In construction defect disputes, it is routine to see a claim known as a violation of building code claim. It is a statutory claim brought under Florida Statute s. 553.84.
Section 553.84 provides:
Notwithstanding any other remedies available, any person or party, in an individual capacity or on behalf of a class of persons or parties, damaged as a result of a material violation of this part or the Florida Building Code has a cause of action in any court of competent jurisdiction against the person or party who committed the material violation; however, if the person or party obtains the required building permits and any local government or public agency with authority to enforce the Florida Building Code approves the plans, if the construction project passes all required inspections under the code, and if there is no personal injury or damage to property other than the property that is the subject of the permits, plans, and inspections, this section does not apply unless the person or party knew or should have known that the material violation existed. For purposes of this section, the term “material violation” means a Florida Building Code violation that exists within a completed building, structure, or facility which may reasonably result, or has resulted, in physical harm to a person or significant damage to the performance of a building or its systems.
A recent federal district case examined a violation of building code claim when the dispute did not center on a “completed building, structure or facility.”
In WP Property Holdings I, LLC v. JR&co, Inc., 2026 WL 3561832 (M.D. Fla. 2026), a warehouse owner hired a contractor to install roof membrane on its existing roof, i.e., a roof replacement project. During the course of the project, the roof failed causing water intrusion. The warehouse owner sued the contractor and included a violation of building code claim under Florida Statute s. 553.84. The federal district court granted summary judgment on this claim in favor of the contractor because the claim did NOT involve a completed building:
Construction and repair work is generally a time-intensive affair. Until a job is done, the work will almost inevitably stand outside the building code. Take a roof replacement. The moment a contractor rips off an old roof, the building is obviously no longer code-compliant—and cannot become compliant again until the new roof is in place. Under [the owner’s] reading, every roofer would violate § 553.84 simply by starting the job, remaining perpetually liable until the final nail is driven. That makes no sense. Other legal doctrines—negligence, for one— more aptly govern how contractors manage an active job site. Section 553.84 does a different job: it ensures that the finished product complies with the code. Because [the contractor’s] work was still in progress, [the owner’s] statutory claim fails as a matter of law.
To bring the point home, [the owner] offers no precedent applying § 553.84 to ongoing repair or construction jobs. And every case the Court could find invoking this statute involved finished products.
WP Property Holdings, supra, at *2 (citations omitted).
Remember, when asserting a violation of building code claim, make sure the claim and dispute is focused on a “completed building, structure, or facility.”
Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.
