If you are involved on a construction project, make sure you understand your construction lien rights, which are a creature of statute. This includes making sure your lien is TIMELY recorded and includes the CORRECT information. If you are unsure of how to preserve and perfect your lien rights, then you want to work with construction counsel to advise you in this process and PREPARE your construction liens to avoid mistakes that are otherwise avoidable.
In Coastal Building Contractors, LLC v. Calixte, 2026 WL 332873 (Fla. 4th DCA 2026), a subcontractor recorded a construction lien on a residential project. Although it completed its work on December 1, 2022, it incorrectly stated in its lien that its completion date was October 21, 2022. Thus, when the subcontractor recorded the lien on February 16, 2023, the lien was untimely on its face. A year later, the subcontractor amended the lien with the correct final furnishing date, but the amendment was untimely. (A construction lien needs to be recorded within 90 days from the lienor’s final furnishing and a lien needed to be amended within this 90 day time frame. Based on the lien, more than 90 days elapsed from October 21, 2022, and the date the lien was recorded on February 16, 2023.)
The trial court dismissed the subcontractor’s lien for being untimely. The trial court further found the lien was not timely amended to reflect the accurate completion date (which would have made the lien timely).
The appellate court reversed because the lien was actually timely based on the subcontractor’s actual completion date, it just contained an error as to the final furnishing date in the lien. The appellate court found that the correct inquiry here was “whether that error [in the lien as to the completion date] prejudiced the homeowners. If no prejudice occurred, then the error falls within the statutory safe harbors and the lien is valid.” Coastal Building Contractors, supra, at *1.
The lien law contains a safe harbor which essentially provides that the negligent inclusion or omission of information in the lien does not invalidate an otherwise valid lien if it doesn’t prejudice / adversely affect the owner:
Although the lien notice included erroneous information (the wrong date) and excluded correct information (the right date), section 713.08 contains two safe-harbor provisions that might salvage the claim from such mistakes. First, “the negligent inclusion or omission of any information in the claim of lien which has not prejudiced the owner does not constitute a default that operates to defeat an otherwise valid lien.” § 713.08(3), Fla. Stat. (2022). And second, “errors in such claim of lien shall not, within the discretion of the trial court, prevent the enforcement of such lien as against one who has not been adversely affected by such omission or error.” § 713.08(4)(a).
***
The safe harbor analysis instead must ask whether the error prejudiced the owner. In a counterfactual world where no error occurred and the correct information was included, would things have played out differently for the [owner]? For example, did the error prevent them from understanding the claim and defending their rights with respect to it? Did they in good faith rely to their detriment on the erroneous information, or did they know the information was wrong, cross their fingers, and hope they had drawn bank error in their favor?
Coastal Building Contractors, supra at *2, 3.
While the safe harbor is helpful when it comes to mistakes, the reality is there is no reason to make a mistake as to the completion date, as such mistake should have been caught because it rendered the lien facially untimely.
Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.