SUBCONTRACTOR’S LIABILITY INSURER’S DUTY TO DEFEND THE “ADDITIONAL INSURED” GENERAL CONTRACTOR

shutterstock_306317915Construction projects can lead to insurance coverage disputes.  One such dispute arises when a general contractor is sued for construction defects and resulting property damage and it tenders the defense of the claim / lawsuit to an implicated subcontractor’s liability insurer.  A general contractor does this because it (hopefully) will be an additional insured under the subcontractor’s liability policy.  Being identified as an additional insured under a subcontractor’s liability policy is imperative for a general contractor as part of its normal risk assessment. The issue will typically come up in any construction defect lawsuit because if the general contractor is an additional insured it will, and should, tender the defense of the lawsuit to implicated subcontractors’ insurers. 

 

Sometimes, a subcontractor’s liability insurer will deny the duty to defend the general contractor.  Yes, this happens.  When it does, the general contractor’s insurer will provide a defense to the general contractor but may pursue the subcontractor’s insurer for reimbursement of fees and costs based on the general contractor being an additional insured under the subcontractor’s liability policy.

 

For example, in Travelers Property Casualty Co. of America v. Amerisure Ins. Co., 161 F.Supp.3d 113 (N.D.Fla. 2015), the general contractor’s liability insurer (Travelers) sued a stucco subcontractor’s liability insurer (Amerisure) where the underlying issue was whether the general contractor was an additional insured under the subcontractor’s liability policy.  The subcontractor’s insurer refused to defend the general contractor in an underlying construction defect lawsuit.  The general contractor’s insurer provided a defense in the underlying lawsuit and sued the subcontractor’s insurer for reimbursement.  

 

“Under Florida law, a liability insurer’s duty to defend extends to an entire lawsuit if any claim in the lawsuit may come within the policy’s coverage.”  Travelers Property Casualty Co., 161 F.Supp.3d at 1137.    The underlying complaint against the general contractor alleged property damage caused by defective stucco installation.  This meant that the complaint triggered the duty to defend and the Court held the general contractor was an additional insured under the subcontractor’s liability policy.  For this reason, the Court maintained that the subcontractor’s insurer (Amerisure) owed the general contractor’s insurer (Travelers) the reasonable attorney’s fees incurred in the defense of the general contractor in the underlying lawsuit:

 

When Amerisure [subcontractors’ insurer] failed to step up, Travelers [general contractor’s insurer] did what Amerisure should have done: Travelers provided Yates [general contractor] a defense. The attorneys Travelers hired chose to defend the case not only by answering the claims but also by asserting third-party claims against subcontractors, including Jemco [stucco subcontractor]. Travelers paid the fees and costs incurred in connection with the third-party claims, apparently concluding that this was the best strategy for defending the claims and that its duty to defend Yates thus obligated it to pay for the third-party claims as well. There is support for that view. 

***

Had Amerisure provided a defense as it should have done, the attorneys it hired might or might not have made the  same strategic decision as the attorneys hired by Travelers. But now Amerisure can complain, at most, about unreasonable decisions, not about decisions that reasonably could have gone either way. As a leading commentator has put it, when an insurer breaches its duty to defend,

the insured is justified in assuming the defense of the action and is released from the contractual obligation to leave the management of the case to the insurer. Not only does the insurer lose the power to control the defense or dictate to the insured how the case should be handled, but the insurer cannot complain about the conduct of the defense by the insured or the negligent handling of the case by the insured’s attorney.

 

Travelers Property Casualty Co. of America, 161 F.Supp.3d at 1138-39 (internal citations omitted).

 

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.