CONTRACT DISPUTES ACT AND JURISDICTIONAL REQUIREMENTS

When dealing with a claim on a federal construction project, there are a couple of key background jurisdictional points. These points were briefly highlighted in the recent appeal, Mega Star Logistics Service Co. v. Department of State, CBCA 8232, 2026 WL 253738 (CBCA 2026).  Here are the two points.

FIRST, when it comes to jurisdiction, for a board of contract appeals “to exercise jurisdiction over a claim, the CDA [Contract Disputes Act] requires the contractor to submit a written claim to the contracting officer for a COFD [contracting officer final decision], with a subsequent appeal of the COFD or deemed denial if the CO [contracting officer] does not issue a COFD.”  Thus, you need to submit a formal claim under the Contract Disputes Act to the contracting officer to get a final decision from the contracting officer (or the contracting officer waiving the final decision by not timely furnishing one). Mega Star Logistics, supra.

SECOND, “[s]hould a contractor choose to appeal to the Board [of Contract Appeals], the CDA requires that the contractor file is appeal no more than ninety days following receipt of the COFD.Megal Star Logistics, supra.  Thus, once you get the final decision from the contracting officer, if you plan to appeal, you need to do so within 90 days.

Both these jurisdictional points are important.

Remember to (1) formally submit your claim under the Contract Disputes Act, and (2) file your appeal within 90 days from receipt of the contracting officer’s final decision. Even if you don’t get a final decision, treat the untimely response by the contracting officer as a “deemed denial” and timely file your appeal within the 90 days after the deemed denial (the time for the contracting officer to render a final decision has come and gone).

If you blow these points off, then you will face a motion to dismiss which will be granted because there won’t be jurisdiction to properly hear your appealed claim!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SUBSTITUTING MATERIALS AND FAILURE TO COMPLY WITH CONTRACTUAL REQUIREMENTS

It is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials.  Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials.  This is not the situation you want to find yourself in because this is oftentimes a costly endeavor.  This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project.  The best thing that you can do is comply with the contractual requirements if you want to substitute materials.   If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material.  Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.

In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system.   However, the prime contractor installed PVC piping instead of cast iron piping.  The prime contractor believed it had the appropriate approval through its submittal.  The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron.  The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping.  The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer.  On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal.  The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.”  Appeal of-Sauer, Inc., supra.

The prime contractor argued the government approved the deviation and use of PVC by another government representative.  This argument failed because only the contracting officer had the authority to change a contract or task orderAppeal of-Sauer, Inc., supra (citing FAR clauses that reference that only the contracting officer has authority to modify or deviate from a contract).

Next, the prime contractor argued estoppel and waiver in that government personnel were present and observed the construction of the above ground sanitary piping with PVC and waited 16 weeks before directing the prime contractor that it could not use PVC piping.   The prime contractor argued this unreasonable delay should be deemed the government constructively accepting PVC and the government either waived the right to demand strict compliance with cast iron or should be estopped from demanding such compliance. This argument failed:

Here, only the contracting officer could vary the task order requirements.  Therefore, to establish waiver, [the prime contractor] must demonstrate that the contracting officer knowingly rescinded the government’s right to require compliance with a task order minimum requirement.  Even assuming government personnel on site may have observed the installation and use of PVC pipe, there is no evidence that the contracting officer knowingly waived the task order requirement.

The government is generally entitled to insist upon strict compliance with the contract specifications and to require correction of nonconforming work.  There are instances, however, where the government may waive strict compliance with contractual requirements and is estopped from later re-imposing those requirements upon the contractor.  These cases require knowing failure to exact performance – presumably by one with authority to waive contractual terms.

Appeal of-Sauer, Inc., supra (internal quotations mitted).

Lastly, the prime contractor argued under the economic waste doctrine—that removing the PVC and replacing it was cast iron constituted economic waste, particularly since PVC and cast iron piping are functionally equivalent.  “To establish economic waste, the work performed must substantially comply with the specifications; the work must be adequate for the intended purpose; and the cost of correction must be economically wasteful.  Economic waste does not ipso facto excuse non-performance but serves to limit excessive damages for repair of non-conforming work.”  Appeal of-Sauer, Inc., supra(internal quotation omitted).

The Board found that economic waste did not apply because the prime contractor did NOT substantially comply with the specification and PVC was not the functional equivalent to cast iron based on the intended application (which was to control the noise level and sound transmission of waste materials flowing through the piping).  Further, while the government was receptive to another remedial measure, none was offered to the government.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CERTIFYING CLAIM UNDER CONTRACT DISPUTES ACT

Under the Contract Disputes Act (41 USC 7101 en seq.), when a contractor submits a claim to the government in excess of $100,000, the claim MUST contain a certification of good faith, as follows:

For claims of more than $100,000 made by a contractor, the contractor shall certify that–

(A) the claim is made in good faith;

(B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief;

(C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and

(D) the certifier is authorized to certify the claim on behalf of the contractor.

41 U.S.C. 7103(b)(1).  See also 48 C.F.R. s. 33.207(c) as to the wording of the certification.

The contracting officer is not required to render a final decision on the claim within 60 days if, during this time period, he/she notifies the contractor of the reasons why the certification is defective. 41 U.S.C. 7103(b)(3).   Importantly, the contracting officer’s failure to render a decision within 60 days is deemed an appealable denial.

However, “[a] defect in the certification of a claim does not deprive a court or an agency board of jurisdiction over the claim. Prior to the entry of a final judgment by a court or a decision by an agency board, the court or agency board shall require a defective certification to be corrected.”  Id.

This is important.  In a recent decision out of the Federal Circuit, DAI Global, LLC v. Administrator of the United States Agency for International Development, 945 F.3d 1196 (Fed. Cir. 2019), a government contractor submitted a claim to the government with a defective certification.   The contracting officer waited 70 days (not the required 60 days) before notifying the contractor that the claims did not contain the required certification.   The contractor (smartly interpreting the contracting officer’s untimely notification as a denial of the claim) appealed to the Civilian Board of Contract Appeals.   The Board dismissed the contractor’s claims for lack of jurisdiction claiming the contractor failed to certify the claims and the contractor’s errors in preparing the certification were not correctible.  The contractor appealed to the United States Court of Appeals, Federal Circuit.

First, the appellate court held that the Contract Disputes Act states that a defect in the certification does NOT deprive a board over jurisdiction.  Whether the defect is technical in nature or not is of no moment since a board is not deprived of jurisdiction if there is any defect in the certification.

Second, the appellate court held that that the contracting officer failed to timely notify the contractor of the defective certification.  It was required to either issue a final decision on the claim or notify the contractor of the defective certification within 60 days.  “Because the contracting officer failed to issue a decision within the statutory period [60 days], [the contractor’s] claim was deemed denied and became appealable to the Board.” DAI Global, LLC, supra.

It is always good practice to work with counsel when preparing or submitting a claim.  Here, the contractor had good counsel as counsel treated the contracting officer’s untimely notification to the contractor of a defective certification as an appealable denial of the claim.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.