DON’T IGNORE PREJUDGMENT INTEREST

When it comes to contracts, there may be a clause that provides that untimely payments shall bear interest at a particular rate.  Or it may be the statutory rate.  That clause will come into play when determining prejudgment interest. In ANY dispute, prejudgment interest can be an important damages component that accrues from the date of the loss.  Don’t ignore prejudgment interest.

The Fourth District of Florida, in a construction dispute, maintained:

“[I]f a plaintiff establishes that he sustained out-of-pocket loss, prejudgment interest must be awarded from the date of the loss. The trial court has no discretion regarding awarding prejudgment interest and must do so applying the statutory rate of interest in effect at the time the interest accrues.”

Bensusan v. Design Engineering Group, LLC, 2025 WL 3466367 (Fla. 4th DCA 2025) (citation omitted).

In this dispute, a subcontractor prevailed on a claim with the owner after the owner entered into a guaranty agreement with the subcontractor if the subcontractor was not paid by the general contractor. The subcontractor was not paid and prevailed in its claim under the guaranty agreement with the owner. An issue was the application of prejudgment interest which was affirmed at the statutory rate since the guaranty agreement did not specify a rate.

Prejudgment interest is a legitimate category of damages and represents real money. It comes into play when trying a case or prevailing in that case. Now, to settle a case, it may require a party to overlook this category, which makes sense because settlement requires a give and take. But it is a real and legitimate category of damages that should not be ignored.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CONSEQUENTIAL vs. DIRECT DAMAGES AND WAIVER OF CONSEQUENTIAL DAMAGES

In a recent case, a design professional tried to argue it had a “get out of jail free” costs for repair and remediation costs an owner sustained due to structural engineering errors and omissions. The “get out of jail” free card was based on a waiver of consequential damages in their contract.  The contract, however, did NOT define consequential damages which gave the design professional the argument that the damages the owner claimed should be deemed consequential. The trial court, finding that such damages were NOT consequential in nature and not contractually waived by the owner, discussed the difference between consequential and direct damages (see below).  In doing so, though, the trial court explained:

Based on the definitions of the relevant terms and the facts of this case, the Court finds that [Owner’s] costs of remediation and repair are not consequential damages that were waived in the Agreement. [Design Professional] was contractually obligated to provide plans, including structural engineering plans, for the construction of a hospital in a large project coordinated among many sophisticated parties. The costs of remediation and repair did not “result indirectly from” [Design Professional’s] plans, nor did they arise from “dealings with third parties” in either the more “traditional” sense (such as lost profits or loss of reputation) or the causative way described by the Keystone Airpark court. Instead, the costs to repair and remediate are the “direct, natural, logical[,] and necessary consequences of” [Design Professional’s] deficient plans. Thus, recovery of these damages is not barred by the consequential-damages waiver in the Agreement.

Orlando Health, Inc. v. HKS Architects, Inc., 2025 WL 1919349, *7 (M.D.Fla. 2025) (internal citations and footnotes omitted).

While a waiver of consequential damages in construction contracts are commonplace, there are implications which need to be discussed and vetted during the preparation and negotiation of the contract.

Difference Between Consequential Damages and Direct Damages

Florida courts have defined “consequential damages” as damages that “do not arise within the scope of the immediate buyer seller transaction, but rather stem from losses incurred by the non-breaching party in its dealings, often with third parties, which were a proximate result of the breach, and which were reasonably foreseeable by the breaching party at the time of contracting.” “The most common form of consequential damages is lost profits.” Other examples of losses typically regarded as falling into this category are reputational damage … rental expenses, and loss of use, id.

On the other hand, direct damages—sometimes also referred to as “general damages” —“are commonly defined as those damages which are the direct, natural, logical and necessary consequences of the injury.” They “naturally and necessarily flow or result from the injuries alleged” and “may be described as those damages ‘as may fairly and reasonably be considered as arising in the usual course of events from the breach of contract itself.’ ”

Orlando Health, Inc. v. HKS Architects, Inc., 2025 WL 1919349, *4 (M.D.Fla. 2025) (internal citations and footnotes omitted).

PROVING AND DEFENDING AGAINST CONSTRUCTION DEFECT DAMAGES

Recent decisions in Florida (see here) have harshly come out against owners in construction defect cases that fail to properly measure their damages as of the date of the breach. The result has been a big “L” for owners in these cases based on an appeal even though the owners won at the trial level.

In a recent case, an owner presented construction defect damages from an expert and prevailed at trial. However, the damages were NOT measured as of the date of the breach, but years after. The appellate court reversed and remanded in favor of the contractor, meaning the owner lost the case.

If you are involved in a construction defect case, make sure the below is instilled in your thought process and analysis because you NEED to know how to prove construction defect damages and defend against construction defect damages:

“Damages for a breach of contract should be measured as of the date of the breach. Fluctuations in value after the breach do not affect the nonbreaching party’s recovery.” Damages are not supported by competent, substantial evidence when damages are assessed for a time other than that of the time of breach.
***
The homeowners “had a duty to prove each element of their claim, including the proper measure of damages.” “The generally prevailing rule is that a party will not be permitted a new trial on remand to remedy its own failure to present sufficient evidence to support its claim.” On remand, the homeowners are not entitled to a new trial on damages “because such a hearing ‘improperly allows appellee “a second bite at the apple” at proving damages.’ ”

Vuletic Group L.L.C. v. Malkin, 50 Fla.L.Weekly D1546c (Fla. 4th DCA 2025) (internal citations omitted).

Do not neglect the proper measure of damages in construction defect cases!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION DEFECT DISPUTES: KNOW YOUR MEASURE OF DAMAGES!!!!!

Remember this: know your measure of damages in a construction defect dispute. If you don’t, as shown below, the outcome can be unforgiving. The measure of damages is one of your most important elements of proof. You are filing suit for damages; thus, knowing what you can reasonably recovery is paramount.

In a recent dispute, Bandklayder Development, LLC v. Sabga, 50 Fla.L.Weekly D91e (Fla. 3d DCA 2025), a residential developer sold a single-family house while it was under construction in an as-is purchase agreement. Post-closing, the purchasers claimed defects and served a Florida Statutes Chapter 558 notice of construction defects letter. The purchaser subsequently initiated a construction defect lawsuit. During the nonjury trial, the purchaser’s expert testified that the purchasers suffered damages approximating $323,000 calculated as of January 19, 2022 (which was the date of the expert’s report). The expert further testified that the cost to finish the incomplete/defective work increased by 35% at the date of the May 2023 trial. However, the expert never testified as to the amount of damages as of the date of the contractual breach, which at the latest, would have been in April 2018 when the notice of construction defects letter was sent (or, at its earliest, June 2017 when closing occurred). At trial, the judge entered judgment for the purchasers in the amount of about $425,0000.  This was reversed on appeal with judgment to be entered in favor of the developer.  Why? Because the purchasers employed the wrong measure of damages and the only thing that prevented them from introducing the right measure of damages was within their control.  Harsh outcome for not applying the correct measure of damages!

To apply the correction measure of damages:

As a general rule in construction defect cases, “the measure of damages is the reasonable cost of making the performed work conform to the contract.”  “The purpose of compensation is to restore the injured party to the condition which he would have been in had the contract been performed.” 

It is well-established in Florida that damages for breach of a construction contract based on defective work are calculated as of the date of the breach. In 1982, the Florida Supreme Court, in Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037 (Fla. 1982), adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which provides:

(1) For a breach by one who has contracted to construct a specified product, the other party can get judgment for compensatory damages for all unavoidable harm that the builder had reason to foresee when the contract was made, less such part of the contract price as has not been paid and is not still payable, determined as follows:

(a) For defective or unfinished construction he can get judgment for either

(i) the reasonable cost of construction and completion in accordance with the contract, if this is possible and does not involve unreasonable economic waste; or

(ii) the difference between the value that the product contracted for would have had and the value of the performance that has been received by the plaintiff, if construction and completion in accordance with the contract would involve unreasonable economic waste.

In doing so, the Court observed: “Subsection 346(1)(a), therefore, is designed to restore the injured party to the condition he would have been in if the contract had been performed. This aim corresponds with general Florida law. We adopt subsection 346(1)(a) as the law in Florida regarding breaches of construction contracts.” 

Importantly, the Court then held:

Damages for a breach of contract should be measured as of the date of the breach.  Fluctuations in value after the breach do not affect the nonbreaching party’s recovery.

See Bandklayder Development, supra (internal citations omitted).

The purchasers’ problem here, is that they failed to prove their damages or offer evidence of their damages as of the date of the breach. Otherwise, damages is based on guesswork which is a big no-no! “‘[D]amages cannot be based upon speculation or guesswork, but must have some reasonable basis in fact.’” See Bandklayder, supra.  This guesswork is demonstrated by the purchaser’s expert that testified that the repair damages increased by about 35% from the date of his report to the date of the trial.

If you need help understanding your measure of damages, please consult a construction lawyer that works collaboratively with an expert.  Just remember: KNOW YOUR MEASURE OF DAMAGES!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CUMULATIVE IMPACT CLAIMS AND DEFINITION BY CERTAIN BOARDS

What is a cumulative impact claim?  This is commonly referred to as the unforeseeable ripple effect of changes, i.e., the death by a thousand cuts.  Cumulative impact claims refer to a disruption on productivity based on the cumulative impact of changes and their impact on unchanged work. Cumulative impact claims are difficult claims to prove, particularly based on the causation standpoint (and argument they could be released based on change order language). If pursuing or considering a cumulative impact claim, you will need to work with a consultant(s) and lawyer that understand the dynamic of these claims to best maximize your arguments and recovery from a causation and damages standpoint. Cumulative impact damages are real.  They occur. But they are not damages you can just throw out there or use loosely and expect to develop traction on compensation.

Below is how cumulative impact claims are defined by certain Boards of Contract Appeals. The definitions are important.

In Appeal of Centex Bateson Construction, Co., Inc., 9901 BCA P 30153, VABCA 4613 (VABCA 1998), the Board explained:

Direct impact, as the immediate and direct effect of a change on unchanged work, is considered foreseeable.

***

Direct impact is generally characterized as the immediate and direct disruption resulting from a change that lowers productivity in the performance of the changed or unchanged work. Direct impact is considered foreseeable and the disrupting relationship to unchanged work can be related in time and space to a specific change Cumulative impact is the unforeseeable disruption of productivity resulting from the “synergistic” effect of an undifferentiated group of changes. Cumulative impact is referred to as the “ripple effect” of changes on unchanged work that causes a decrease in productivity and is not analyzed in terms of spatial or temporal relationships. This phenomenon arises at the point the ripples caused by an indivisible body on two or more changes on the pond of a construction project sufficiently overlap and disturb the surface such that entitlement to recover additional costs resulting from the turbulence spontaneously erupts. This overlapping of the ripples is also described as the “synergistic effect” of accumulated changes. This effect is unforeseeable and indirect. Cumulative impact has also been described in terms of the fundamental alteration of the parties’ bargain resulting from changes. This approach is highlighted by the ASBCA’s discussion of cumulative impact in Atlantic Dry Dock Corporation:

The Board has long recognized the concept of so-called cumulative disruption. In Triple “A” South, [citation omitted] we defined this type of impact as the disruption, which occurs between two or more change orders and basic work and is exclusive of that local disruption that can be ascribed to a specific change. It is the synergistic effect… of changes on the unchanged work and on other changes. Describing appellant’s evidence of such impact as merely ‘anecdotal/ the Board held that to recover for cumulative disruption, a contractor must show that the Government exceeded the permissible limits of its discretion under the Changes clause and ordered changes that ‘materially alter the nature of the bargain agreed upon.’ [citation omitted]

***

Causation, in the context of a cumulative impact, can be an elusive commodity because the concept of cumulative impact is, in itself, somewhat amorphous. Several points relevant to cumulative impact and causation, however, are clear. First, the mere existence of numerous contract changes in and of themselves, whether or not the number of changes is considered to be reasonable or unreasonable and whether or not the changes resulted from defective specifications, establishes no right to recover cumulative impact costs. Consequently, contract changes alone, regardless of their number or nature combined with Government liability do not serve as a substitute for causation and do not necessarily give rise to cumulative impact damages. Second, it is clear that demonstrating an overrun in labor and the existence of numerous changes without some evidence linking the changes to the overrun is insufficient proof of causation. Finally, there must be some proof of a causal connection established showing that the undifferentiated group of contract changes affecting the changed and unchanged contract work resulted in the loss of productivity on that work. This proof may take the form of demonstrating that there are no other reasons for a loss of productivity for which the Government is not responsible

In Appeals of Norman Engineering Co., 92-BCA P 24900, NASA BCA No. 1189-12 (NASA 1992), the Board noted:

As a matter of law, an “impact” claim or a “cumulative impact” claim is a claim based on the constructive change theory that is asserted separately from individual compensable changes. Cumulative impact arises from changes which had such an effect on performance that there is a separately compensable impact claim that does not include the direct costs of the changes.

In Appeal of Bechtel Nat., Inc., 90-1 BCA P 22549, NASA BCA No. 1187-7 (NASA BCA 1989), the Board found:

Cumulative impact need not be traced to specific causes of increased performance costs, but can arise from changes which, when viewed retrospectively, were so many and had such effect on performance that there is a separately compensable impact claim. We do not require the specificity here that would otherwise be necessary for Appellant to prevail on entitlement. The sheer number of change orders, however, cannot establish the validity of a cumulative impact claim. Impact is not demonstrated solely by showing the number of changes or clarifications to the contract.  General unsupported statements that a contractor suffered impact are not sufficient proof that it did, and the absence of contemporaneous documentary evidence of the disruptive effects to the work may provide reason for rejecting the claim.

In McMillin Bros. Constructors, Inc., 91-1 BCA P 23351, EBCA No. 328-10-84 (EBCA 1990), the Board maintained:

Since 1968, when the Changes clause was amended to include the above phrase “whether or not changed by any order”, boards have experienced an increasing number of claims of cost “impact” on unchanged work, which allegedly was not priced and settled as a cost of performing the changed work.  In cases involving a multitude of changes, these alleged added costs have been commonly referred to as “cumulative impact” costs. Because contractors are required to include known and generally foreseeable impacts on unchanged work in pricing the cost of a change, the term “cumulative impact” has come to mean, in a generic sense, the impact on unchanged work which is not attributable to any one change but flows from the synergy of the number and scope of changes issued on a project. The underlying theory is that numerous changes cause a cascading ripple-type of impact on performance time and efficiency which is too uncertain or diffuse to be readily discernable at the time of pricing each individual change

We do not question that such impacts from cumulative changes do, in some instances, occur and should be compensated. However, we are mindful that impacts, whether on changed or unchanged work, which flow directly from individual changes are, with few exceptions, legally compensated by the price negotiated for the change and, thus, should be excluded from recovery under a cumulative impact claim. We are also mindful that even when a compensable cumulative impact is found, proof of damages under a total cost approach (an approach often relied upon in this type of claim) is acceptable only where safeguards for its use have been clearly established. The total cost method is not favored, in part, because it is extremely difficult to assure that the contract is not transformed into a de facto cost reimbursement contract and that costs which should be borne by Appellant are excluded.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE INDEPENDENT TORT DOCTRINE (AND ITS IMPORTANCE)

A non-construction raises an important legal principle.  Here it is because it applies to construction disputes.  It actually applies to many business-type disputes.  It is based on what is widely referred to as the independent tort doctrine:

Florida law does not allow a party damaged by a breach of contract to recover exactly the same contract damages via a tort claim. “It is a fundamental, long-standing common law principle that a plaintiff may not recover in tort for a contract dispute unless the tort is independent of any breach of contract.  A plaintiff bringing both a breach of contract and a tort claim must allege, in addition to the breach of contract, “some other conduct amounting to an independent tort.” 

Bedoyan v. Samra, 47 Fla.L.Weekly D1955a (Fla. 3d 2022) (internal citations omitted).

The reason this principle–the independent tort doctrine–is important is because it has become common for parties to assert many causes of action against another party in the same lawsuit.  Oftentimes, they deal with the SAME damages and underlying conduct.  Sometimes, it is the “throw everything but the kitchen sink” approach.  Thus, a party may assert a contract claim (or seek contractual damages) in conjunction with numerous tort claims (e.g., negligence, fraud, negligent misrepresentation, breach of fiduciary duty, etc.).  Yet, when push comes to shove, the damages sought are no different than the contractual damages, i.e., it is all the same damages based on the same conduct.  The damages do not derive from an independent tort (e.g, separate conduct) unrelated to a contractual breach, or contractual damages.

This case of Bedoyan is an example. Here, there was a partnership dispute that was tried. The plaintiff claimed the defendant breached their oral partnership agreement and breached fiduciary duties. The trial court granted defendant’s motion for a directed verdict on plaintiff’s breach of fiduciary duty claim. The plaintiff’s breach of fiduciary duty claim “was not independent from his allegation of breach of contract; the same conduct gave rise to both. As such, there are no damages for breach of fiduciary duty separate and apart from the breach of the contract, and the trial court correctly directed a verdict against [plaintiff] on this issue.”  Bedoyan, supra.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

MEASURE OF DAMAGES FOR BREACH OF CONSTRUCTION CONTRACT

How do you determine damages for a breach of a construction contract?  If you are interested in pursing a breach of a construction contract action, this is something you NEED TO KNOW!

The recent Fourth District Court of Appeal’s decision in Cano, Inc. v. Judet, 46 Fla. L. Weekly D2083b (Fla. 4th DCA 201) explains:

Where a contractor breaches a construction contract, and the owner sues for breach of contract and the cost to complete, the measure of damages is the difference between the contract price and the reasonable cost to perform the contractSee Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037, 1039-40 (Fla. 1982). In Grossman, the supreme court adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which it concluded was “designed to restore the injured party to the condition he would have been in if the contract had been performed.” Id. at 1039. In other words, the owner will obtain the benefit of his bargain [and this is known as benefit of the bargain damages]. But where there is a total breach of the contract as opposed to a partial breach, an injured party may elect to treat the contract as void and seek damages that will restore him to the position that he was in prior to entering into the contract or the party may seek the benefit of his bargainSee McCray v. Murray, 423 So. 2d 559, 561 (Fla. 1st DCA 1982).

In Judet, an owner entered into a fixed price contract with a contractor to repair damage from a lightning strike. The contract amount was $300,000 payable in $30,000 installments.  A few months after the contractor commenced performance, the owner terminated the contractor because the owner learned the contractor had not obtained required electrical and plumbing permits.  At this time, the owner had paid the contractor $90,000.  The contractor recorded a $40,000 lien for an amount it claimed it was owed and filed a lawsuit to foreclose its construction lien. The owner counter-sued the contractor to recover a claimed over-payment and a disgorgement of monies for unpermitted work.  The owner was NOT claiming benefit of the bargain damages, but rather, damages for the contractor’s total breach “to restore him to the position that he was in prior to entering into the contract.”

After a bench trial, the trial court found the contractor committed the first material breach by failing to obtain the required electrical and plumbing permits.  Thus, the trial court held that the contractor was only entitled to the value of the work it performed, an amount of $49,150 as determined by the owner’s expert.  The trial court then entered a judgment in favor of the owner for $40,850 which was the difference between the value of the work performed ($49,150) and what the owner had paid the contractor prior to termination ($90,000).  This was affirmed by the appellate court: “The trial court entered judgment for [the owner] to place him in the position immediately prior to the contract by returning the payments he made to [the contractor] less the quantum meruit value of [the contractor’s] work.”  Judet, supra.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

ANTICIPATORY REPUDIATION OF A CONTRACT — THE PROSPECTIVE BREACH

There are instances where a party can engage in the anticipatory repudiation of their obligations under a contract.  In essence, this is basically a party prospectively breaching the contract by repudiating their obligations in the contract.

A prospective breach of contract occurs where there is absolute repudiation by one of the parties prior to the time when his performance is due under the terms of the contract.  Such a repudiation may be evidenced by words or voluntary acts but the refusal must be distinct, unequivocal, and absolute. Moreover, repudiation can be shown where one party makes additional demands not included in the initial agreement:

            The law is clear that where one party to the contract arbitrarily demands performance not required by the contract and couples this demand with a refusal to further perform unless the demand is met, the party has anticipatorily repudiated the contract, which anticipatory repudiation relieves the non-breaching party of its duty to further perform and creates in it an immediate cause of action for breach of contract.

24 Hr Air Service, Inc. v. Hosanna Community Baptist Church, Inc., 46 Fla. L. Weekly, D1344a (Fla. 3d DCA 2021) (quotations and citations omitted).

In 24 Hr Air Service, an air conditioning contractor agreed to perform repairs to a Church’s air conditioning unit.  However, when the contractor went into the attic to start the repairs, the wooden platform in the attic was unstable and a portion of the ceiling collapsed.  The Church repaired the ceiling.  However, the contractor refused to return to complete its repairs citing safety reasons.  The contractor requested proof the repairs to the ceiling were made before it returned to complete its contracted work and such proof was never provided.

Did the contractor’s refusal to complete its work amount to anticipatory repudiation of its contract by imposing the additional demand of proof of repairs to the ceiling before completing its contracted work?  Both the trial and appellate court believed so.

The Contractor’s request that the Church provide safety assurances of the ceiling repairs constitutes an additional demand that was not agreed to by the parties under the service contract.  Despite the Contractor’s argument that it never abandoned the job, its demand for safety assurances coupled with its refusal to complete the agreed repairs until such assurances were provided was an anticipatory breach of the contract. 

24 Hr Air Service, Inc., supra.

Based on the anticipatory repudiation or breach of the contract, what were the Church’s damages?

The proper measure of damages “would be either the reasonable cost of completion, or the difference between the value the repair would have had if completed and the value of the repair that has been thus far performed.”  24 Hr Air Service, Inc., supra (quotation and citation omitted).  This is referred to as benefit-of-the bargain damages, with the objective to place the damaged party in the position “he would have been in had the contract been completely performed.”  Id.    The party, however, cannot seek what is known as “betterment” or a better deal than what it originally bargained for—a party “can neither receive more than [it] bargained for nor be put in a better position than [it] would have been had the contract been performed.”  Id.

If you are dealing with a breach of contract, or even a prospective breach / anticipatory repudiation of an existing contract, it is advisable to seek legal counsel to assist you in preserving your arguments, the proper measure of damages for the breach, and any potential betterment associated with your damages.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION COSTS MUST BE REASONABLE

 

When it comes to proving a construction cost, particularly a cost in dispute, the cost must be REASONABLE.   Costs subject to claims must be reasonably incurred and the party incurring the costs must show the costs are reasonable.

An example of the burden falling on the contractor to prove the reasonableness of costs is found in government contracting.

“[T]here is no presumption that a [government] contractor is entitled to reimbursement ‘simply because it incurred…costs.’”  Kellogg Brown & Root Services, Inc. v. Secretary of Army, 973 F.3d 1366, 1371 (Fed. Cir. 2020) (citation omitted).  Stated differently, a federal contractor is not entitled to a presumption of reasonableness just because it incurs costsId.

In government contracting, the Federal Acquisition Regulations (known as “FAR”) puts the burden of reasonableness on the contractor that incurred the costs.  Id.

FAR s. 31-201-2(a) [Determining allowability] provides, “A cost is allowable only when the cost complies with all of the following requirements: (1) Reasonableness….”

FAR 31-201-3 [Determining reasonableness] maintains:

(a) A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business. Reasonableness of specific costs must be examined with particular care in connection with firms or their separate divisions that may not be subject to effective competitive restraints. No presumption of reasonableness shall be attached to the incurrence of costs by a contractor. If an initial review of the facts results in a challenge of a specific cost by the contracting officer or the contracting officer’s representative, the burden of proof shall be upon the contractor to establish that such cost is reasonable.

 (b) What is reasonable depends upon a variety of considerations and circumstances, including-

            (1) Whether it is the type of cost generally recognized as ordinary and necessary for the conduct of the contractor’s business or the contract performance;

            (2) Generally accepted sound business practices, arm’s-length bargaining, and Federal and State laws and regulations;

            (3) The contractor’s responsibilities to the Government, other customers, the owners of the business, employees, and the public at large; and

            (4) Any significant deviations from the contractor’s established practices.

In Kellogg Brown & Root Services, a government contractor on an international project received a task order from the government to provide accommodations and life support services which equated to trailers for temporary housing for army personnel.  The government was to provide protection / security for the contractor.  The contractor subcontracted the procurement of the trailers.  The contractor claimed due to delays from the Army’s failure to meet its protection obligations, there were delivery delays resulting in storage costs and additional double handling costs (e.g., loading and unloading of trailers more than once) incurred by its subcontractor.  The contractor submitted a claim of “$48,754,547.25 in equitable adjustments for idle truck costs due to the backup of trailers at the border and double handling costs” due to the government’s failure to provide protection, along with associated markup.  Kellogg Brown & Roof Services, supra, at 1369.   The contracting officer’s final decision denied all of the claim but $3,783,005 which pertained to land that had to be leased to store the trailers due to the delay.

The contractor appealed the final decision to the Armed Services Board of Contract Appeals.  The Board concluded that the contractor had NOT demonstrated its costs were reasonable.  In particular, the Board found: (a) the contractor did not demonstrate a prudent person conducting a competitive business would have resolved its subcontractor’s delay claim upon the same model submitted by the subcontractor; and (b) the contractor did not demonstrate the double handling costs were reasonable.  The contractor submitted estimates from its subcontractor and did not submit any actual costs; thus, the Board found the damages models (estimates) were unreasonable and flawed.  For this reason, the Board denied all recovery prompting the contractor to appeal to the United States Court of Appeals for the Federal Circuit.

The United States Court of Appeals agreed with the Board that the contractor failed to show the costs it incurred were reasonable.  Even if the contractor established the government’s liability for the costs, the claim failed due to the failure to show the reasonableness of the incurred cots.

In addressing this issue, the Court noted that the contractor was not required to show the actual costs incurred by the subcontractor, but it was required to show the payments to its subcontractor—costs incurred—were reasonable.  The problem for the contractor was that it failed to show in any of its cost calculations that the methodology used to calculate the delay costs was reasonable.  Instead, the Court picked apart, based on what the Board concluded from the evidence, the model employed by the contractor for being inconsistent and unreasonable based on a number of different grounds as the contractor’s damages model did not depict actual events that occurred.  The Court explained, “[the contractor] supplied no meaningful evidence to the Board showing the reasonableness of its costs, nor has it explained the inconsistencies between its proposed cost model and the factual record.”  Kellogg Brown & Root Services, supra, at 1374.

Regardless of the type of project, it is important to remember that a party (e.g., contractor) still must demonstrate that the cost it is claiming as damages is a cost that it is reasonably incurred!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

SPECIFIC PERFORMANCE: EQUITABLE REMEDY TO ENFORCE AFFIRMATIVE OBLIGATION

When a party breaches an agreement, particularly when dealing with real estate, there is an equitable remedy known as specific performance that requests the trial judge issue an order to affirmatively force the breaching party to perform, i.e., close on the real estate contract.   You are asking the court to require the other party to specifically perform an affirmative obligation.  See Melbourne Ocean Club Condominium Ass’n, Inc. v. Elledge, 71 So.3d 144, 146 (Fla. 2011).

A decree of specific performance is an equitable remedy ‘not granted as a matter of right or grace but as a matter of sound judicial discretion’ governed by legal and equitable principles.  Specific performance shall only be granted when 1) the plaintiff is clearly entitled to it, 2) there is no adequate remedy at law, and 3) the judge believes that justice requires it.

Castigliano v. O’Connor, 911 So.2d 145, 148 (Fla. 3d DCA 2005) (internal citations omitted).

An example of specific performance may play out, as mentioned, in a real estate contract where a seller refuses to close on the transaction.

For instance, in M&M Realty Partners at Hagen Ranch, LLC v. Mazzoni, 2020 WL 7296793 (11th Cir. 2020), a buyer entered into a land sale contract with a seller.  The contract included a six-year (contingency) period for the buyer to secure permits required to develop the land.  Closing never occurred and the buyer sued the seller for specific performance – to force the seller to close on the sale of the land.

During the six-year contingency period, the buyer spent substantial monies to secure permits.  Meanwhile, during this period, the seller received a better offer for the land.  The buyer claimed this prompted the seller to avoid closing.  Nonetheless, when the buyer secured the approvals to develop the land, it notified the seller that it wants to close on the land.  The seller refused claiming the buyer had not satisfied all conditions to closing, prompting this lawsuit for specific performance.  The trial court ruled in favor of the seller holding that the buyer failed to prove it was ready, willing, and able to perform (close) under the contract because there was no evidence that the buyer had sufficient funds to close.  The Eleventh Circuit Court of Appeals affirmed.

To establish a prima facie claim for specific performance of a contract or for damages for breach of a contract, Florida law requires the plaintiff to show it was ready, willing, and able to perform the contract.  A purchaser may show it is financially ready and able by showing it has (1) the necessary “cash in hand,” (2) “personal[ ] possess[ion] of assets … and a credit rating” that show a “reasonable certainty to command the requisite funds,” or (3) “a binding commitment … by a financially able third party.”  It is undisputed that [the buyer]…in this case, had neither (1) the necessary $5 million of cash in hand [to close] nor (2) assets and a credit rating sufficient to command that sum. Therefore [the buyer’s] only hope is to show it had (3) a binding commitment from a financially able third party.

[The buyer] argues that it was ready, willing, and able to perform under the contract, first, because [the ultimate principals of the members of the buyer limited liability company] could command credit from a bank in excess of $5 million and, second, because [the principals] each had over $5 million in cash. As [the buyer] is relying upon the resources of third parties, namely [principals], to show it was ready, willing, and able to close, [the buyer’s] arguments properly go to the third possible showing, i.e., that it has a binding commitment from a financially able third party. [The buyer] argues that its principals’ personal resources are sufficient to show the company had a “reasonable certainty” of being able to complete the purchase, but this falls short of the “binding commitment” the law requires.

M&M Realty Partners at Hagen Ranch, supra, at *2 (internal citations omitted).

The Eleventh Circuit agreed that the fact that the buyer’s ultimate principals had the funds is of no moment.  There was no evidence to support that either of the principals made a binding commitment (or any commitment, for that matter) to give or lend the money to the buyer to close on the land.  The Eleventh Circuit was not going to disregard corporate formalities of setting up a limited liability company for purposes of insulating liability simply because the principals of the two members of the limited liability company independently had money to close.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.