DO NOT FILE A MILLER ACT PAYMENT BOND LAWSUIT AFTER THE ONE-YEAR STATUTE OF LIMITATIONS

Under the Miller Act, a claim against a Miller Act payment bond must be commenced “no later than one year after the date on which the last of the labor was performed or material was supplied by the person bringing the action.” 40 U.S.C. s. 3133(b)(4).  Stated another way, a claimant must file its lawsuit against the Miller Act payment bond within one year from its final furnishing on the project.

Filing a lawsuit too late, i.e., outside of the one-year statute of limitations, will be fatal to a Miller Act payment bond claim.  This was the outcome in Diamond Services Corp. v. Travelers Casualty & Surety Company of America, 2022 WL 4990416 (5th Cir. 2022) where a claimant filed a Miller Act payment bond lawsuit four days late.  That four days proved to be fatal to its Miller Act payment bond claim and lawsuit.  Do not let this happen to you!

In Diamond Services Corp., the claimant submitted a claim to the Miller Act payment bond surety.  The surety issued a claim form to the claimant that requested additional information. The claimant returned the surety’s claim form. The surety denied the claim a year and a couple of days after the claimant’s final furnishing.  The claimant immediately filed its payment bond lawsuit four days after the year expired.  The claimant argued that the surety should be equitably estopped from asserting the statute of limitations in light of the surety’s letter requesting additional information. (The claimant was basically arguing that the statute of limitations should be equitably tolled.) The trial court dismissed the Miller Act payment bond claim finding it was barred by the one-year statute of limitations and that equitable estoppel did not apply.

On appeal, the Fifth Circuit maintained that a party must show it was misled to its detriment when relying on equitable estoppel.  The Fifth Circuit held the surety’s letter with its claim form and requesting additional information “made no representations that [the claimant] would be paid or that [the surety] would engage in claim negotiations with [the claimant], and explicitly reserved ‘all rights and defenses…include[ing], without limitation, defenses that may be available under any applicable notice and suit limitation provisions.’” Diamond Services Corp., supra. Hence, it was not reasonable for the claimant to rely on this letter in electing not to timely bring suit within the one-year statute of limitations.

Sureties, as a matter of course, will respond to its receipt of a claim requesting additional information.  That letter may accompany the surety’s preferred claim form.  Let’s be clear here.  The completion of the claim form and furnishing of additional information is not a statutory requirement to pursue a Miller Act payment bond claim (and it’s not a statutory requirement to many statutory bonds). Whether the claim form is submitted, or whether additional information is furnished, does not equate to a surety paying a claim.  It just does not.  For this reason, there should NEVER be an instance where a claimant forbears its rights to timely sue thinking a surety will pay the claim based on the submission of a claim form or additional information.

Timely file your Miller Act payment bond lawsuit within the one-year statute of limitations.  No ifs, ands, or buts.  This is true whether you submit a claim form or additional information or you do not.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: COMPELLING ARBITRATION BASED ON EQUITABLE ESTOPPEL

In the prior posting, I discussed arbitration provisions and to clearly and unmistakably include in the arbitration provision the person — judge or arbitrator — you want to determine the arbitrability of a given dispute.

In another posting, I discussed how the doctrine of equitable estoppel can be used by a non-signatory to a contract with an arbitration provision to compel arbitration or to compel a non-signatory to arbitration. This occurs “when a signatory to a contract containing the arbitration clause raises allegations of substantially interdependent and concerted misconduct by both a non-signatory [to the contract] and one or more of the signatories to the agreement.” Kratos Investments LLC v. ABS Healthcare Services, LLC, 46 Fla.L.Weekly D603a (Fla. 3d DCA 2021) (internal citations omitted).

Whether or not to include an arbitration provision in your contract is a dispute resolution consideration that should be factored in on the frontend.  Further, whether or not to compel a given dispute to arbitration based on an arbitration provision (whether or not you are a non-signatory to the contract with the arbitration provision and want to raise equitable estoppel) is another dispute resolution consideration that should be factored in when the dispute arises.  It is always best to consult with counsel during the contract drafting and negotiation process and when the dispute arises to best prepare for your dispute resolution options moving forward

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

GOOD-TO-KNOW POINTS REGARDING (I) MILLER ACT PAYMENT BONDS AND (II) PAYMENT BOND SURETY COMPELLING ARBITRATION

Every now and then I come across an opinion that addresses good-to-know legal issues as a corollary of strategic litigation decisions that are questionable and/or creative.  An opinion out of the United States District Court of New Mexico, Rock Roofing, LLC v. Travelers Casualty and Surety Company of America, 2019 WL 4418918 (D. New Mexico 2019), is such an opinion.

In Rock Roofing, an owner hired a contractor to construct apartments. The contractor furnished a payment bond.  The contractor, in the performance of its work, hired a roofing subcontractor.  A dispute arose under the subcontract and the roofer recorded a construction lien against the project. The contractor, per New Mexico law, obtained a bond to release the roofer’s construction lien from the project (real property).  The roofer then filed a lawsuit in federal court against the payment bond surety claiming it is entitled to: (1)  collect on the contractor’s Miller Act payment bond (?!?) and (2) foreclose its construction lien against the lien release bond furnished per New Mexico law.

Count I – Miller Act Payment Bond

Claiming the payment bond issued by the contractor is a Miller Act payment bond is a head scratcher. This claim was dismissed with prejudice upon the surety’s motion to dismiss. This was an easy call.

A Miller Act payment bond is a bond a prime contractor gives to the United States (US) for a public project. Here, the contractor entered into a contract with a private developer for a private apartment project. There was nothing to suggest that the private developer was, in fact, the US government or an agent of the US government.  There was also nothing to suggest that the apartment project was, in fact, a public project.  The roofer alleged that it believed the US Department of Housing and Urban Development provided funding for the project. The Court found this allegation as a big so-what: “The Court finds this allegation insufficient to demonstrate either the payment bond was furnished to the [US] Government as required by the [Miller Act], or that the apartment complex was a public building or public work as required by the [Miller Act].” Rock Roofing, LLC, 2019 WL at *3.

Count II – Foreclosure of Construction Lien Against Lien Release Bond

The surety moved to compel the roofer’s foreclosure claim against the lien release bond to arbitration pursuant to the contractor’s subcontract with the roofer.  The roofer countered that arbitration was inappropriate since the surety was not a party to the subcontract.

The Court (relying on a Florida district court opinion I was intimately involved with) found that the doctrine of equitable estoppel applied to compel the roofer to arbitration because the roofer’s claim for payment was based on its subcontract that contains the arbitration provision. “Because [the roofer’s] claim on the payment bond depends on its subcontract with [the contractor], the arbitration clause in the subcontract must precede [the roofer’s] right to bring suit as provided by the payment bond.” Rock Roofing LLC at *7.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.