MAKE SURE CONSTRUCTION LIENS ARE PROPERLY PREPARED AND DO NOT CONTAIN ERRORS


If a construction lien is improperly filed or contains errors, an owner will try to capitalize on the improper filing or errors in order to get the lien discharged from his property. This is what an owner should do, although he should not lose sight over the difference between a ministerial error in the lien that you do not bank your entire defense on versus a truly substantive error under Florida’s Lien Law that could give the owner leverage in the dispute (e.g., not recording the claim of lien within 90 days from final furnishing, a subcontractor/supplier not serving a notice to owner, a lien from an unlicensed contractor, or a lien that includes improper amounts for nonlienable items).

 

The recent case of Premier Finishes, Inc. v. Maggirias, 2013 WL 5338052 (Fla. 2d DCA 2013), illustrates an error in a lien (that appears ministerial at first glance) that resulted in the lien being discharged by the trial court. However, although not discussed in the opinion, this case addresses much more than an error in a lien, but an interesting licensing issue.

 

In this case, a contractor was engaged to build a house. The contractor entered into the contract under a fictitious name. However, from reviewing the case, it does not appear that the fictitious name was a registered fictitious name, nor does it appear that the fictitious name was registered as a licensed contractor. Rather, it was simply an acronym used by the licensed contractor.

 

A payment dispute arose when the owner terminated the contractor, and the contractor recorded a claim of lien and moved to foreclose the lien. However, the lien was recorded and lawsuit initiated by the contractor and not the fictitious name that entered into the contract. The owner argued that the contractor was not a proper lienor and therefore the lien should be discharged because it was not the entity that actually entered into the contract. The trial court agreed.

 

On appeal through a petition for a writ of certiorari, the Second District reversed for two main reasons.

 

First, the Court held that a contract entered into under a fictitious name is enforceable (even if that fictitious name is not properly registered). See Fla. Stat. 869.09(9). The Court explained: “[I]f Premier Finishes [contractor] was the real entity using the fictitious name when entering into the contract, it is the actual party to the contract or the contractor…and is entitled to proceed with a claim of lien against the Owner.” Premier Finishes, 2013 WL 5338052 at *3.

 

Second, under Florida’s Lien Law, a ministerial error does not invalidate a lien unless the owner can show he was prejudiced by the error. See Fla. Stat. 713.08(4). The owner will have to show how he was adversely affected / prejudiced by the error, which would require an evidentiary hearing and can be quite challenging to prove.

 

Now, what is interesting about this case is whether there was any argument that the lien should be unenforceable because the fictitious entity that signed the contract was an unlicensed contractor (assuming this is the case). Under Florida Statute s. 489.128, contracts entered into by an unlicensed contractor are unenforceable in law or in equity by the unlicensed contractor. Thus, an unlicensed contractor cannot properly lien. Instead of the focus being on the error in the lien due to the lien being recorded by the contractor instead of the fictitious entity, the argument could center on the fact that the contract was entered into by an unlicensed contractor and, therefore, the contract and corresponding lien are not enforceable. Perhaps, the owner plans on raising this argument to establish prejudice.

 

While the contractor can certainly raise arguments to address the fact that the fictitious name is properly licensed since the contractor that owns the fictitious name is properly licensed, a contractor that is required to be licensed by the state (e.g., general contractor, mechanical contractor, electrical contractor, plumbing contractor, etc.) is technically supposed to register and identify the fictitious name it is doing business under. See Fla. Stat. 489.119.  Although, notably, there is an older case, Martin Daytona Corp. v. Strickland Const. Services, 881 So.2d 686 (Fla. 5th DCA 2004), that held that a subcontractor’s failure to obtain a license under its fictitious name did not render the contract unenforceable. However, this case was decided under a previous version of Florida Statute s. 489.128 and, importantly, the current version of this statute likely would not have applied to this case since the subcontractor (a mason) is not required to obtain a state license like a general contractor. It is uncertain how this case would be decided under current law.

 

The key is to double check your liens to ensure they are accurate and do not contain errors. Naturally, it is always a good thing to work with an attorney to prepare your lien so that if you know that if an error will likely exist you can game plan accordingly.  For example, if you entered into contracts in the name of an unregistered fictitious name, the decision in Premier Finishes can support your argument that the fictitious name would not render the contract or lien unenforceable especially if the fictious name is used by a properly licensed contractor.  Also, contractors needs to be sure they maintain proper licenses to remove any argument that the contract or lien is unenforceable. Keep in mind that under the law, a contract with an unlicensed contractor is unenforceable one-way by the unlicensed contractor; the other party to the contract can still seek recourse.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

MORE ON THE HARSH REALITIES OF CONTRACTORS NOT BEING PROPERLY LICENSED


Previously, we posted an article about the Florida’s court’s decision in Earth Trades, Inc. v. T&G Corp., 2013 WL 264440 (Fla. 2013), which demonstrates the huge risk an unlicensed contractor undertakes by entering into a contract based on Florida Statute s. 489.128 that would render contracts by the unlicensed contractor unenforceable in law or equity.

 

Well, unfortunately for the unlicensed contractor, there are more harsh realities further demonstrated by the Fourth District Court of Appeal’s ruling in Home Construction Management, LLC v. Comet, Inc., 2013 WL 440101 (Fla. 4th DCA 2013). This case references Florida Statute s. 768.0425 which provides in material part: “In any action against a contractor for injuries sustained resulting from the contractor’s negligence, malfeasance, or misfeasance, the consumer shall be entitled to three times the actual compensatory damages sustained in addition to costs and attorney’s fees if the contractor is neither certified as a contractor by the state nor licensed as a contractor pursuant to the laws of the municipality or county within which she or he is conducting business.”

 

In Home Construction Management, an owner hired an unlicensed contractor to complete the construction of a residence. Due to issues that are not discussed in the case, the owner sued the contractor for treble damages pursuant to s. 768.0425 and recovered a judgment against the unlicensed contractor (although the appellate court found that the representative of the unlicensed contractor–likely the person that signed the contract–was not a specific party to the contract and could not be liable for treble damages).

 

Besides the unlicensed contractor being unable to enforce its contract in any way, shape, or form in the event they are not paid, they could expose themselves to treble damages under s. 768.0425 (in addition to having to pay back all funds it received as an unlicensed contractor since a party cannot profit from an illegality). Statute 768.0425 is potentially extremely harsh because this statute would extend to contractors that do not necessarily need to be licensed by the state, but need to be licensed by a local jurisdiction in which they are performing work!!!  Thus, ensuring proper licensure is important to any contractor performing work, regardless of whether that work requires a license by Florida’s Construction Industry Licensing Board.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE HARSH REALITIES OF A CONTRACTOR NOT BEING PROPERLY LICENSED


The recent Florida Supreme Court’s decision in Earth Trades, Inc. v. T&G Corp., 2013 WL 264440 (Fla. 2013), demonstrates the harsh realities for an unlicensed contractor. In this case, a general contractor hired a site subcontractor. The subcontractor, alleging nonpayment, filed suit against the contractor and the contractor’s payment bond. The contractor argued that its site subcontractor was unlicensed and therefore was unable to pursue any cause of action against either the contractor or the payment bond. The contractor relied on Florida Statute s. 489.128 which provides in material part: “As a matter of public policy, contracts entered into on or after October 1, 1990, by an unlicensed contractor shall be unenforceable in law or in equity by the unlicensed contractor.

 

The unlicensed subcontractor argued what is referred to as the in pari delicto doctrine.  This doctrine stands for the proposition that a party who has knowledge and participates in the wrongdoing cannot reap the benefits of the wrongdoing. In other words, the subcontractor was arguing that the general contractor knew it was unlicensed and, thus, cannot reap the benefits of the harsh effects of the statute that would prohibit it from any remedy associated with the contractor’s nonpayment.

 

The Florida Supreme Court held that this in pari delicto doctrine does not apply even if the contractor knows that the subcontractor was unlicensed and hires the subcontractor anyway.

 

General contractors and subcontractors that are required to be licensed by the state (Florida’s Construction Industry Licensing Board) need to ensure they are properly licensed. Otherwise, if they enter into a contract with a party and despite the other party knowing about the lack of license, they will be out of luck. This could mean the other party has no legal obligation to pay it and arguably could seek to recoup monies paid to the unlicensed contractor. Obviously, this could be avoided by ensuring proper licensure, especially now that the defense “well, the other party knew I wasn’t properly licensed” no longer applies.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE IMPORTANCE OF PROPER CONSTRUCTION CONTRACTING LICENSES


Florida law requires general contractors (and certain specialty subcontractors) to be licensed with the state of Florida. See Florida Statutes Chapter 489, Part I. This is because construction contracting, similar to other professions, is regulated. The law treats the licensure of contractors very seriously in that, “[C]ontracts entered into on or after October 1, 1990, by an unlicensed contractor shall be unenforceable in law or in equity by the unlicensed contractor.” Fla.Stat. §489.128(1). Therefore, an unlicensed contractor that performs work will be unable to enforce nonpayment, which would include not properly being able to lien or foreclose on a lien. This could financially ruin a contractor that did a great job on a project but cannot secure final payment because it was not properly licensed.

 

Contractors need to ensure they are properly licensed prior to entering into a contract with an owner. Likewise, owners need to ensure that the contractor they are hiring is properly licensed. The construction contracting licensure law can be difficult navigating; therefore, having an attorney assist with any licensure questions is important to save both contractors and owners the heartache that may ensue if proper licenses are not in place.

 

In determining whether a contractor is unlicensed, the law provides:

 

“[A]n individual is unlicensed if the individual does not have a license required by this part concerning the scope of the work to be performed under the contract. A business organization is unlicensed if the business organization does not have a primary or secondary qualifying agent in accordance with this part concerning the scope of work to be performed under the contract. For purposes of this section, if a state license is not required for the scope of work to be performed under the contract, the individual performing that work is not considered unlicensed.
***
[A] contractor shall be considered unlicensed only if the contractor was [a] unlicensed on the effective date of the original contract for the work, if stated therein, or if not stated, [b] the date the last party the contract executed it, if stated therein. [c] If the contract does not establish such a date, the contractor shall be considered unlicensed only if the contractor was unlicensed on the first date upon which the contractor provided labor, services, or materials under the contract.” Fla.Stat. §489.128(1)(a), (c).

 

Recently, in Austin Building Company v. Rago, Ltd., 2011 WL 1563797 (Fla. 3d DCA 2011), the Third District dealt with the issue of whether a general contractor and subcontractor where properly licensed. In this case, an owner entered into a contract with the properly licensed general contractor (“GC”) in March 2005 for the construction of a condominium in Miami. The contract provided that once the GC’s affiliate (“Affiliate”) became a licensed general contractor in Florida, the GC would assign the contract and related documents to the Affiliate.

 

After the execution of the contract, GC engaged a structural concrete subcontractor (“Subcontractor”) that immediately commenced work in April 2005 without a formal contract in place. Months later, the Affiliate became licensed and formally executed the subcontract with the Subcontractor. The Affiliate, however, terminated the Subcontractor due to the Subcontractor’s defective work and, as a result, the Subcontractor sued the GC, the Affiliate, and their payment bond for nonpayment, and the Affiliate countersued the Subcontractor. Both parties moved for summary judgment arguing that the other was not a properly licensed contractor and, therefore, should not be entitled to enforce the subcontract.

 

The Third District Court of Appeal found that there remained a question of fact as to whether the GC or the Affiliate served as the general contractor when the Subcontractor started performing work. Notably, at the time the Subcontractor started performing construction activities without a contract, the Affiliate was not a licensed contractor. However, the GC was licensed. If the GC was the contractor at the start of the Subcontractor’s performance, the GC and/or the Affiliate should be in a position to enforce the Subcontract (which would seem to be the case given that it was contemplated when the owner hired the GC that the GC would eventually assign the contract and related documents to the Affiliate when the Affiliate became licensed). However, if the Affiliate is deemed to be the contractor at the start of the Subcontractor’s performance, then the Affiliate should not be able to enforce the subcontract to recover sums associated with the Subcontractor’s defective work because it was admittedly not a licensed contractor when the Subcontractor commenced performance.

 

The Third District further found that the Subcontractor did not need to be licensed and could enforce the subcontract. Although the case does not fully explain, it remains uncertain as to what activities the concrete Subcontractor performed that would have required a state license.

 

This case reveals the importance of proper construction contracting licenses. If the Subcontractor was not properly licensed with the state, then it would have no avenue to recover for nonpayment. This is difficult for many under capitalized subcontractors that rely on timely payments to fund their operations. On the other hand, if the contractor was not properly licensed, then it would have no avenue to recover against the Subcontractor for defective work. This would then make the contractor directly responsible for the Subcontractor’s work without any true avenue to recoup its costs against the Subcontractor.

 

For more on contractor licensing, please see: https://floridaconstru.wpengine.com/more-on-the-harsh-realities-of-contractors-not-being-properly-licensed/

and

https://floridaconstru.wpengine.com/the-harsh-realities-of-a-contractor-not-being-properly-licensed/

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.