APPRECIATING THE RISKS OR FRUSTRATIONS OF ARBITRATION


Arbitration, just like litigation, can come with its own risks and frustrations. Once an arbitration award is rendered, the prevailing party will usually file an action or move to compel a circuit court to confirm the arbitrator’s award so that the award is turned into a judgment. However, a party that does not like the arbitrator’s award, will try to move to modify or vacate the award in accordance with Florida’s Arbitration Code (Florida Statutes Chapter 682). Although there are specific statutory grounds in order to move to modify or vacate an arbitrator’s award (and the motion must be filed within a specific window of time – typically, 90 days after delivery of the award), non-prevailing parties will still make an effort to vacate or modify the award with the circuit court within their required time parameters. The bases to modify or vacate an award are different than appellate rights afforded to litigants in court because an arbitration award is not supposed to be vacated or modified if an arbitrator erred as to the law.

 

The case of Wells v. Castro, 38 Fla. L. Weekly D1509a (Fla. 3d DCA 2013), illustrates certain frustrations. Without going into the factual details of the dispute, an arbitrator entered an award in favor of a claimant (party demanding arbitration) against one respondent (party responding to the demand for arbitration) and against the claimant as to another respondent. All of the parties agreed that the arbitrator is vested with the authority to determine the prevailing party for purposes of being entitled to attorneys’ fees. The respondent that prevailed as to the claimant’s claim wanted to be the prevailing party in order to recover its attorneys’ fees. However, the arbitrator found that neither party was the prevailing party meaning neither the respondent nor claimant would be entitled to recover their attorneys’ fees (as to the claimant’s claim against the prevailing respondent). Notably, under the Florida Supreme Court’s decision in Trytek v. Gale Indus., Inc., 3 So.3d 1194 (Fla. 2009), a court is to look at which party prevailed on the significant issues in the case for purposes of determining the prevailing party and has discretion to determine that there is not a prevailing party; stated differently, there is now uncertainty as to whether a party will be deemed the prevailing party and be entitled to their attorneys’ fees under the “significant issues” standard.

 

The respondent that prevailed moved the circuit court to essentially modify the arbitration award arguing that the arbitrator erroneously concluded that neither party was the prevailing party and that the respondent should have been deemed the prevailing party because it prevailed as to the claimant’s claims. The trial court granted the motion and deemed the respondent the prevailing party for purposes of being entitled to attorneys’ fees.

 

On appeal through a petition for a writ of mandamus (in this case, an appeal for the appellate court to order the trial court to confirm the arbitrator’s award), the Third District reversed the trial court maintaining: (a) the parties agreed to have the arbitrator determine the issue of prevailing party for purposes of attorneys’ fees (and need to live by that determination) and (b) an arbitrator’s error of law is not a basis to vacate or modify an award.   Thus, if the arbitrator erred in determining the prevailing party under Florida caselaw, the parties need to live with that determination because they agreed to have the arbitrator determine this issue in their arbitration.

 

While there are certain benefits to arbitration, it can come with its own risks and frustrations.  Again, the reasons to modify or vacate the award are limited under Florida statute and not designed to correct an arbitrator’s potential errors in law.  Also, if the parties want the arbitrator to determine the prevailing party for purposes of attorneys’ fees (which makes sense since the arbitrator will be the most familiar with the factual nature of the dispute), the parties will more than likely have to live by that determination.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CAREFUL DRAFTING OF ARBITRATION PROVISIONS TO ENSURE THE STATUTE OF LIMITATIONS APPLIES TO CLAIMS RESOLVED THROUGH ARBITRATION


Many construction contracts include arbitration provisions as the means to resolve a dispute instead of resorting to litigation.  Certain owners prefer to resolve their disputes with contractors through arbitration and certain contractors, likewise, prefer to resolve their disputes with subcontractors through arbitration.

 

The case of Raymond James Financial Services, Inc. v. Phillips, 36 Fla. L. Weekly D2479a (2d DCA 2011), certified the following question to the Florida Supreme Court:

 

“Does Section 95.011, Florida Statutes, apply to arbitration when the parties have not expressly included a provision in their arbitration agreement stating that it is applicable.”

 

While this case was not a construction case, the question certified to the Florida Supreme Court was a fundamental issue that applied to ALL arbitration provisions.  Section 95.011 is included in Florida Statutes Chapter 95 (“Chapter 95”) dealing with the statute of limitations for actions.  The statute of limitations requires lawsuits to be brought within the specified timeframe set forth in Chapter 95 or else the action is time-barred, meaning it cannot properly be asserted under the law.  In this case, however, the Second District found that there was nothing in the arbitration provision at-issue that required actions to be brought within the limitations periods set forth in Chapter 95 and, along these lines, nothing in Chapter 95 clarified that the statutes of limitations for actions was intended to apply to disputes resolved through arbitration.

 

This decision was crucial because if the statute of limitations is not intended to apply to disputes resolved through arbitration, and nothing in the arbitration provision clarifies that the statute of limitations periods set forth in Chapter 95 are intended to apply, then there is technically NO time period for when a dispute needs to be initiated because they could never be time-barred under the law.  The corollary of this is that it could open arbitration floodgates because parties that thought they could no longer bring an arbitration claim under the law could now assert an argument that their claim was never time-barred under the law.

Luckily, the Florida Supreme Court answered the Second District’s certified question in the affirmative holding that the statute of limitations DOES APPLY TO ARBITRATION PROCEEDINGS!!! See Raymond James Financial Services, Inc. v. Phillips, 126 So.3d 186 (2013).  This means that the defense of statute of limitations can be raised in an arbitration proceeding as a basis to bar an untimely filed claim.

 

With respect to construction contractors, parties that utilize the AIA Agreements (promulgated by the American Institute of Architects) that select arbitration as the dispute resolution procedure should still safely ensure the agreement contains a provision to the effect:

 

“In no effect shall the demand for arbitration be made after the date when institution of legal or equitable proceedings based on such claim would be barred under the applicable statute of limitations.”

 

The AIA standard form agreements usually include this provision almost verbatim.  This provision should not be deleted.  When drafting or negotiating an AIA agreement that includes an arbitration provision, a party should ensure that language to the effect is included in the agreement and not deleted or substantially manipulated so as to render it ambiguous.  Also, parties that do not use an AIA agreement and prefer arbitration need to draft such a provision or mimic one after the provision used in the standard form AIA agreements to ensure the statute of limitations applies to claims / disputes resolved through arbitration no matter what.  

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.