SURETY REQUIRING COLLATERAL SECURITY UNDER GENERAL AGREEMENT OF INDEMNITY

In order to procure bonds (payment and performance bonds), you need to sign a General Agreement of Indemnity (referred to as the “GAI”) with the surety (bonding company). It does not matter the surety issuing the bonds, the terms and conditions in the General Agreement of Indemnity are largely consistent. These terms and conditions are one-sided written in favor of the surety. This is because bonds are not insurance. When a surety issues such bonds, it is doing so under the premise that it will get reimbursed every penny that it incurs relative to its exposure- whether incurred in attorney’s fees, consulting costs, or remediating a default or claim under the applicable bond. The General Agreement of Indemnity is one of the most powerful contracts in construction and is a contract that is not to be taken lightly.  It provides the surety numerous rights in the event of a claim.

A recent case, Travelers Casualty and Surety Co. of America v. Hemmer Construction, 2026 WL 2164439 (M.D.Fla. 2026), serves as an example. A bonded contractor was terminated for default on a construction project. The surety entered into a takeover agreement and assessed its exposure at north of $15 Million. The surety demanded that the contractor post collateral with the surety in the amount of north of $15 Million. The contractor refused and the surety filed a lawsuit that included a preliminary injunction requiring the contractor to post collateral security and furnish financial records.  There were other asserted claims such as indemnification. The contractor and its indemnitors countered arguing that its affirmative defenses should apply to bar the preliminary injunction, with the key defense being that the surety engaged in bad faith in assessing exposure and entering into the takeover agreement.

The contractor lost and the court granted the preliminary injunction.  Here is why. These are important considerations if you are ever in a situation where your surety is demanding collateral:

 

(1) The contractor and its indemnitors bore the burden of proof as to its affirmative defenses and, in particular at the preliminary injunction stage, the likelihood of success. “So Indemnitors must demonstrate their likelihood of success on such defenses. They fail to do so.” Hemmer Construction, supra, at *3.

 

(2) The key defense of bad faith was irrelevant at the preliminary injunction stage. “Collateralization and indemnification are distinct concepts. The sole issue before the Court is whether [surety] is entitled to collateral security; [surety] does not seek indemnification in its motion for preliminary injunction. And courts have held that ‘[w]hile issues of bad faith may be relevant to Plaintiff’s claim for indemnification under the [Indemnity] Agreement, they are not relevant to Plaintiff’s contractual right to collateral security.” Hemmer Construction, supra, at *3 (citation omitted).

 

(3) The defense of bad faith won’t apply unless the contractor and its indemnitors post the collateral security. “Courts routinely hold that ‘defendants’ failure to post collateral precludes the defendants’ relying on the defense of bad faith.’” Hemmer Construction, supra, at *3 (citation omitted).

 

(4) And as an aside, the contractors and its indemnitors did not substantiate bad faith. “ ‘To show bad faith, an indemnitor must show that the surety acted with ‘deliberate malfeasance,’ which is an intentional wrongful act that the actor has no legal right to do or any wrongful conduct which affects, interrupts, or interferes with the performance of official legal duty.’ ‘[A] lack of diligence or negligence is not the equivalent of bad faith, and even gross negligence is not the same as bad faith.” Hemmer Construction, supra, at *3 (citations omitted). Stated differently, proving that the surety acted in bad faith is a very difficult burden of proof!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

QUICK NOTE: PRINCIPAL ARGUING BAD FAITH AGAINST ITS OWN SURETY

The General Agreement of Indemnity a principal executes with its surety is the most–and certainly one of the most–powerful documents in construction. Consider this when executing a General Agreement of Indemnity in order to procure bonds.

In a recent case, the surety sought indemnity from its indemnitors (including the bond principal) after resolving a termination claim against its principal. One of the defenses the indemnitors raised was “bad faith,” i.e., the surety engaged in bad faith in settling the obligee’s performance bond claim.

A principal arguing bad faith against its own surety is a difficult defense. I fully understand why it is raised at times but, nevertheless, it is still difficult because here are the elements that must be proven in order to prevail on the bad faith claim claim against your own surety: “1) the surety lacked a reasonable basis for paying the claims; and 2) the surety knew or recklessly disregarded its lack of a reasonable basis for doing so….Bad faith can also be demonstrated by a showing of recklessness or improper motive such as self-interest or ill will.”  Travelers Cas. & Sur. Co. of America v. Bunting Graphics, Inc., 2025 WL 1665595, *4 (W.D.Pa. 2025) (internal citations and quotations omitted). 

In this recent case, the district court found the bad faith argument unpersuasive because the indemnitors could not show the surety lacked a reasonable basis in paying the obligee’s performance bond claim:

As outlined above, indemnity contracts, like the one here, grants [the surety] broad discretion in settling claims. Such express discretion is consistent with construction and surety industry practices in order to prevent indemnity claims from becoming mired in litigation. The “under belief it was liable” phrasing permits sureties to evaluate and resolve claims without the necessity of litigation to determine the merits of a claim or to establish an indemnitor’s liability to the surety. Thus, [the surety’s] actions and decision to pay the claim were within its contractual discretion and [the principal] has not met its burden to produce evidence sufficient to establish bad faith.
***
The record does not support a lack of reasonableness or slipshod evaluation by [the surety]. Such conduct does not comport with [the principal’s] bad faith narrative.

Bunting Graphics, Inc., supra, at *5.

Remember, the General Agreement of Indemnity grants your surety power to exercise rights if a claim is made against your bonds, even if you think the claim is bogus. Countering that the surety acted in bad faith in resolving or paying an obligee’s bond claim has proven to be a difficult hurdle largely based on the discretion granted to a surety in the General Agreement of Indemnity.

 

  

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

LET’S TALK ABOUT A STATUTORY FIRST-PARTY BAD FAITH CLAIM AGAINST AN INSURER

Let’s talk about a statutory first-party bad faith claim against an insurer under Florida law. A recent opinion, discussed below, does a nice job providing a synopsis of a first-party statutory bad faith claim against an insurer:

The Florida Legislature created the first-party bad faith cause of action by enacting section 624.155, Florida Statutes, which imposes a duty on insurers to settle their policyholders’ claims in good faith.  The statutory obligation on the insurer is to timely evaluate and pay benefits owed under the insurance policy.  The damages recoverable by the insured in a bad faith action are those amounts that are the reasonably foreseeable consequences of the insurer’s bad faith in resolving a claim, which include consequential damages. 

“[A] statutory bad faith claim under section 624.155 is ripe for litigation when there has been (1) a determination of the insurer’s liability for coverage; (2) a determination of the extent of the insured’s damages; and (3) the required [civil remedy] notice is filed pursuant to section 624.155(3)(a).” 

“An insured may obtain a determination of the insurer’s liability and the extent of their damages by litigation, arbitration, settlement, stipulation, or the payment of full policy limits.”  Additionally, payment of an appraisal award by the insurer constitutes a determination of the insurer’s liability and the extent of the insured’s damages. 

Cingari v. First Protective Ins. Co., 49 Fla.L.Weekly D89a (Fla. 4th DCA 2023) (internal citations omitted).

The fact pattern in this case is somewhat nutty. This case dealt with a homeowner’s property insurance policy. The homeowners discovered cracks in their walls and submitted an insurance claim. The insurer issued two partial payments.  However, the homeowner felt its insurer was not properly adjusting the claim and filed a Civil Remedy Notice as the perquisite for a statutory bad faith claim. The homeowner subsequently invoked the appraisal process in the policy. The insurer agreed and the claim proceeded through the appraisal process (after a lawsuit was initiated for the court to appoint the umpire to preside over the appraisal process). The umpire found damages more than the partial payments paid by the insurer resulting in the insurer paying the policy limits under the policy.  The homeowner then filed a bad faith action against its insurer for failing to timely and properly adjust the loss. The insurer moved for summary judgment arguing that AFTER it paid the policy limits it discovered that the loss (that it paid for) was, in fact, excluded under the policy by an earth settlement exclusion. The trial court agreed with the insurer that because there was no coverage, there could be no bad faith claim against the insurer.

The appellate court concluded differently under the facts of the case: “we conclude the trial court erred in accepting the insurer’s argument that because no coverage existed, the homeowner was not entitled to litigate whether the insurer acted in bad faith.” Cingari, supra.  Why did the appellate court conclude differently? Two main reasons:

(1) The insurer never raised that “no coverage exists” to the umpire during the appraisal process.

(2) “[T]he focus of a first-party bad faith claim is whether the insurer in good faith timely and property investigated and resolved claims filed by the insured.” Cingari, supra. In other words, the focus centers on the insurer’s investigation of the cause of the loss. Remember, the insurer argued it did not discover the basis of the exclusion until AFTER it paid the policy limits per the appraisal process.

[T]he insurer’s statements that it ‘proceeded under an erroneous policy interpretation’ in the umpire appointment suit [for the appraisal] and ‘gratuitously’ paid the policy limits and appraisal award certainly raise an inference that the insurer did not properly investigate the claim. The homeowner argued…that the failure to properly investigate caused the insurer to improperly extend settlement of the claim through the appraisal process. In doing so, the insurer arguably violated the requirements in section 624.155(1)(b)1. and 2., Florida Statutes (2020), to ‘attempt[] in good faith to settle claims’ and ‘promptly settle claims[.]

 Cingari, supra.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

TWO WORTHY INSURANCE TOPICS: (1) BAD FAITH, AND (2) SETTLING WITHOUT INSURER’S CONSENT

The recent Eleventh Circuit Court of Appeals’ decision, American Builders Insurance Company v. Southern-Owners Insurance Company, 56 F.4th 938 (11th Cir. 2023), is an insurer versus insurer case that touches on two important insurance topics: (1) common law bad faith against an insurance company, and (2) an insurer’s affirmative defense that an insured settled a claim without its consent.  The Eleventh Circuit provides invaluable legal discussion on these topics that any insured (and an insured’s counsel) need to know and appreciate.  While this article won’t go into the granular facts as referenced in the opinion, it will go into the law because it is the law the facts of a case MUST cater to and address.

In this case, a person performing subcontracting work fell from a roof without fall protection and became paralyzed from the waist down. The general contractor had a primary liability policy and an excess policy. The general contractor’s primary liability insurer investigated the accident and assessed the claim.  The subcontractor’s liability insurer, which was the primary insurance policy (the general contractor was an additional insured for work the subcontractor performed for the general contractor), did little to investigate and assess the claim and then refused to pay any amount to settle the underlying claim or honor its defense and indemnity obligation to the general contractor.

Both the general contractor’s primary insurer and excess insurer each tendered policy limits to settle the claim and avoid a bad faith claim by exposing the general contractor to more than policy limits, which was the determination had the matter proceeded to a trial.

The general contractor’s primary liability insurer then sued the subcontractor’s liability insurer for common law bad faith (based on equitable subrogation).  The subcontractor’s liability insurer, among other things, argued it should be absolved because its policy was breached when payment was made to the claimant without its consent. The case proceeded to trial and a jury found in favor of the general contractor’s primary liability insurer.  The subcontractor’s liability insurer appealed…and lost.

Common Law Bad Faith

[T]he critical inquiry in a bad faith [action] is whether the insurer diligently, and with the same haste and precision as if it were in the insured’s shoes, worked on the insured’s behalf to avoid an excess judgment. Additionally, any damages claimed by an insured in a bad faith case must be caused by the insurer’s bad faith. That is, the bad faith conduct must directly and in natural and continuous sequence produce[] or contribute[] substantially to producing such [damage], so that it can reasonably be said that, but for the bad faith conduct, the [damage] would not have occurred.

The bad faith inquiry is determined under the ‘totality of circumstances’ standard, and we focus not on the actions of the claimant but rather on the insurer in fulfilling its obligations to the insured. That said, a claimant’s actions –such as a decision not to offer a settlement-remain relevant in assessing bad faith. Insurers have obligations to advise the insured of settlement opportunities, to advise to the probable outcome of the litigation, to warn of the possibility of an excess judgment, and to advise the insured of any steps he might take to avoid [the] same,” as well as to investigate the facts, give fair consideration to a settlement offer that is not unreasonable under the facts, and settle, if possible, where a reasonably prudent person, faced with the prospect of paying the total recovery, would do so. These obligations … are not a mere checklist, however, and, as the Florida Supreme Court has explained, [a]n insurer is not absolved of liability simply because it advises its insured of settlement opportunities, the probable outcome of the litigation, and the possibility of an excess judgment.

Moreover, insurance companies occasionally have an affirmative duty to offer settlements.  Bad faith may be inferred from a delay in settlement negotiations which is willful and without reasonable cause. Thus, [w]here  liability is clear, and injuries so serious that a judgment in excess of the policy limits is likely, the insurer must initiate settlement negotiations. In such a case, where [t]he financial exposure to [the insured] [i]s a ticking time bomb and [s]uit c[an] be filed at any time, any delay in making an offer under the circumstances of this case even where there was no assurance that the claim could be settled could be viewed by a fact finder as evidence of bad faith.

American Builders Insurance Company, supra, at 944-45 (internal quotation and citation omitted).

Here, the jury reasonably found that the subcontractor’s liability insurer “acted in bad faith because it delayed acting on its duty to investigate and settle [the claimant’s] claim.” American Builders Insurance Company, supra at 945.  The facts “could lead a reasonable jury to conclude that the [subcontractor’s liability insurer] delayed its investigation instead of attempting ‘to resolve the coverage dispute promptly’ or using ‘diligence and thoroughness.’” Id. at 946 (internal quotation and citation omitted).

Here, a reasonable jury could also find that the subcontractor’s liability insurer caused the general contractor’s liability insurer damages.  The subcontractor’s liability insurer wanted to focus on the claimant and his attorney’s action.  This was shot down. “Of course, there’s a difference between focusing on a claimant’s actions, which would be improper, and factoring a claimant’s actions into the totality of circumstances analysis, which is not improper. In this case, though, [the subcontractor’s liability insurer] flipped Florida law on its head and exclusively focused on [the claimant and his attorney’s] actions.”  American Builders Insurance Company, supra, at 947 (internal quotation and citation omitted).

Insurer “Consent” Affirmative Defense

The subcontractor’s liability insurer argued that the general contractor’s primary liability insurer breached the subcontractor’s liability insurance contract “by failing to receive its consent before settling with [the claimant].”  American Builders Insurance Company, supra, at 944.   This was also shot down.

Subcontractor’s liability insurance contract provided:

[N]o insured will, except at the insured’s own cost, voluntarily make a payment, assume any obligation, or incur any expense, other than for first aid, without our consent. [T]his language required the insured to obtain the insurer’s consent before settling. That is, while an insured is free to enter into a reasonable settlement when its insurer has wrongfully refused to provide it with a defense to a suit, … the insured is not similarly free to independently engage in such settlements where, as here, the insurer had not declined a defense to suit.

The Florida Supreme Court requires an insurer to establish three things in order to succeed on this affirmative defense: (1) a lack of consent; (2) substantial prejudice to the insurer; and (3) diligence and good faith by the insurer in attempting to receive consent. The first element has a few exceptions. The insured may settle without obtaining consent if the insurer wrongfully refused to provide [the insured] with a defense to a suit, or offers a conditional defense that the parties cannot agree upon.  Moreover, even if the insured was obliged to obtain consent, the failure to do so is not an affirmative defense unless the insurer also establishes substantial prejudice and evinces good faith in bringing about the cooperation of the insured.

American Builders insurance Company, supra, at *947-48.

Here, the issue of whether the general contractor’s primary liability insurer needed consent was not at-issue.  It did.  But the subcontractor’s liability insurer still needed to establish substantial prejudice and good faith, and the jury could find it proved neither, which it did.  American Builders Insurance Company, supra, at *948.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

ELEVENTH CIRCUIT’S NOTEWORTHY DISCUSSION ON BAD FAITH INSURANCE CLAIMS

The Eleventh Circuit Court of Appeal’s opinion in Pelaez v. Government Employees Insurance Company, 2021 WL 4258821 (11th Cir. 2021) is a non-construction case that discusses the standard for pursuing a bad faith claim against an insurer.   This case dealt with an automobile accident. While the facts of the case are interesting and will be discussed, the takeaway is the Eleventh Circuit’s noteworthy discussion on the standard for bad faith claims and how they should be evaluated.  This discussion is included below–with citations–because while the term “bad faith” is oftentimes thrown around when it comes to insurance carriers, there is indeed an evaluative standard that is applied to determine whether an insurance carrier acted in bad faith.

In Pelaez, a high school student driving a car crashed with a motorcycle.  The motorcycle driver was seriously injured and airlifted to the hospital.  The accident was reported to the automobile liability insurer of the driver of the car.  The insurer through its investigation initially believed the motorcycle driver was contributory negligent.  Eleven days after the crash, after learning additional information, the insurer tendered its bodily injury policy limits of $50,00 to the motorcycle driver even though it never received a settlement demand. The insurer sent a tender package to the motorcycle driver’s lawyer that included a $50,000 check for the bodily injury claim and a proposed release.  The accompanying letter told the attorney to contact the insurer with any questions about the release and to edit the proposed release with suggested changes.  The insurer also wanted to inspect the motorcycle in furtherance of adjusting the property damage claim which also had a policy limit of $50,000.  A location of where the motorcycle could be inspected was never provided.

Shortly thereafter, counsel for the motorcycle driver rejected the policy limits tender offer claiming that the proposed release form included with the tender package was overbroad (and it was) since it did not specifically carve-out property damage claims.  The insurer again told the lawyer to edit the release and asked for the location of the motorcycle because its intent was to treat the bodily injury and property damage claims separate.  Instead of a response, the motorcycle driver sued the driver of the car.   Clearly, the objective was not the $50,000 policy limits, but the potential bad faith exposure.

The property damage claim for the motorcycle ultimately settled but the bodily injury claim continued to trial.  During trial, the parties consented to a judgment where a judgment was entered against the driver of the car for $14,900,000; the parties stipulated that the judgment shall not be recorded and cannot be collected against the car driver.  Instead, the motorcycle driver agreed to collect solely against the car driver’s insurance policy.  The car driver’s insurer was not a party to the judgment or stipulation.

Thereafter, both the car and motorcycle drivers sued the car driver’s automobile liability insurer for bad faith refusal to settle.  The trial court entered summary judgment in favor of the car driver’s insurer finding no reasonable jury could find the insurer acted in bad faith under the totality of the circumstances.  The Eleventh Circuit affirmed the trial court’s summary judgment in favor of the insurer based on the totality of circumstances including the insurer’s efforts to settle the bodily injury claim for policy limits. In doing so, the Eleventh Circuit includes the following noteworthy discussion on such bad faith insurance claims:

“It has long been the law of [Florida] that an insurer owes a duty of good faith to its insured.” Berges v. Infinity Ins. Co., 896 So. 2d 665, 672 (Fla. 2004). The duty has been well-defined for more than 40 years, since the Florida Supreme Court described it in Boston Old Colony Ins. Co. v. Gutierrez, 386 So. 2d 783 (Fla. 1980):

An insurer, in handling the defense of claims against its insured, has a duty to use the same degree of care and diligence as a person of ordinary care and prudence should exercise in the management of his own business. For when the insured has surrendered to the insurer all control over the handling of the claim, including all decisions with regard to litigation and settlement, then the insurer must assume a duty to exercise such control and make such decisions in good faith and with due regard for the interests of the insured. This good faith duty obligates the insurer to advise the insured of settlement opportunities, to advise as to the probable outcome of the litigation, to warn of the possibility of an excess judgment, and to advise the insured of any steps he might take to avoid same. The insurer must investigate the facts, give fair consideration to a settlement offer that is not unreasonable under the facts, and settle, if possible, where a reasonably prudent person, faced with the prospect of paying the total recovery, would do so.

Id. at 785; see also, e.g., Harvey v. GEICO Gen. Ins. Co., 259 So. 3d 1, 6–7 (Fla. 2018) (quoting Boston Old Colony to define the duty); Kropilak v. 21st Century Ins. Co., 806 F.3d 1062, 1067–68 (11th Cir. 2015) (same). “Breach of this duty may give rise to a cause of action for bad faith against the insurer.” Perera v. U.S. Fid. & Guar. Co., 35 So. 3d 893, 898 (Fla. 2010). Florida’s bad faith law is “designed to protect insureds who have paid their premiums and who have fulfilled their contractual obligations by cooperating fully with the insurer in the resolution of claims.” Berges, 896 So. 2d at 682.

Where “liability is clear, and injuries so serious that a judgment in excess of the policy limits is likely, an insurer has an affirmative duty to initiate settlement negotiations.” Harvey, 259 So. 3d at 7 (quotation marks omitted). “In such a case, where the financial exposure to the insured is a ticking financial time bomb and suit can be filed at any time, any delay in making an offer … even where there was no assurance that the claim could be settled could be viewed by a fact finder as evidence of bad faith.” Id. (cleaned up).

“In Florida, the question of whether an insurer has acted in bad faith in handling claims against the insured is determined under the ‘totality of the circumstances’ standard.” Berges, 896 So. 2d at 680. Indeed “the critical inquiry” in a bad faith action is not whether an insurer met the obligations set out in Boston Old Colony but instead “whether the insurer diligently, and with the same haste and precision as if it were in the insured’s shoes, worked on the insured’s behalf to avoid an excess judgment.” Harvey, 259 So. 3d at 7 (noting that the Boston Old Colony obligations “are not a mere checklist”).

The “focus in a bad faith case is not on the actions of the claimant but rather on those of the insurer in fulfilling its obligations to the insured.” Berges, 896 So. 2d at 677. For that reason, a claimant’s “actions can[not] let the insurer off the hook when the evidence clearly establishes that the insurer acted in bad faith in handling the insured’s claim.” See Harvey, 259 So. 3d at 11 (emphasis added) (rejecting the “conclusion that where the [claimant]’s own actions[ ] even in part cause the judgment, the insurer cannot be found liable for bad faith”) (quotation marks omitted); id. (noting that “an insurer can[not] escape liability merely because the [claimant]’s actions could have contributed to the excess judgment”) (emphasis added and footnote omitted); id. at 12 (rejecting the idea that, “regardless of what evidence may be presented in support of the [claimant]’s bad faith claim,” the “insurer could be absolved of bad faith” if it “can put forth any evidence that the [claimant] acted imperfectly during the claims process,” which “would essentially create a contributory negligence defense for insurers” that is “inconsistent with [Florida’s] well-established bad faith jurisprudence”).

 “[N]egligence is not the standard” for evaluating bad faith actions, Harvey, 259 So. 3d at 9, but “[b]ecause the duty of good faith involves diligence and care in the investigation and evaluation of the claim against the insured, negligence is relevant to the question of good faith,” Boston Old Colony, 386 So. 2d at 785. And “[a]lthough bad faith is ordinarily a question for the jury, both this Court and Florida courts have granted summary judgment where there is no sufficient evidence from which any reasonable jury could have concluded that there was bad faith on the part of the insurer.” Eres, 998 F.3d at 1278 (cleaned up); see also State Farm Fire & Cas. Co. v. Zebrowski, 706 So. 2d 275, 277 (Fla. 1997) (concluding, in a statutory third-party bad faith action, that summary judgment was appropriate). “While an overbroad release can create a jury question about bad faith, it doesn’t necessarily do so.” Eres, 998 F.3d at 1279.

Palaez, supra, at *4-6.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

STATUTORY BAD FAITH CLAIM NOT TOLLED MERELY BECAUSE PROPERTY INSURER INVOKES APPRAISAL PER THE POLICY

A statutory bad faith claim is NOT tolled merely because the property insurer invoked the appraisal process in the property insurance policy.  Zaleski v. State Farm Florida Ins. Co., 46 Fla.L.Weekly D416b (Fla. 4th DCA 2021).  A statutory bad faith claim requires the insured to comply with Florida Statute s. 624.155 and submit a civil remedy notice with Florida’s Department of Financial Services identifying the bad faith violations.  The insurer is given sixty days to cure the asserted bad faith violations (typically involving non-payment or the payment of a lowball amount due to failure to settle a claim in good faith).

A statutory bad faith claim under s. 624.155 “is ripe for litigation when there has been (1) a determination of the insurer’s liability for coverage; (2) a determination of the extent of the insured’s damages; and (3) the required [civil remedy] notice is filed pursuant to section 624.155(3)(a).”  Zaleski, supra (citation omitted).

In Zaleski, the property insurer argued that the sixty-date statutory cure period under section 624.155 should be tolled when it invokes the appraisal process within this sixty-day window; and because the insurer timely paid the award rendered by the appraiser, there can be no statutory bad faith.  This argument was rejected:

The appraisal award is not a condition precedent to [the property insurer’s] obligation to pay Homeowners a fair amount due under the policy.  To allow the sixty-day cure period to toll at the invocation of the appraisal process would allow insurers to cause delay or otherwise act in bad faith while escaping liability as long as it makes payment within the sixty-day time period of the appraisal award.  This would negate and frustrate the purpose of the statute.

 Zaleski, supra.

Of importance, when an insurer receives a statutory bad faith claim (i.e., the civil remedy notice), it

[M]ust evaluate a claim based upon proof of loss required by the policy and its expertise in advance of a determination by a court or arbitration.  In other words, when an insurer receives a claim, it has an independent duty to evaluate the claim in advance of a determination of damages and take timely, independent action. Thus, the focus in a bad faith case is not whether the insurer ultimately paid the amounts due under the policy, but whether it acted reasonably in evaluating a claim prior to the determination of damages.

For example, “[a] fair evaluation would be evidence that an insurer did not action in bad faith.  But a lowball offer made in bad faith is not cured by an insurer ultimately paying what it is later found to owe via appraisal process.” The determination of good faith or bad faith, however, “is usually a question for the finder of fact.”

Zaleski, supra, (internal citations omitted).

As I have mentioned in prior articles, it is key to work with qualified counsel when pursuing a property insurance claim and, of course, a bad faith insurance claim.  Counsel can ensure all rights are preserved when it comes to preserving a bad faith claim and preparing and submitting the required civil remedy notice that starts the clock for the sixty-day cure period.  Notably, in Zaleski, the insurer recognized coverage and paid what the insured believed, and what turned out to be, a lowball amount.  The insured filed its civil remedy notice to start the cure period.  The insurer then invoked the appraisal process hoping it would cure the sixty-day cure period; it did not.  The appraiser determined the insured was entitled to almost the amount the insured’s adjuster valued the claim, which the insurer paid.  However, as discussed, the invocation of the appraisal process and the timely payment of the appraiser’s award had NO bearing on whether the insurer committed bad faith based on its initial lowball payment.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUITE NOTE: EXTRA-CONTRACTUAL, CONSEQUENTIAL DAMAGES AGAINST PROPERTY INSURER MUST BE PURSUED IN SEPARATE BAD FAITH CLAIM

Unfortunately, the Fifth District Court of Appeals’ holding in this case did not last long.   As discussed here, the Florida Supreme Court, quashing the Fifth District’s decision, ruled that an insured cannot recover extra-contractual, consequential damages against his/her/its property insurer absent a separate bad faith claim.  This means that arguing extra-contractual damages against a property insurer claiming the damages flow from the insurer’s breach of the insurance contract are NOT going to fly in an action claiming the insurer breached the terms of the policy.  An insured will need to pursue a separate bad faith insurance claim against his/her/its insurer to recover such damages.    Make sure you consult with counsel when it comes to pursuing a property insurance claim including understanding damages covered by the policy and separate damages that may flow from a bad faith insurance claim.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

FIRST-PARTY STATUTORY BAD FAITH – 60 DAYS TO CURE MEANS 60 DAYS TO CURE

In a first party bad-faith lawsuit, such as a bad faith claim against an insured’s property insurer, there are three requirements that must be met before the bad faith lawsuit is filed: “‘(1) determination of the insurer’s liability for coverage; (2) determination of the extent of the insured’s damages; and (3) the required notice must be filed under section 624.155(3)(a).’” Fortune v. First Protective Ins. Co., 45 Fla. L. Weekly D2092a (Fla. 2d DCA 2020) (citation omitted).

The third requirement is for the insured to file a Civil Remedy Notice (known as a “CRN”) as a condition precedent to filing a statutory bad faith lawsuit giving the insurer 60 days’ notice of the bad faith violation and to cure the violation, i.e., pay the claim if the violation is payment.

A very common bad faith payment violation is the assertion that the insurer did NOT attempt “in good faith to settle claims when, under the circumstances, it could and should have done so, had it acted fairly and honestly towards its insured and with due regard for his or her interests.”  Fla. Stat. s. 624.155(1)(b)(1).

Can a statutory bad faith action still be triggered if the insurer invokes the appraisal process per the insurance policy BEFORE the insured files its CRN?   The answer is yes!

In Fortune, an insured suffered a loss stemming from a hurricane.  The insurer adjusted the loss, after applying the deductible and depreciation, at approximately $3,000 and paid that money to the insured.  The insured disputed this was a final amount for the loss and the insurer demanded appraisal per the policy.  The insured then filed a CRN to start the statutory bad faith process.  The insurer did NOT cure the violation—pay the claim—within the required 60-day period.  The parties went through appraisal and the umpire determined the loss to be approximately $120,000.  The insurer paid what it owed per the umpire’s award.  The insured then filed his bad faith lawsuit.  The trial court granted summary judgment in favor of the insurer finding there was no bad faith because the insurer instituted the appraisal process before the insured filed a CRN and then paid the award.

The Second District Court of Appeals reversed the summary judgment.

An insured is not precluded from filing a CRN prior to a determination of the insurer’s liability for coverage (requirement 1 above) or a determination of the extent of the insured’s damages (requirement 2 above).  Thus, the insured was within his rights to file a CRN after the insurer instituted the appraisal process.  See Fortune, supra (“Even if a policy requires the mediation or appraisal process to occur prior to suit being filed, an appraisal is not a condition precedent to the insurer fulfilling its obligation to fairly evaluate the claim and to either deny coverage or to offer an appropriate amount based on that fair evaluation.”).

Moreover, “an alleged payment violation [by the insurer] would require payment within the sixty-day cure period.”  Fortune, supra.  This means that the insurer invoking the appraisal process and then paying the umpire’s award AFTER the 60-day cure period expired does not cure a bad faith payment violation.

If you are dealing with a property insurance coverage claim or dispute, it is imperative that you work with counsel to ensure your rights are preserved.  In this case, the insured’s bad faith rights were preserved against the insurer by the insured filing a CRN even after the insurer instituted the appraisal process.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

YOUR BAD FAITH JURY INSTRUCTION AGAINST AN INSURER IS IMPORTANT

A statutory bad faith claim against an insurer is derived from Florida Statute s. 624.155.  A bad faith claim against a first party insurer, such as a property insurer, must be statutory.  Check out the hyperlink of the statute, but a party must first file a Civil Remedy Notice identifying the statutory violations to preserve the statutory bad faith claim giving the insurer an opportunity to cure.

In a noteworthy case, Cooper v. Federated National Insurance Company, 44 Fla. L. Weekly D2961a (Fla. 5th DCA 2019), the Fifth District Court of Appeal dealt with the jury instruction for an insured’s statutory bad faith claim against their property insurer.  The insured filed a bad faith claim predicated on the property insurer violating the provisions of Florida Statute s. 626.9541(1)(i)3, which involves unfair claim settlement practices.  The insured had a jury trial and submitted a proposed jury instruction regarding bad faith that tracked the very essence of their bad faith claim and was modeled after s. 626.9541(1)(i)(3).  The trial court, however, denied this jury instruction, instead adopting a standard jury instruction for bad faith.  The jury returned a verdict in favor of the property insurer and the insured appealed arguing it was reversible error for the trial court NOT to present to the jury their bad faith jury instruction.  The Fifth District agreed and ordered a new trial finding that the trial court’s failure to present the jury instruction amounted to a miscarriage of justice.

Florida’s standard bad faith jury instruction is not the be-all-end-all of jury instructions for bad faith. Specifically for a statutory bad faith claim, the standard jury instruction would not fully model a party’s theory of bad faith which would be modeled after a statutory violation.  The lack of a proper jury instruction is not compensated for by an attorney’s closing argument as to the insured’s theory of the case:

Leaving it to the parties’ attorneys to explain to the jury in closing argument what legal principles apply is an inadequate substitute for an accurate, relevant, and complementary instruction that contains legal principles not covered in a standard instruction.  Contrary to [the property insurer’s] argument, we do not believe that the standard bad faith jury instruction sufficiently informed the jury of all the relevant law regarding bad faith. Nor do we believe that, under the facts of this case, the acts constituting a violation of section 626.9541(1)(i)3. were subsumed within the standard jury instruction.

Cooper, supra (internal quotations omitted).

A jury instruction is important and is nothing to sneeze at.  Here, the Fifth District thought so as it reversed a jury’s verdict finding that the failure to include a bad faith jury instruction that modeled the theory of the case and specific statutory violations the insured was aiming to prove was reversible error.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

60-DAY CLOCK FOR STATUTORY BAD FAITH “CURE PERIOD” STARTS WHEN CIVIL REMEDY NOTICE ELECTRONICALLY FILED

 

The Second District Court of Appeal in Harper v. Geico General Insurance Company, 44 Fla.L.Weekly D618c (Fla. 2d DCA 2019) explained that the 60-day clock for a statutory bad faith cure period stars when the civil remedy notice is electronically filed with Florida’s Department of Financial Services:

Subsection 624.155(3)(d) plainly states that no action shall lie if the damages are paid or corrective action is taken within sixty days after the insured files the CRN [Civil Remedy Notice}. Under current procedures, an insured files a CRN with the Department electronically. See Fla. Admin. Code R. 69J-123.002(1). And while the Department also requires the insured to print a copy of the completed CRN from the Department’s website and send it to the insurer, the Department nevertheless considers the form to be “filed” when the insured clicks the “submit” button at the end of the electronic form. See Civil Remedy Notice of Insurer Violations FAQ, https://apps.fldfs.com/CivilRemedy/Help.aspx (follow “Continue” hyperlink; then follow “How do I file a Civil Remedy Notice?” hyperlink) (last visited Dec. 20, 2018). At that time, the CRN is assigned a “filing number” and any changes must be made by clicking on “edit filing.” Hence, the requirements of section 624.155(3)(d) are met when the insured electronically files the CRN with the Department, and that action starts the sixty-day cure period for the insurer.2 Therefore, we hold that the sixty-day cure period under section 624.155 begins when the CRN is electronically filed with the Department, and to avoid a bad faith action, the insurer must pay the claim or take corrective action within sixty days from the date the CRN is electronically filed.

Harper, supra.

This is important because the insurer must fail to cure within this 60-day cure period to trigger the statutory requirements of a statutory bad faith claim.  If the insurer fails to cure within this 60-day cure period, the insured has preserved an argument for a statutory bad faith claim.  See Harper, supra (“Therefore, because GEICO did not pay Harper’s claim within sixty days of the date the CRN was electronically filed with the Department, it did not pay the claim within the sixty-day cure period, and Harper was entitled to pursue her action for GEICO’s alleged bad faith.”).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.