Phone: (954) 361-4720   Email: Dadelstein@gmail.com
Florida Construction Legal Updates Logo
  • Home
  • About Me
  • Contact Me
  • Previous Articles

Tag Archives: account stated

SOMETIMES, BEING TOO CUTE WITH PLEADING ALLEGATIONS IS UNNECESSARY

Posted on June 2, 2018June 2, 2018 by Edward Garber

shutterstock_616259696There are times where being too darn cute with your pleading allegations is unnecessary and does not work.  But, the point is really that the cuteness is unnecessary.

 

In a Miller Act payment bond dispute in Boneso Brothers Construction, Inc. v. Sauer, Inc., 2018 WL 2387833 (N.D.Cal. 2018), a claimant asserted claims against a Miller Act payment bond surety for breach of the payment bond, breach of a subcontract, open account, and account stated.  The question is why would the claimant sue the payment bond surety for breach of subcontract (when the subcontract was not with the surety), and open account and account stated.  I have no clue, other than such claims appeared quite unnecessary when the claimant asserted an action on the Miller Act payment bond (which is what the surety is liable under — actions under the statutory payment bond).  Such claims were dismissed.  And, they should have been.

 

A claimant cannot navigate around an action under a Miller Act payment bond by suing the surety for breach of an underlying subcontract.  Such a claim would obviate any preconditions to suing the surety under the bond and extend the surety’s exposure.

 

In Florida, and elsewhere, an account stated and open account are distinct causes of action.

 

An account stated is a claim when there is an “agreement between persons who have had previous transactions, fixing the amount due in respect of such transactions, and promising payment.”  Farley v. Chase Bank, U.S.A., N.A., 37 So.3d 936, 937 (Fla. 4th DCA 2010) (quotation and citation omitted).  An “account stated requires an express or implied agreement between the parties that a specified balance is correct and due and an express or implied promise to pay the balance.”  Id.

 

An open account   “is an unsettled debt arising from items of work and labor, with the expectation of further transactions subject to future settlements and adjustments.”  Id. (quotation and citation omitted).  In an action on an open account, the claimant must actually attach a copy of the itemized account, unlike an account stated action.  Id.

 

The reality is none of these other claims would really apply to a Miller Act payment bond surety.  Moreover, the surety naturally was being indemnified by its payment bond-principal, so it is not like the surety put itself in a position where it affirmatively acknowledged the so-called “debt” the subcontractor claimed was owed.  The cuteness in trying to “throw the book” at the surety was not necessary, specifically when the subcontractor had an action on the Miller Act payment bond!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

Recent Posts

  • APPLICATION OF ORDINANCE AND LAW COVERAGE IN PROPERTY INSURANCE POLICY AND TWENTY-FIVE PERCENT RULE
  • RECOVERING ATTORNEY’S FEES AND ARGUING THE FEES ARE INEXTRICABLY INTERTWINED
  • APPLICABILITY OF FLORIDA’S BUILDING CODE IS A QUESTION OF LAW
  • THE PREFATORY WHEREFORE CLAUSES IN AGREEMENTS MATTER
  • SUBSTANTIATING TERMINATION FOR CONVENIENCE COSTS

Categories

  • 31 USC 3730
  • acceleration
  • additional insured
  • administrative dispute resolution
  • anticipatory repudiation
  • appraisal
  • Arbitration
  • Assignments
  • Associations (Condo / Homeowners)
  • Assumption of Liability Agreements
  • attorneys fees
  • Bankruptcy
  • bid protest
  • breach of contract
  • building code
  • cardinal change
  • caveat emptor
  • CCNA
  • Changes / Change Orders
  • Charts
  • commercial impracticability
  • competent substantial evidence
  • conditions precedent
  • Construction Defects
  • constructive eviction
  • Consultant's corner
  • Contract Disputes Act
  • Contract Drafting
  • copyright infringement
  • cumulative impact
  • Damages
  • Davis Bacon Act
  • Defective Specifications
  • Delay Damages
  • Design Professionals
  • design-build
  • differing site conditions
  • Discovery
  • dispute resolution
  • Economic Loss Rule
  • economic waste
  • escrow agent
  • estoppel
  • exculpatory provision
  • Expert witnesses
  • False Claims Act
  • First cost and betterment
  • Florida Deceptive and Unfair Trade Practices Act
  • fraud
  • General Agreement of Indemnity
  • genuine issue of material fact
  • Government Contracting
  • home office overhead
  • home office overhead / Eichleay
  • horizontal immunity
  • implied covenant of good faith
  • Indemnification
  • injunctions
  • Insurance
  • intended third party beneficiary
  • interpleader
  • Johnson v. Davis
  • lender liability
  • Licensing
  • Lien
  • liquidated damages
  • lis pendens
  • lost profits
  • material breach
  • material escalation
  • Miller Act
  • mortgage foreclosure
  • Negligence
  • notice
  • novation
  • Pay-When-Paid
  • payment bond
  • performance bond
  • Pleadings
  • Premise Liability
  • promissory note
  • prompt payment act
  • Public Procurement
  • Quick Note
  • Real Estate Deposits
  • Releases
  • rental supplier
  • requests for equitable adjustment
  • safety
  • set-off
  • slander of title
  • Sovereign Immunity
  • Spearin doctrine
  • specially fabricated materials
  • Spoliation of Evidence / Document Management
  • statute of frauds
  • statute of limitations
  • subcontractor claims against government
  • Subrogation
  • Substantial completion
  • substituting materials
  • Successor Liability
  • summary judgment
  • suspension
  • teaming agreement
  • Termination for Convenience
  • termination for default
  • tortious interference
  • trade secret
  • UCC
  • Uncategorized
  • Underground Facility Damage Prevention and Safety Act
  • unjust enrichment
  • unlicensed contracting
  • unusually severe weather
  • Venue
  • video conference
  • warranties
  • weather
  • webinar
  • workers compensation

David Adelstein

Phone: (954) 361-4720
Email: Dadelstein@gmail.com

Navigation

  • Home
  • About Me
  • Contact Me
  • Archive
Copyrights © Florida Construction Legal Updates. Website By Brand Partners.