified in the letter of intent or clarified by an executed written subcontract. 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

DON’T DRAFT AN AMBIGUOUS SCOPE OF WORK IN YOUR CONSTRUCTION CONTRACT


Contractors should spend time carefully drafting and agreeing to a detailed scope of work.  Otherwise, a dispute may arise relating to that scope of work.  This dispute can take the form of a change order dispute where the contractor argues that the subcontractor’s change order request was base contract work and, thus, does not entitle the subcontractor to additional compensation. Or, the dispute can take the form of a defect claim where the subcontractor argues that the defect being asserted against it was never within its scope of work to begin with.

 

If there is a scope of work dispute, a court will look to the contract and any applicable change orders in order to see what the contract requires.  If an ambiguity exists relating to the scope of work, the court will determine whether the ambiguity is a patent ambiguity or a latent ambiguityA patent ambiguity clearly exists on the face of the contract based on defective, insensible, or obscure language used in the contract whereas a latent ambiguity is not apparent from the face of the contract, but becomes apparent when extrinsic / parol evidence is introduced that leads to the contract being interpreted in two reasonably plausible mannersSee Barrington v. Gryphon Investments, Inc., 32 So.3d 668 (Fla. 2d DCA 2010).  With a patent ambiguity, parol evidence (extrinsic evidence used to clarify the intent of the parties relating to a contractual provision) is NOT allowed to clear up the ambiguity; rather, it is up to the trier of fact (judge or jury) to interpret the patent ambiguity without extrinsic evidence explaining the intent of the partiesSee, e.g., Barclays American Mortg. Corp. v. Bank of Central Florida, 629 So.2d 978 (Fla. 5th DCA 1993) (it was up to trier of fact to interpret letter of credit containing 2 different expiration dates).  On the other hand, with a latent ambiguity, parol evidence is allowed to be introduced relating to the parties’ intent to assist the trier of fact in clearing up the ambiguity.

 


The opinion in Macky Bluffs Development Corp. v. Advance Construction Services, Inc., 2008 WL 109390 (N.D.Fla. 2008) illustrates what can happen if there is an ambiguous scope of work.  Here, a developer entered into a change order with a contractor to fix the collapsed wall of a retention pond.  The change order required the contractor to haul off collapsed material from the bottom of the pond.  To fix the wall, the contractor hauled collapsed material and stockpiled the material on lot #8 (owned by the developer).  The contractor reused suitable material in reconstructing the wall in addition to material it excavated from lot #8.  The unsuitable material the contractor did not use in reconstructing the wall was spread out and compacted on lot #8 versus being hauled offsite to a dumping site.

 

Years later, the developer discovered the unsuitable materials had been buried on lot #8 that required it to excavate and remove this material and refill with suitable material.  The developer then sued the contractor for the costs it incurred in remediating this issue.  The contractor moved for summary judgment arguing that lot #8 was never part of its scope of work and it reconstructed the wall of the retention pond pursuant to the change order.   Unfortunately, the change order did not specify whether the contractor was required to haul off unsuitable material to an offsite dumping facility or it was required to leave that material on lot #8.  In fact, it does not appear the change order even mentioned that the contractor was going to stockpile collapsed material on lot #8 and reuse suitable material in reconstructing the wall.   The owner’s position was that while the contractor could use lot #8 as a temporary storage area, the contractor was always required to haul off unsuitable material to an offsite dumping facility.  The contractor disagreed stating it was always going to leave unsuitable material on lot #8 that it could not reuse to reduce the costs associated with fixing the wall.  Yet, the change order did not address this issue and was ambiguous as to what the contractor’s scope of work consisted of relative to reconstructing the wall with stockpiled suitable material and what it was required to do with unsuitable material it did not reuse.

 

The Northern District maintained that the scope of work in the change order contained a latent ambiguity because the change order did not identify where the contractor was required to haul off the collapsed material and both the contractor and owner’s interpretation of this scope of work was plausible and reasonable.   The court’s opinion includes a good discussion about the difference between a patent ambiguity and a latent ambiguity:

 

Under Florida law, the interpretation of a contract is a matter of law for the court’s determination so long as the terms of the contract are unambiguous.  The existence of an ambiguity in a contract is also a matter of law.  There are two types of ambiguities that can exist in a contract: patent and latent.  A patent ambiguity is one that appears on the face of the contract.  A latent ambiguity, on the other hand, exists where the language employed is clear and intelligible and suggests but a single meaning, but some extrinsic / parol evidence creates a necessity for interpretation or a choice among two or more possible meanings.  If the ambiguity is patent, then parol evidence cannot be used to clarify the parties’ intent.  If the court finds, however, that there is a latent ambiguity in the contract, then parol evidence must be heard in order to explain the meaning of the ambiguous term.  After receiving parol evidence clarifying the latent ambiguity, if there is no genuine issue of material fact remaining, the court can resolve the ambiguity as a matter of law.  Where, however, the terms of the written instrument are disputed and reasonably susceptible to more than one construction, an issue of fact is presented as to the parties’ intent which cannot properly be resolved by summary judgment.”

Macky Bluffs Development Corp., supra, at *2 (internal citations and quotations omitted).

 

Had the parties clearly clarified the scope of work relating to how collapsed material was going to be stockpiled on lot #8 and reused and whether unsuitable material was going to be (a) hauled offsite or (b) left on lot #8, there probably would be no scope of work dispute.  But, because this issue was not truly defined, it presented an ambiguity that naturally resulted in a dispute when the developer needed to remove the unsuitable material on lot #8.  The key is to spend the effort to clearly articulate the scope of work, whether it is base contract work or change order work, to best support your argument when a scope of work dispute subsequently arises.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.