SUBCONTRACTOR’S MILLER ACT PAYMENT BOND CLAIM

 

shutterstock_426148276Since I wrote my ebook on the application of federal Miller Act payment bonds, I have not discussed a case applying the Miller Act.  Until now!

 

Below is a case that reinforces two important points applicable to Miller Act payment bond claims.  First, the case reinforces what a claimant needs to prove to establish a Miller Act payment bond claim.  Very important.  Second, the case reinforces that a subcontractor is going to be governed by its subcontract. This means that those provisions regarding payment and scope of work are very important.  Not that you did not already know this, but ignoring contractual requirements will not fly.

 

In U.S.A. f/u/b/o Netplanner Systems, Inc. v. GSC Construction, Inc., 2017 WL 3594261 (E.D.N.C. 2017), a prime contractor hired a subcontractor to run cabling and wiring at Fort Bragg.  The subcontractor claimed it was owed a balance and filed a lawsuit against the general contractor the Miller Act payment bond.

 

“A plaintiff must prove four elements to collect under the Miller Act: (1) labor or materials were supplied for work in the contract; (2) the supplier of that labor or materials is unpaid; (3) the supplier had a good faith belief that the labor or materials were for the specified work; and (4) jurisdictional requisites are met.”   U.S.A. f/u/b/o Netplanner Systems, Inc., supra, at *5. 

 

The prime contractor claimed that the subcontractor was not owed any balance since it violated terms of the subcontract regarding its timely performance.  Per the subcontract, the subcontractor agreed that it would perform and complete its work in accordance with the schedule approved by the federal government and that final payment will be made when the subcontractor fully performed in accordance with the requirements of the Contract Documents.

 

In this case, the trial court determined there were questions of fact involving whether the subcontractor complied with the terms of the subcontract.  But, in doing so, the trial court confirmed, again, what we already know — that the subcontractor’s performance will be determined in reference to its underlying subcontract.

 

 

‘Whether a subcontractor has been paid in full for providing labor and materials must be determined by reference to the underlying subcontract as it relates to the scope of the work and the payment terms.’”  U.S.A. f/u/b/o Netplanner Systems, Inc., supra, at *5 quoting U.S. ex rel. Acoustical Concepts, Inc. v. Travelers Cas. and Sur. Co. of Am., 635 F.Supp.2d 434, 438 (E.D. Va. 2009).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

EBOOK: MILLER ACT PAYMENT BOND FUNDAMENTALS

41j9kWWd95L._AC_US436_QL65_I finally did it!  I wrote an ebook on the fundamentals of Miller Act payment bonds.  A nuts and bolts approach focusing on the practical application of Miller Act payment bonds.  It is currently on Amazon, Nook, and iTunes.  If you are interested in Miller Act payment bonds, check it out.  

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

MILLER ACT AND “PUBLIC WORK OF THE FEDERAL GOVERNMENT”

UnknownThe Miller Act applies to the “construction, alteration, or repair of any public building or public work of the Federal Government.”  40 U.S.C. s. 3131.   

 

A recent opinion out of the Northern District of Oklahoma sheds light on what the Miller Act means regarding its application to any public work of the Federal Government.    See U.S. v. Bronze Oak, LLC, 2017 WL 190099 (N.D.Ok. 2017).   If the project is not a public works project of the Federal Government, the Miller Act does not apply.

 

In this case, the Department of Transportation entered into an agreement with the Cherokee Nation where the Department would provide lump sum funding and the Nation would use the money to fund transportation projects.   Based on the federal funding, the Nation issued a bid for a transportation project in Mayes County, Oklahoma and the project was awarded to a prime contractor.  The prime contractor provided a payment bond that identified the United States as the obligee (as a Miller Act payment is required to do) and stated that it was issued per the Miller Act.    Thereafter, the Nation and Mayes County, Oklahoma entered into a Memorandum of Understanding where the County would assume responsibility for the construction and maintenance of the project and the Nation would pay the County an agreed amount upon the completion of the project.

 

A subcontractor filed suit claiming the prime contractor owed it money for work performed on the project.  One of the counts asserted was against the payment bond – the subcontractor claimed it was a Miller Act payment bond.  The prime contractor and payment bond surety moved to dismiss the lawsuit arguing that the payment bond is not a Miller Act payment bond, thus, the federal court has no jurisdiction to entertain the lawsuit.  How could this be?  The payment bond itself said it was issued per the Miller Act and identified the United States as the obligee as a Miller Act payment bond is required to do.

 

The underlying issue the Court examined was whether the project was a public works project of the Federal Government.  Again, if it was not, the Miller Act did not apply.  The Court explained:

 

Whether plaintiff may bring a suit under the Miller Act depends on whether the project is a “public work of the Federal Government.” The statute itself gives no guidance in interpreting the phrase. While there is no clear definition or test for classifying a project a “public work of the Federal Government,” courts often look to the following factors: “whether the United States is a contracting party, an obligee to the bond, an initiator or ultimate operator of the project; whether the work is done on property belonging to the United States; or whether the bonds are issued under the Miller Act.” Here, on the one hand, the United States is not a contracting party or an initiator or ultimate operator of the project, and the work was not done on federal land. On the other hand, the United States is obligee of the payment bond, and the bond was issued under the Miller Act. Additionally, the Nation funded the project with money it received from the federal government…and the DOT retained some control over the project by requiring semi-annual reports on, and occasional access to for inspections….

Bronze Oak, LLC, supra, at *2 (internal citations omitted).

 

To the dismay of the subcontractor-claimant, the Court held that the payment bond was NOT a Miller Act payment bond irrespective of what the bond actually said.  This meant that the Court had no jurisdiction to entertain the lawsuit (as there was no other basis that would give the federal court subject matter jurisdiction).  Although the Federal Government had a relationship with the project through its federal funding, that relationship was not strong enough to label the project as a public works project of the Federal Government.

 

The United States is the obligee of the payment bond, but even with federal funding of the project, this is not enough to bring the project under the Miller Act. The project is owned and maintained by the County and is not on federal land. The Nation initiated the project, and the federal government is not a contracting party. Finally, agreements among the contracting parties that federal law will apply does not transform a project that does not fall under the Miller Act into one that does.

Bronze Oak, LLC, supra, at *4. 

  

This was a tough ruling because if the subcontractor filed suit in state court the prime contractor and surety likely would have moved to dismiss that suit at some point in time arguing that the state court had no jurisdiction to entertain a Miller Act payment bond claim.  So, this situation appeared to be a lose-lose to the subcontractor that relied on the terms of the bond in pursuing the bond as a Miller Act payment bond.   

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: AIM TO AVOID A STAY TO YOUR MILLER ACT PAYMENT BOND CLAIM

imagesStrategy is important.  This is especially true if you are trying to avoid arbitration.  In a recent federal district court case, a subcontractor sued the prime contractor and the Miller Act payment bond surety.  The subcontractor, however, had an arbitration provision in its subcontract with the prime contractor.  The prime contractor moved to compel arbitration pursuant to the subcontract and moved to stay the subcontractor’s Miller Act payment bond claim.  The last thing, and I mean the last thing, the subcontractor wanted to do was to stay its claim against the Miller Act payment bond.  However, the district court compelled the subcontractor’s claim against the prime contractor to arbitration and stayed the subcontractor’s Miller Act payment bond claim pending the outcome of the arbitration.  See U.S. v. International Fidelity Ins. Co., 2017 WL 495614 (S.D.Al.  2017).  This is not what the subcontractor wanted. 

 

The outcome of this ruling may have been different if the subcontractor never sued the prime contractor and only sued the Miller Act payment bond surety.  The Miller Act payment bond surety did not move to compel the Miller Act claim to arbitration evidently meaning there was nothing in the subcontract that would support such an argument.  Had only the Miler Act payment bond surety been sued, the subcontractor may have likely been able to proceed with its payment dispute against the surety in federal district court without having to worry about arbitrating the same dispute with the prime contractor. 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

PRIME CONTRACTOR & SURETY’S RECOVERY OF ATTORNEY’S FEES IN MILLER ACT LAWSUIT

imagesCan a claimant recover attorney’s fees in a Miller Act payment bond dispute even though the Miller Act does not contain a prevailing party attorney’s fee provision?  Yes, if the underlying contract that formed the basis of the suit provided for attorney’s fees.  

 

What about a prime contractor and surety—can they recover their attorney’s fees if they prevail in a Miller Act payment bond claim and the underlying contract provides a basis for fees?   The Eleventh Circuit Court of Appeals in U.S.A. f/u/b/o RMP Capital Corp. v.  Turner Construction Co., 2017 WL 244066 (11th Cir. 2017) seemingly just answered this question in the affirmative when it reversed a lower court’s ruling that precluded a prime contractor and surety that prevailed in a Miller Act claim from recovering their attorney’s fees:

 

Like all other parties to contracts, general contractors on federal projects and their sureties can recover attorney’s fees where a contract allocates attorney’s fees to them. Here the contract that Turner [prime contractor] and the Sureties claim entitles them to an award of attorney’s fees was between Southwick [sub-subcontractor] and Bolena [subcontractor]. We remand to the district court to interpret that contract in the first instance, so as to determine whether it entitles Turner and the Sureties to an award of attorney’s fees, and if so how much.  Id at *2 (internal citation omitted).

 

 

While this ruling may seem harmless, it is a favorable ruling to a prime contractor and surety that prevail in a Miler Act payment bond claim when the underlying contract provides for attorney’s fees (which would likely be the same contract the claimant relies on to seek attorney’s fees).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

MILLER ACT PAYMENT BONDS

Do you do work on federal construction projects?  Are you familiar with the Miller Act?  Below is a portion of a recent presentation on Miller Act payment bonds.

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2016/10/miller-act1.pptx”]

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

PRIME CONTRACTOR INTERVENING INTO LAWSUIT AS PRINCIPAL OF MILLER ACT PAYMENT BOND

images-1In a Miller Act payment bond lawsuit (or any payment bond lawsuit for that matter), there are many times where a claimant (subcontractor, sub-subcontractor, or supplier) will sue the Miller Act payment bond surety and NOT the prime contractor or principal of the payment bond.  There are also times where the prime contractor moves to intervene in the lawsuit as the principal of the payment bond. Perhaps the prime contractor wants to assert a counterclaim against the claimant or a third-party claim.  These affirmative claims would belong to the prime contractor and not its surety; thus, the prime contractor moves to intervene in the lawsuit so that it can assert such affirmative claim(s) in the context of the dispute against its surety.  Oftentimes, a federal district court will allow the prime contractor to permissively intervene in the lawsuit as the principal of the payment bond, especially if the prime contractor plans to assert an affirmative claim to allow for the efficient resolution and disposition of all such claims. 

 

For example, in U.S. f/u/b/o Jackson Geothermal HVAC & Drilling, LLC v. Western Surety Co., 2016 WL 1030392, (D.N.J. 2016), the prime contractor hired a subcontractor to provide HVAC, geothermal services, plumbing, and sprinklers.  The subcontractor, in turn, subcontracted the geothermal services to the claimant–a sub-subcontractor on the project.  The sub-subcontractor (claimant) filed a lawsuit against the Miller Act payment bond surety for approximately $300,000.  The prime contractor, as principal of the payment bond, moved to intervene in the lawsuit primarily to (a) assert an affirmative claim for negligence against the sub-subcontractor and (b) assert a third-party claim against its subcontractor for breach of contract and negligence.  The issue before the court was whether the prime contractor should be able to intervene in the sub-subcontractor’s lawsuit against the Miller Act payment bond surety.  The district could found that permissive intervention was appropriate to allow the prime contractor to intervene in the sub-subcontractor’s Miller Act payment bond lawsuit:

 

[T]he Court finds no reason to believe that permitting Ranco [prime contractor / principal of payment bond] to intervene in this matter will unduly delay these proceedings or unfairly prejudice the adjudication of Jackson’s rights. While Ranco could pursue its state law claims against B&S [subcontractor] and Jackson [sub-subcontractor claimant] in state court, “notions of judicial economy suggest aggregating them in a single proceeding […] rather than have different tribunals examine these issues at different times.” Indeed, as the Third Circuit has noted, the court’s policy preference, i.e., “judicial economy, favors intervention over subsequent collateral attacks.” As a result, the Court finds that intervention will protect all of the parties from having to revisit the main issues being litigated here in separate proceedings. Thus, the Court shall permit Ranco to intervene in this matter. 

Western Surety Company, supra, at *4 (internal citation omitted).

 

There are times where a principal prime contractor intervening into a lawsuit against its surety may not be appropriate.  But, if the principal has affirmative claims or if the surety happens to be represented by different counsel (such that the surety is not allowing the principal to defend it with the principal’s preferred counsel) the prime contractor has a stronger basis to intervene in the lawsuit as a principal of the payment bond.   A prime contractor intervening in a lawsuit against its Miller Act payment bond surety is an important consideration based on the factual circumstances of the dispute.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: SUIT AGAINST MILLER ACT PAYMENT BOND MAY NOT BE BROUGHT UNTIL 90 DAYS AFTER FINAL FURNISHING

 

imagesIf you have a claim against a Miller act payment bond, a lawsuit cannot be brought until 90 days after your final furnishing date.  This is set forth in 40 USC s. 3133(b)(1) that provides if you “have not been paid in full within 90 days after the day on which…[you]…performed the last of the labor or furnished or supplied the material for which the claim is made [you] may bring a civil action on the payment bond.”   In other words, your claim is ripe 90 days after your final furnishing date.  With that said, even if you prematurely filed suit before this 90-day period, there is authority that the lawsuit should not be dismissed, but rather, you can cure this by filing a supplemental pleading (relating back to the original pleading).  Otherwise, if the lawsuit was dismissed, you could potentially be facing a statute of limitations argument barring your right to seek a Miller Act payment bond claim.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DO NOT EXECUTE A WAIVER AND RELEASE IN CONSIDERATION OF PAYMENT THAT RELEASES CLAIMS YOU ARE NOT PREPARED TO RELEASE

imagesAbsolutely do NOT execute a waiver and release in consideration of a progress payment that waives and releases claims (such as change order requests, lost productivity, or delay) that you are not prepared to release through the date of the release.  Carve out such exceptions from the release—identify those claims or rights you are not prepared to release.  Otherwise, when you go to pursue such claims, the waiver and release you previously executed will come back to haunt you!

 

For example, in U.S. f/u/b/o Chasney and Company, Inc. v. Hartford Accident & Indemnity Co., 2016 WL 852730 D.Md. 2016), a prime contractor on a federal project subcontracted with a mechanical and plumbing subcontractor.  The subcontractor’s last partial waiver and release it executed in consideration of a progress payment was in November 2013 for payment through October 31, 2013. The waiver and release provided that the subcontractor waived and released all liens, claims, and demands against the prime contractor or its surety in connection with the project through the period covered by the payment (through October 31, 2013).  The waiver and release included space for the subcontractor to identify exceptions. No such exceptions were identified.  In fact, prior to November 2013, the subcontractor executed a total of 24 progress waivers and releases and never excepted a single item or claim from the release. 

 

Notwithstanding, the subcontractor encountered design defects that caused it to incur additional costs and delayed its performance.  The subcontractor asserted pass-through claims that the prime contractor submitted to the federal government.  However, when the prime contractor and government settled their issues and a global settlement was reached, no amounts were assigned to respective items such as the subcontractor’s pass-through claims. The subcontractor then asserted the Miller Act payment bond lawsuit against the prime contractor’s Miller Act payment bond surety.

 

Applicable here, the surety and prime moved for summary judgment that any damages, including delay-related damages, that the subcontractor sought through October 31, 2013 were waived and released through the subcontractor’s November 2013 progress waiver and release.  The District Court of Maryland agreed since all it had to look to was the last waiver and release the subcontractor executed where it waived and released such rights:

 

By executing the October 31 Partial Release without exempting its claim, Chasney [subcontractor] relinquished its right to pursue the claim should it ever ripen. In hindsight, Chasney may regret its decision to sign such a release—but the Court’s task is to examine the agreement the parties did sign, not the agreement that one or the other now wishes they had negotiated instead….

***

In summary, the Court’s analysis begins and ends—as it must—with the unambiguous language of the Partial Releases. By signing each release, Chasney waived all claims relating to work performed through the covered period: no reasonable factfinder could conclude otherwise. While Chasney’s opposition brief teems with subtle linguistic maneuvers (and more than a few red herrings), Chasney cannot avoid the plain consequences of its contracting through artful argument….”

 

U.S. f/u/b/o Chasney & Company, 2016 WL at *7, 9 (internal quotations omitted).

 

Do NOT let this happen to you.  Preserve your rights and claims and do NOT waive and release claims you are NOT prepared to release!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

SUBCONTRACTORS MAY (LIKELY) BE REQUIRED TO STAY THEIR MILLER ACT PAYMENT BOND CLAIMS PENDING THE OUTCOME OF THE CONTRACT DISPUTES ACT RESOLUTION PROCESS

UnknownIf you are a subcontractor on federal construction projects, the opinion by the District Court of Alaska in U.S. f/u/b/o Brice Environmental Services Corp. v. Bhate Environmental Associates, Inc., 2016 WL 544406 (D.Alaska 2016),  provides an interesting or not-so-interesting outlook on subcontractors that participate (perhaps by choice) in the request for equitable adjustment (REA) and Contract Disputes Act dispute resolution process.  (See this article for more on this outlook that creates a conflict between a subcontractor’s Miller Act payment bond rights and a prime contractor’s participation in the Contract Disputes Act dispute resolution process.) 

 

In this matter, a soil remediation subcontractor submitted an REA to the prime contractor for approximately $3 Million associated with the prime contractor’s standby and additional work directives.  The subcontractor claimed that most of the REA was unrelated to issues caused by the owner, but rather, caused by the prime contractor.  The subcontractor and prime contractor agreed to a mutual termination of the subcontractor and the subcontractor reduced its REA to approximately $1.1 Million (to include only incurred costs versus anticipated costs).  The prime contractor then submitted a change order request to the federal government.  The subcontractor shortly thereafter sued the prime contractor and its Miller Act payment bond surety.

 

The prime contractor and its Miller Act payment bond surety moved to stay the lawsuit pending the completion a Contract Disputes Act resolution and, if required, completion of arbitration thereafter.  The subcontractor did not oppose staying its Miller Act payment bond claim pending arbitration with the prime contractor, but opposed staying the case pending the resolution of the prime contractor’s Contract Disputes Act claim. However, the subcontractor acknowledged that claims attributable to the federal government are passed through to the government and that the subcontractor shall not maintain any proceeding against the prime contractor with respect to government-related (owner) claims until resolution of Contract Dispute Act claims.  Moreover, the subcontract provided for the completion of the Contract Disputes Act resolution process between the prime contractor and federal government before the subcontractor could maintain any proceeding against the prime contractor in connection with any omission, default, or act by the federal government.   

 

 

Here, the subcontractor could not establish that the federal government’s acts did not contribute to its claims against the prime contractor; and, the prime contractor submitted a change order to the federal government that included the subcontractor’s costs supporting its position that the federal government’s acts were connected to the subcontractor’s claim.  Nonetheless, the subcontractor argued it would be unfair if it had to bear the brunt of waiting for the resolution of any Contract Disputes Act claim between the prime contractor and federal government before the subcontractor could pursue its claim against the prime contractor.  The Court dismissed this argument and stayed the action pending the outcome of the Contract Disputes Act resolution process between the prime contractor and federal government expounding:

 

The economic strain of awaiting resolution of the CDA procedures between Defendant Bhate [prime contractor] and AFCEC [federal government] is, while burdensome, still a reasonably foreseeable event under the Subcontract. Furthermore, denying the Motion to Stay and allowing this matter to proceed would bifurcate the matter, creating parallel proceedings involving many of the same facts and witnesses. Additionally, it could potentially force Defendants [prime contractor and surety] to take inconsistent positions in the simultaneous proceedings, supporting Plaintiff’s claims against AFCEC while defending against them in the arbitration between the parties. An order staying this matter is supported not only by the contract, but also the promotion of judicial economy and efficiency.

Bhate Environmental Associates, supra, at *4. 

 

This is undoubtedly a harsh ruling for a subcontractor that is now forced to wait a potentially long time while the prime contractor participates in the Contract Disputes Act resolution process. While harsh, the subcontractor agreed to bear this risk in its subcontract.  And, from the Court’s rationale, even if the subcontractor did not bear this risk, the Court still found that staying the subcontractor’s claims promoted judicial economy since it prevented the prime contractor from dealing with simultaneous disputes (one with the subcontractor and another with the federal government) and taking inconsistent positions.  

 

From the prime contractor’s perspective, this language that requires the subcontractor to bear this risk and stay any dispute pending the outcome of the Contract Disputes Act resolution process is extremely important language (based on the precise reasoning by the Court quoted above). 

 

From the subcontractor’s perspective, this reinforces the notion that it is imperative for parties to appreciate the risks they are agreeing to in their contracts, particularly as it relates to the resolution of disputes.  Also, this reinforces the risk that a subcontractor performing federal construction work may have to bear irrespective of the subcontract.  

 

Although the subcontractor is now in a wait-and-see mode while the Contract Disputes Act process runs its course, the subcontractor was smart by perfecting its Miller Act payment bond rights by timely filing suit.  Even though the prime contractor’s Contract Disputes Act resolution process may take some time, the prime contractor and its payment bond surety will ultimately have to deal with this dispute if the outcome of its Contract Disputes Act claim does not fully resolve the subcontractor’s claim to the subcontractor’s satisfaction.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.