RIGHTFULLY RECOVERING UNDER A COBLENTZ AGREEMENT

A recent case out of the Middle District of Florida, The Peninsula at St. John’s Center Condominium Association, Inc. v. Amerisure Ins. Co., 2025 WL 1547631 (M.D.Fla. 2025) discusses what a party must do to RIGHTFULLY recover under a Coblentz agreement under Florida law:

“In Florida, a party seeking to recover under a Coblentz agreement must prove: (1) coverage; (2) a wrongful refusal to defend; and (3) that the settlement was objectively reasonable and made in good faith. “Florida law clearly states that liability of an insurer depends upon whether the insured’s claim is within the coverage of the policy. This remains true even when the insurer has unjustifiably failed to defend its insured in the underlying action.”  “A determination of coverage, therefore, is a condition precedent to any recovery against an insurer.”
 
The party seeking recovery has the burden “to allocate the settlement amount between covered and uncovered claims.”  “[A]n insurer faced with a Coblentz action has the right to litigate its contractual duty to indemnify on the actual facts of the underlying litigation just as it would in an action against its insured.”  Once the party seeking to recover under a Coblentz agreement has established coverage and allocated damages amounts between covered and uncovered claims, the burden shifts to the defendant who must then prove that either the Coblentz agreement was unreasonable or was negotiated in bad faith.

Id. At *5 (internal citations omitted).

In this case, an insurer for a contractor denied coverage, and thus, the duty to defend, in a large, complex construction defect coverage lawsuit with multiple parties. The association-claimant entered into a Coblentz agreement with the contractor and then the association, through an assignment of the general contractor’s rights under the contractor’s commercial general liability policy, sued the contractor’s insurer.  The Middle District held that the insurer was not liable to the association under the Coblentz framework. This means the association was collecting nothing from the contractor’s insurer.

First, it was undisputed that the operative complaint in the construction defect lawsuit was a third amendment complaint. Yet, this amended complaint was never presented to the insurer for a coverage position. It should have, regardless of whether the insurer denied its obligations under a previous version of the complaint. Thus, there was never a wrongful denial to defend to trigger the Coblentz framework because the insurer was not given the operative complaint to determine whether it had a duty to defend.

Next, the Middle District found that the insurer was not liable under the Coblentz framework (even if the insurer had been given the operative complaint) because the association-claimant “has not satisfied its burden to allocate between covered and uncovered claims.” The Peninsula at St. John’s Condominium Ass’n, supra, at *11. The claimant has the burden to allocate damages between covered and uncovered claims and the inability to allocate would destroy the Coblentz framework. Id. at *9. (“[T]he Coblentz Agreement is unenforceable because it does not properly allocate between covered and uncovered claims.”).

Moreover, as if the other two bases were not enough, the Middle District further maintained the Coblentz Agreement was not reasonable. In other words, it included unreasonable amounts. “What Coblentz does not do is authorize the insured to indiscriminately load the carrier’s wagon with bricks of damage that no reasonable person would expect as consequences of the underlying claim.” The Peninsula at St. John’s Condominium Ass’n, supra, at *11. The Middle District found the damages amount subject to the Coblentz agreement was not reasonable as it loaded up damages and did not account for other party’s liability or amounts in which it settled with other parties.

There are times considering a Coblentz agreement is 100% worth it. If considering a Coblentz agreement, make sure to draft it correctly to maximize the best arguments you can in pursuing coverage. Do it right!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

FLORIDA CLAIMS ADMINISTRATION STATUTE AND DIFFERENCE BETWEEN POLICY DEFENSE AND COVERAGE DEFENSE

A recent insurance coverage dispute involving an automobile liability insurance policy contains a worthy discussion, particularly on the difference between a policy defense and a coverage defense.  In this case, the carrier did not provide a defense to the defendant and the plaintiff and defendant entered into a Coblentz agreement.  The plaintiff, as assignee of the insured, filed a lawsuit against the automobile liability policy for coverage. Summary judgment was granted in favor of the insurer finding there was no coverage under the terms of the policy. This was affirmed.

1. Scope and Extent of Insurance Coverage

The scope and extent of insurance coverage is determined by the language of the insurance policy. Thus, the policy’s text is paramount and must be the starting point of our analysis. Parrish v. State Farm Florida Ins. Co., 356 So. 3d 771, 774 (Fla. 2023); see also State Farm Mut. Auto. Ins. Co. v. Menendez, 70 So. 3d 566, 569 (Fla. 2011) (“In interpreting an insurance contract, we are bound by the plain meaning of the contract’s text.”); § 627.419(1), Fla. Stat.

***

The policy must be enforced as written. Courts are without power to rewrite insurance contracts or create insurance coverage where none exists. Excelsior Ins. Co. v. Pomona Park Bar & Package Store, 369 So. 2d 938, 942 (Fla. 1979); U.S. Fire Ins. Co. v. Morejon, 338 So. 2d 223, 225 (Fla. 3d DCA 1976) (“Florida courts adhere to the principle that a court should not rewrite a contract of insurance extending the coverage afforded beyond that plainly set forth in the insurance contract.”).

Fojon v. Ascendant Commercial Ins. Co., 49 Fla.L.Weekly D1799b (Fla. 3d DCA 2024)

2. Florida’s Claims Administration Statute and Difference between Coverage Defenses and Policy Defenses

An argument that was raised by the plaintiff (as assignee of the insured) was that the liability insurer waived its right to deny coverage because the insurer failed to comply with Florida’s Claims Administration Statute.

Florida’s Claims Administration Statute is embodied in Florida Statute s. 627.426, which provides in material part in subsection (2):

(2) A liability insurer shall not be permitted to deny coverage based on a particular coverage defense unless:

(a) Within 30 days after the liability insurer knew or should have known of the coverage defense, written notice of reservation of rights to assert a coverage defense is given to the named insured by registered or certified mail sent to the last known address of the insured or by hand delivery; and

(b) Within 60 days of compliance with paragraph (a) or receipt of a summons and complaint naming the insured as a defendant, whichever is later, but in no case later than 30 days before trial, the insurer:

        1. Gives written notice to the named insured by registered or certified mail of its refusal to defend the insured;
        2. Obtains from the insured a nonwaiver agreement following full disclosure of the specific facts and policy provisions upon which thecoverage defenseis asserted and the duties, obligations, and liabilities of the insurer during and following the pendency of the subject litigation; or
        3. Retains independent counsel which is mutually agreeable to the parties. Reasonable fees for the counsel may be agreed upon between the parties or, if no agreement is reached, shall be set by the court.

Importantly, as reflected in the statute, it pertains to coverage defenses. Not policy defenses.

A policy defense is an assertion that the terms of the insurance contract do not provide for coverage. AIU Ins. Co. v. Block Marina Inv., Inc., 544 So. 2d 998, 1000 (Fla. 1989). For example, a policy defense exists where the insuring agreement is not triggered, such as when a person does not qualify as an insured or when a vehicle does not qualify as a covered auto. Other examples include where an exclusion applies, or when a loss occurs outside of the policy period.

On the other hand, a coverage defense involves forfeiture of insurance coverage that otherwise exists. Coverage defenses arise where the insured fails to comply with a condition or duty required by the policy, such as failing to cooperate, committing fraud, or failing to provide prompt notice. It is based on some action or inaction of the insured after the loss. Grigsby, supra, at 8 (“It focuses on the insured’s behavior, post-loss in particular.”).

Fojon, supra.

When it comes to a coverage defense, an insurer must comply with Florida’s Claims Administration Statute. “If it does not, it is estopped from asserting the coverage defense – a breach of a policy condition that would forfeiture coverage. It can still, however, assert a policy defense – a defense of no coverage.”  Fojon, supra (internal citation omitted).

However, in this coverage dispute, the insurer relied on a policy defense in denying coverage and its defense of the insured, not a coverage defense . “Therefore, the Claims Administration Statute does not apply, and it does not bar [insurer] from denying coverage.” Fojon, supra.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

BENEFIT OF THE COBLENTZ AGREEMENT AND CONSENT JUDGMENT

If you are not familiar with the concept of what is commonly known as a Coblentz agreement relative to an insurance coverage dispute, review these prior postings (here and here and here). This is a good-to-know agreement if you are a claimant and need to consider an avenue of collection if the insured’s carrier denies coverage out of the gate (meaning the carrier has denied both the duty to defend and the duty to indemnify).

A recent Eleventh Circuit Court of Appeals opinion demonstrates the Coblentz agreement concept.  In Barrs v. Auto-Owners Ins. Co., 2024 WL 3673089 (11th Cir. 2024), an owner asserted a construction defect claim against its contractor.  The owner hired the contractor to deconstruct a building and the contractor hired a demolition subcontractor. The owner noticed work was not being performed and materials (e.g., lumber) were missing; the demolition subcontractor had stolen materials. The subcontractor was terminated, and the owner claimed the contractor’s negligence allowed the theft and delayed his project. The contractor’s commercial general liability (CGL) insurer notified the insured-contractor that coverage did not exist and refused to defend the contractor. The owner sued the contractor under various theories of liability.  The owner and contractor entered into a settlement agreement (i.e., the Coblentz agreement) where the contractor “admitted liability in the amount of $557,500.00….A consent judgment was entered against [the contractor] that closely tracked the settlement agreement but did not indicate which portion of the damages award was attributed to which claims. The agreement also assigned [owner] and all of [the contractor’s] rights to claim coverage and to recover available funds under [the contractor’s CGL policy].”

The owner then sued the contractor’s insurer under the CGL policy based on the owner being assigned contractor’s rights under the policy. While the federal district court found Georgia law applied, it further found that the contractor’s CGL policy provided coverage for some of owner’s claims against contractor – it provided coverage for owner’s “claims of negligent hiring, retention, and supervision to the extent that he sought damages for stolen lumber and materials.” Barrs, supra, at *2. The CGL policy did not cover any faulty workmanship or improper deconstruction.  The district court subsequently entered judgment in favor of the owner against the insurer for $557,500. The CGL insurer appealed arguing, mainly: (1) the damages are not covered by its policy, and (2) it had no duty to indemnify the owner because the consent judgment did not allocate between covered and uncovered claims.

As for the CGL insurer’s first point of contention (damages are not covered), he Eleventh Circuit held no exclusion barred coverage for the negligent hiring, retention, and supervision claims for damages associated with stolen lumber and materials.

As for the CGL insurer’s second point of contention (no duty to indemnity because of lack of allocation in consent judgment), the Eleventh Circuit held that nothing under Georgia law precludes enforcement of an unallocated consent judgment:

“The district court held that “[w]hen an insurance company refuses to defend its insured, without any reservation of rights, and its insured secures ajudgment (without fraud or collusion), an insurance company must pay the entire judgment.” It determined that the consent judgment here wasenforceable because (1) it complied with the procedures established in Coblentz v. American Surety Company of New York, 416 F.2d 1059 (5th Cir.1969); (2) Georgia common law didn’t appear to allow an insurer a second bite at the apple when it chose not to participate in the underlying lawsuit; and (3) [owner’s] declaration attested that the $557,500 settlement was less than the value of the stolen lumber, so even if the consent judgment wasn’t properly allocated, the recovery was reasonable.

We agree that the consent judgment was crafted and executed in compliance with Coblentz. To be sure, although Georgia law estops an insurer from contesting its insured’s liability when it refuses to participate in the underlying lawsuit, it doesn’t necessarily prevent an insurer from later contesting coverage. Even so, we affirm because we’ve been pointed to nothing in Georgia law that clearly prevents the enforcement of unallocated consent judgments.  To hold that unallocated consent judgments are unenforceable would be to shift the burden to the insured and would require meddling in Georgia law to a degree that we think would be imprudent.

Barrs, supra at *5 (internal citations omitted).

When dealing with the Coblentz agreement and corresponding consent judgment, it is better practice to allocate damages between covered and uncovered damages. Regardless, this case demonstrates the benefit of a Coblentz agreement when the liability carrier denies coverage out of the gate and the carrier becomes the best avenue of collection.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

KNOW WHETHER YOUR COURSE OF BUSINESS OPERATIONS ARE COVERED OR EXCLUDED BY YOUR INSURANCE

It is a good idea to know what your insurance covers and does not cover.  This way, if your course of business has you performing a certain (risky) operation, you know whether that operation is covered or excluded under your policy.  If you are not sure, discuss with your insurance broker — this is important. There is little value performing an operation that is NOT covered by your insurance policy, as you are now performing a risk that is not covered by insurance.   If you know it is not covered by insurance you may elect to change your operations or see if there is insurance to cover the risk.  Below is a case study of this occurrence dealing with a commercial automobile liability policy where an insured’s operations using a crane mounted to a super duty truck was not covered under their automobile liability policy.

In People’s Trust Ins. Co. v. Progressive Express Ins. Co., 46 Fla. L. Weekly D262a (Fla. 3d DCA 2021), homeowners hired a company to install a shed.  The company hired another company to deliver and install the shed using a crane; the company used a crane mounted to a Ford F-750 super duty truck.  This company improperly operated the crane resulting in the shed falling and damaging the homeowner’s roof.   The homeowners submitted a claim to their property insurer and their property insurer subrogated to their rights and sued.  The company operating the crane’s commercial automobile liability insurer denied coverage, and thus, denied the duty to defend.  As a result, a Coblentz-type agreement was entered into where the company operating the crane consented to a judgment in favor of the property insurer (subrogee) and assigned its rights under its commercial automobile liability policy to the property insurer.   The property insurer then sued the automobile liability carrier for coverage.   The trial court granted summary judgment in favor of the automobile liability insurer finding there was no coverage and this was affirmed on appeal.  Why?

The coverage issue focused on whether a crane mounted to a super duty truck (Ford F-750) was covered or excluded by the commercial automobile liability policy.

The policy included a mobile equipment exclusion; however, mobile equipment did not include, “land vehicles that are subject to a compulsory or financial responsibility law or other motor vehicle insurance law in the state or province where it is licensed or principally garaged.  Land vehicles subject to a compulsory or financial responsibility law or other motor vehicles are considered autos.”    The Ford F-750 super duty truck would not constitute mobile equipment excluded by the policy because it would be a land vehicle subject to a compulsory or financial responsibility law or other motor vehicles insurance law.

However, the crux of the issue was the crane mounted to the Ford F-750 super duty truck.   The policy also excluded coverage for, “Bodily injury, property damage…arising out of the operation of:…b. machinery or equipment that is on, attached to, or part of, a land vehicle that would qualify under the definition of mobile equipment if it were not subject to a compulsory or financial responsibility law where it is principally licensed or principally garaged.”

Based on this exclusion, the Court held:

The truck, “used primarily to provide mobility to a mounted crane,” would be excluded “mobile equipment” under the relevant definition, but for the fact that it is subject to a compulsory or financial responsibility law. The contract contemplates this exact situation. Next, we look to the “13.b. exclusion” which directs us to exclude any claim for property damage “arising out of the operation of . . . machinery or equipment that is on, attached to, or part of, a land vehicle that would qualify under the definition of mobile equipment if it were not subject to a compulsory or financial responsibility law where it is licensed or principally garaged.” There is no dispute that the crane was in use at the time of the incident and that the property damage arose out of the operation of the crane. Where, as here, the record clearly established that the damage at issue was caused by the mounted crane, in operational use, on a vehicle that would otherwise qualify as mobile equipment, the trial court correctly granted summary judgment in favor of [the automobile insurer] on the policy exclusion and properly entered final judgment in accord with such findings.

People’s Trust Ins. Co., supra.

In other words, the company that used the crane mounted to its super duty truck performed an operation excluded by its commercial automobile liability insurance policy.  The company would have been better to know whether this risk was covered or excluded under its policy, see if it could obtain coverage for this operation, or switch its operation appreciating the uninsured risk associated with performing the operation in this manner.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

SOMETIMES YOU NEED TO CONSIDER THE COBLENTZ AGREEMENT


Since insurance, particularly liability insurance, is such an important component when it comes a construction project, understanding certain nuances such as a Coblentz Agreement (a what kind of agreement agreement?!?—keep reading) becomes helpful.  

 

If there is a construction defect claim / lawsuit, the implicated parties (e.g., contractor, design professional, subcontractor, sub-consultants) are going to tender the claim / lawsuit to their respective liability insurer.  This is what they should be doing – notifying the insurer so that the insurer can defend them from the claim / lawsuit and indemnify them from covered damages associated with the claim / lawsuit.  

 

And, if a contractor is an additional insured under an implicated subcontractor’s liability policy, it is going to demand that the insurer defend it (or share in the defense costs with other implicated subcontractors) and indemnify it based on the negligence of the primary insured-subcontractor.

 

This is all par for the course in a construction defect lawsuit–really, any construction defect lawsuit.

 

But, there may come a point where a liability insurer denies coverage meaning they are declining to defend their insured in connection with the claim / lawsuit.    In this situation, the claimant may consider entering into a Coblentz agreement with the insured.  This was the topic in a recent non-construction case in In Re: The Estate of Jorge Luis Arroyo, Jr. v. Infinity Indemnity Insurance Co., 42 Fla. L. Weekly D192a (Fla. 3d DCA 2017), when a personal injury negligence lawsuit was brought against an Estate as the result of a deadly car accident.  The Estate tendered the defense of the negligence lawsuit to the decedent’s insurer, but the insurer declined to defend the Estate of the insured.  The Estate and the personal injury claimant then entered into a Coblentz agreement where the Estate (1) agreed to a consent judgment entered against it, (2) assigned its rights under its liability policy to the claimant, and (3) the claimant agreed not to pursue the consent judgment against the insured.  The Coblentz agreement and consent judgment gave the claimant a path to sue the insured’s liability insurer based on the liability against the insured as set forth in the consent judgment.  (The consent judgment establishes the liability of the insured.)

 

“In order to enforce a consent judgment entered pursuant to a Coblentz agreement, the assignee [claimant] must bring an action against the insurer and prove: (1) insurance coverage, (2) the insurance company wrongfully refused to defend its insured, and (3) the settlement was reasonable and made in good faith.”  In Re: The Estate of Jorge Luis Arroyo, Jr. supra.

 

“[W]hen an insurer refuses to defend its insured from a lawsuit, and the insured later settles the suit by entering into a Coblentz agreement, the insurer is precluded from relitigating the issue of its insured’s liability in subsequent proceedings.”  In Re: The Estate of Jorge Luis Arroyo, Jr. supra.   Stated differently, the insurer is precluded from later raising defenses on behalf of its insured that it could have previously raised had it simply defended its insured. 

 

In this case, the insurer ultimately tried to intervene in an underlying lawsuit once it was sued per the Coblentz agreement.  Although the trial court permitted this intervention, the appellate court reversed because the insurer couldn’t relitigate issues it could have raised had it not declined to defend its insured– it was this declination that gave rise to the Coblentz agreement in the first place.   The consent judgment established the insured’s liability to the claimant; thus, the issues to determine were (1) was there coverage, (2) did the insurer wrongfully refuse to defend the insured; and (3) was the settlement reasonable.  As this case shows, sometimes a claimant needs to consider entering into a Coblentz Agreement to pursue recourse against an insurance policy.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

COBLENTZ AGREEMENT AND ALLOCATION OF DAMAGES IN CONSENT JUDGMENT


I previously discussed Coblentz agreements.  A Coblentz agreement is an agreement between a claimant (e.g., property owner) and a third-party (e.g., general contractor that caused construction defects and damage) when the third-party’s liability insurer denies a defense (and coverage) to the third-party.  The claimant and third-party enter into an agreement where a) the claimant obtains a consent judgment against the third-party, b) the third-party assigns its rights under its liability policy to the claimant based on the insurer’s refusal to defend and indemnify the third-party, and c) the claimant releases the third-party from any individual liability irrespective of whether the claimant recovers from the third-party’s liability insurer. (Check here for a presentation on Coblentz agreements.)

 

One of the key components of the Coblentz agreement is the consent judgment given by the third-party to the claimant.  It is always a good idea to allocate between damages covered by insurance and damages not covered by insurance.  The reason is that liability insurance is not designed to cover defective workmanship.  Rather, it is designed to cover damages resulting from defective workmanship.  In a construction defect dispute, the consent judgment should reasonably allocate the covered damage (damage caused by defective workmanship) and uncovered damage (the cost solely to repair defective workmanship).  These amounts should not be arbitrarily decided but should be supported with expert opinions since this point would be litigated against the liability insurer when the claimant tries to recover from the third-party’s liability insurer. 

 

For example, in the recent opinion of Bradfield v. Mid-Continent Casualty Company, 2015 WL 6956543 (M.D.Fla. 2015), an aspect of the opinion dealt with the lack of an allocation of damages in a consent judgment given in consideration of a Coblentz agreement.  The contractor gave the owner a consent judgment in the amount of $671,050.  But, there was no allocation of this lump sum amount for covered and uncovered damage or what this lump sum was designated for.   The consent judgment was based on an estimate prepared by an expert but the estimate included costs to repair defective work, or work that was not covered by the liability insurance policy.  The Middle District of Florida found that this failure to appropriately allocate covered verses uncovered damage was fatal to the owner’s claim against the third-party contractor’s liability insurer to recover the amount of the consent judgment. The court explained: “Florida law clearly requires the party seeking recovery…to allocate any settlement amount between covered and noncovered claims.” Bradfield, supra, at *24.

 

Even if damages were allocated, the consent judgment still needs to be reasonable and entered in good faith. The court discussed this aspect of the Coblentz agreement despite finding that the failure to allocate was fatal to the owner’s claims against the contractor’s liability insurer.  As to the reasonableness of a consent judgment, the court importantly maintained:

 

When an injured party wishes to recover under a Coblentz agreement, [t]he claimant must assume the burden of initially going forward with the production of evidence sufficient to make a prima facie showing of reasonableness and lack of bad faith, even though the ultimate burden of proof will rest with the carrier. The courts impose good faith and reasonableness requirements in these cases due to the risk that the settlement of liability and damages in a settlement agreement may have little relationship to the strength of a plaintiff’s claim where the insured may never be obligated to pay and has little to lose if he stipulates to a large sum with the plaintiff.

 

In Florida, the test as to whether a settlement is reasonable and prudent is what a reasonably prudent person in the position of the defendant [the insurer] would have settled for on the merits of plaintiff’s claim. Objective and subjective factors are considered, including the degree of certainty of the tortfeasor’s subjection to liability, the risks of going to trial and the chances that the jury verdict might exceed the settlement offer. [P]roof of reasonableness is ordinarily established through use of expert witnesses to testify about such matters as the extent of the defendant’s liability, the reasonableness of the damages amount in comparison with compensatory awards in other cases, and the expenses which have been required for the settling defendants to settle the suit. Bad faith also may be established by evidence of the absence of any effort to minimize liability.

Bradfield, supra, at 27 (internal quotations and citations omitted).

When considering a Coblentz agreement on behalf of a claimant, make sure the judgment allocates between covered and noncovered claims / damages and is reasonable.  The same experts utilized to support the allocation can be utilized to support the reasonableness of the allocation for covered claims / damages.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

CONTRACTUAL LIABILITY EXCLUSION IN CGL POLICIES AND “INSURED CONTRACT” EXCEPTION


Commercial General Liability (CGL) policies contain a CONTRACTUAL LIABILITY EXCLUSION (see adjacent picture). The contractual liability exclusion operates to BAR personal injury and property damage claims “which the insured is obligated to pay by reason of the assumption of liability in a contract or agreement.”  Think indemnification claims which are assumption of liability claims and common in construction. 

But, and this is an important but, there are two exceptions to this exclusion.

First, the contractual liability exclusion does not apply to liability for damages “that the insured would have in the absence of the contract or agreement.”   Think tort claims.

Second, the contractual liability exclusion does not apply to liability for damages “assumed in a contract or agreement that is an ‘insured contract’.”  The key to this exception is the definition of an “insured contract.” 

Applicable to construction, a key definition of an “insured contract” is “that part of any contract…pertaining to your business…under which you assume the tort liability of another party to pay for bodily injury or property damage to a third person or organization.”  This portion of the “insured contract” definition should ideally bring contractual indemnification claims back into play so that contractual indemnification claims are not barred by the contractual liability exclusion.

Be careful, though.  There are endorsements to CGL policies that have modified the definition of “insured contract” to either remove the aforementioned definition all together, meaning contractual indemnification claims would be excluded.  This is a bad endorsement to the definition of “insured contract” if you are involved in construction.

Or, this key definition of “insured contract” has been narrowed to include the following underlined language “that part of any contract…pertaining to your business…under which you assume the tort liability of another party to pay for bodily injury or property damage to a third person or organization, provided the bodily injury or property damage is caused, in whole or in part, by you or those acting on your behalf.”  This means that if you contractually agree to indemnify another for that person’s negligence, this would not meet the definition of “insured contract” since you are agreeing to indemnify another for negligence not caused in whole or in part by you. 

For example, the opinion in Mid-Continent Casualty Co. v. Royal Crane, LLC, 2015 WL 3609062 (Fla. 4th DCA 2015), discusses this narrowed definition of “insured contract” with the underlined language above.  In this case, a subcontractor leased a crane and crane operator from a rental company.  The rental agreement between the subcontractor and rental company contained the following contractual indemnification language:

“Lessee [subcontractor] agrees to indemnify, defend and hold harmless Lessor [rental company], its employees, operators and agents from any and all claims for damage to property, damage to the work or bodily injury (including death) resulting from the use, operation, or possession of the crane and operator whether or not it be claimed or found that such damage or injury resulted in whole or in part from Lessor’s negligence, from a defective condition of the crane or operator or from any act, omission or default of Lessor.”

In other words, the subcontractor was agreeing to indemnify the rental company for the rental company’s negligence.  This is known as a broad form indemnification provision.

 

During construction, a worker was hurt when a truss fell from the crane.  The worker sued the rental company and the crane operator for negligence.  The rental company and operator third-partied in the subcontractor based on the contractual indemnification provision in the rental agreement. However, the subcontractor’s CGL insurer denied coverage (and, thus, a defense in the lawsuit) based on the contractual liability exclusion.

As a consequence of the CGL insurer’s immediate denial of coverage, the subcontractor entered into a Coblentz settlement agreement with the rental company that allowed the rental company to sue the subcontractor’s CGL’s insurer for its wrongful refusal to deny the subcontractor a defense and for coverage under the subcontractor’s policy.  

Coblentz Settlement Agreement

In a nutshell, a Coblentz settlement agreement is an agreement between an insured and a third-party claimant where the insurer denied coverage and, thus, the duty to defend its insured in an underlying lawsuit.  The insured agrees to give the claimant a consent judgment to resolve the lawsuit and an assignment of its rights under its CGL policy to the claimant in exchange for the claimant not enforcing the consent judgment against the insured.  This allows the claimant to now sue the insured’s CGL insurer directly to enforce the consent judgment.  In doing so, the claimant must still prove: (a) the insurer wrongly refused to defend its insured, (b) there is coverage under the policy, and (3) the negotiated consent judgment was made in good faith and is reasonable. But, the consent judgment prevents the insurer from trying to argue the liability of the insured since that could have been argued in the underlying lawsuit that the insurer refused to defend its insured in.  See Royal Crane, supra, at *4-5. (For more information on Coblentz settlement agreements, check out this presentation that discusses this in detail.)

“Insured Contract”

But, the heart of the case really pertained to the contractual liability exclusion and the definition of an “insured contract” as narrowed by endorsement. With respect to the definition of “insured contract” in the policy (see above language), the Fourth District Court of Appeals importantly held:

“[A]n indemnity agreement can be an ‘insured contract’ under the policy where the injury is caused by the indemnitee’s negligence, so long as the named insured ‘caused’ some part of the injuries or damages or is otherwise vicariously liable.”

Royal Crane, supra, at *7. 

In other words, taking the above fact pattern, the indemnity agreement could constitute an “insured contract” to be excepted from the contractual liability exclusion if the worker’s injury was caused by the rental company’s (indemnitee) negligence, so long as the subcontractor (named insured in the CGL policy) caused some part of the injuries or was otherwise vicariously liable to the rental company for the injuries.

 Unfortunately for the rental company, even under this favorable definition of an “insured contract”, the rental company’s third-party complaint against the subcontractor still did not trigger a duty of subcontractor’s CGL insurer to defend and cover the subcontractor:

“Hunter Crane’s [indemnitee-rental company] third party complaint did not assert a legal theory under which Cloutier [insured-subcontractor] can be said to have ‘caused’ the injury in whole or in part.  No allegation described how Cloutier contributed to causing the accident.  No allegation attempted to invoke the borrowed servant doctrine, which dictates that ‘one who borrows and exercises control over the servant or worker of another in effect assumes all liability for the activities of the borrowed servant or worker.’ Nor did the third party complaint cast Cloutier as the employer of an independent contractor who actively participated in or interfered with the job to the extent that it directly influenced the manner in which the work was performed.”

Royal Crane, supra, at *7 (internal quotations omitted).

For this reason, the Fourth District sided with the CGL insurer finding that the contractual liability exclusion barred coverage to the subcontractor such that the CGL insurer had no duty to defend or cover the subcontractor in the underlying litigation.  This also meant that the rental company’s Coblentz settlement agreement provided it no value because it already agreed to give up rights to collect against the subcontractor and it could no longer collect against the subcontractor’s CGL insurer.  What this case does exemplify, however, is the importance of pleading allegations to maximize insurance coverage as well as a more relaxed definition of an “insured contract”  to hopefully prevent the application of the contractual liability exclusion.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CGL INSURANCE AND CONSTRUCTION DEFECTS (DUTY TO DEFEND; TRIGGERING OF CGL POLICY; COVERED RESULTING DAMAGE)


I previously wrote about insurance coverage issues in a construction defect dispute, specifically in the context of the insurer denying coverage outright and refusing to defend its insured.

 

As a sequel to this posting, a noteworthy opinion was issued by the Eleventh Circuit Court of Appeals in Carithers v. Mid-Continent Cas. Co., 2015 WL 1529038 (11th Cir. 2015) in a commercial general liability (CGL) insurance coverage dispute dealing with construction defects to a house.   This opinion discusses central issues to an insurance coverage dispute in a construction defect context: the triggering of a CGL policy, the duty to defend, the duty to indemnify, covered resulting damage stemming from construction defects, and a claimant resolving a dispute with an insured in order to pursue rights against the insured’s CGL carrier (also known as a Coblentz agreement).

 

In this case, the owners hired a general contractor to build their house.  The general contractor had CGL insurance with products completed operations coverage.  Upon discovering construction defects, the owners sued the general contractor.  The general contractor’s insurer refused to defend the general contractor, meaning the insurer denied coverage (which is the last thing the general contractor ever wants to hear).  The insurer denied coverage because the complaint alleged that the damages were not discovered until 2010; however, the general contractor did not have any CGL coverage after 2008.  Thus, if the manifestation theory applied to trigger coverage (discussed below), there would be no coverage under the CGL policy.

 

The general contractor and insurer then entered into a consent judgment in the action for $90,000 in favor of the owners that assigned to the owners the general contractor’s rights under its CGL policy.  (This forms the framework for what is known as a Coblentz agreement.)  The owners then sued the general contractor’s CGL insurer.

 

The issues in this case were (a) the insurer’s duty to defend its general contractor-insured, (b) the triggering of an occurrence under a CGL policy, and (c) resulting damage covered under the CGL policy.

 

(A) Duty to Defend

 

The insurer’s duty to defend is triggered by the allegations in the complaint.  Here, the Eleventh Circuit held that the insurer had a duty to defend because the duty to defend is broader than the insurer’s duty to indemnify and “all doubts as to whether a duty to defend exists in a particular case must be resolved against the insurer and in favor of the insured.” Carithers, supra, at *4 (quotation and citation omitted). “An insurance company must defend an action where the facts alleged against the insured would give rise to coverage, even if those facts are not ultimately proven at trial.”  Id. 

 

(B) Triggering of an Occurrence Under CGL Policy

 

The insurer wanted the manifestation theory to trigger CGL coverage.  Under this theory, the CGL policy is triggered if the damage is discovered (manifests itself) during the policy period.  

 

The reason the insurer wanted this theory to apply is because the owners admitted that they discovered the damage / defects in 2010 when the general contractor’s CGL policy was no longer in effect.

 

Conversely, the owners wanted the injury-in-fact theory to apply to trigger coverage.  Under this theory, the policy is triggered when the damage occurs even if the damage is not discovered until sometime later.  Here, the trial court found that the damage occurred in 2005 when the general contractor’s CGL carrier was in effect (although the damage was not discovered until 2010).  Because there was evidence and a finding as to when the damage occurred, the Eleventh Circuit held that the injury-in-fact theory was the correct theory to trigger CGL coverage.

 

(C) Resulting Damage Covered Under a CGL Policy

 

The cost of repairing damage to other work resulting from faulty workmanship would be covered under the CGL policy.  In other words, repairing damage to another trade’s work would be covered but repairing / replacing damage to the trade’s own work would not be covered.  The Eleventh Circuit analyzed this application to determine whether the trial court appropriately determined that certain items were resulting damage.

 

(1)  Brick

 

The trial could found that the defective application of exterior brick coating caused resulting damage to the brick itself.  If the exterior brick coating was applied by the subcontractor that installed the brick, then the brick should not be covered since the brick was the subcontractor’s own work as opposed to other work.  However, there was no evidence at the trial level whether the brick coating and installation of the brick was done by the same subcontractor or different subcontractors.  Because the plaintiff owners (who were assigned rights under the policy by the general contractor insured) had the burden of proof on this issue, which they failed to meet, the Eleventh Circuit reversed any damage awarded associated with the brick.

 

(2)  The Tile and Mud Base

 

The trial court found that defective adhesive and an inadequate base caused damage to the tile.  The trial court awarded damage to replace the tile and mud base. Similar to the brick, the issue turned on whether the installation of the tile and mud base was done by the same subcontractor or different subcontractors.  And, similar to the brick, no evidence was offered on this point so the Eleventh Circuit reversed any damage awarded associated with the tile and mud base.

 

(3)  Balcony

 

The trial court found that defects in the construction of the balcony resulted in damage to the garage. However, because the balcony had to be rebuilt in order to repair the garage, the trial court held that this work was resulting damage covered by the CGL policy.  The Eleventh Circuit agreed with the trial court holding that the cost of repairing damage resulting from defective work is covered and since repairing the balcony was part of repairing the garage, these costs would be covered.

 

Important take-aways:

  • This case provides strong arguments to an insured when its CGL carrier denies coverage, specifically based on the argument that its policy was never triggered.  Remember, the duty to defend is broader than the duty to indemnify so any doubts must be resolved in favor of the insured.
  • Don’t forget about the injury-in-fact theory to trigger CGL coverage.  If you have evidence, such as an expert opinion, as to when the damage started to occur, this theory can be valuable if the owner discovered the latent defects after the expiration of your CGL policy.  This helps an owner maximize CGL coverage and a general contractor maximize coverage under its CGL policy.
  • Make sure to meet your burden of proof to establish resulting damage or other damage caused by faulty workmanship.  Make sure to prove that the resulting damage was work performed by a different subcontractor and not the subcontractor that performed the faulty workmanship. And, to this point, make sure to include appropriate language in the consent judgment.
  • Make sure you know how to couch your coverage arguments to an insurer in order to maximize insurance coverage.
  • If your insurer denies coverage, consider entering into what is known as a Coblentz agreement with the claimant where a consent judgment is entered against you and rights under your policy are assigned to the claimant.  The benefit is that in consideration of the consent judgment and assignment of rights, the claimant gives up any rights to collect that judgment against you. 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.