VIOLATION OF THE BUILDING CODE IS A QUESTION OF LAW

imagesIn construction defect disputes, oftentimes the owner (or developer or association, as may be applicable) will assert a claim against the general contractor, and perhaps, subcontractors for a violation of the building code.  Such a claim is authorized pursuant to Florida Statute s. 553.84 that provides:

 

Notwithstanding any other remedies available, any person or party, in an individual capacity or on behalf of a class of persons or parties, damaged as a result of a violation of this part or the Florida Building Code, has a cause of action in any court of competent jurisdiction against the person or party who committed the violation; however, if the person or party obtains the required building permits and any local government or public agency with authority to enforce the Florida Building Code approves the plans, if the construction project passes all required inspections under the code, and if there is no personal injury or damage to property other than the property that is the subject of the permits, plans, and inspections, this section does not apply unless the person or party knew or should have known that the violation existed.

 

A violation of the building code serves as evidence of negligence by the offending party.  See Russ v. Wollheim, 915 So.2d 1285, n.1 (Fla. 2d DCA 2005) (“A building code is designed to protect the general public rather than a particular class of individuals, and therefore, violation of a building code is merely evidence of negligence.” )

 

But who determines whether an asserted defect, error, or omission constitutes a violation of the building code?  Is this a question of law for the judge?  Or, is this a question of fact for the jury (in a jury trial)?  Remarkably, cases have held that a violation of a building code, a complicated and rather specialized issue, is a question of law for the judge to determine.

 

In Edward J. Seibert, A.I.A. Architect and Planner, P.A. v. Bayport Beach and Tennis Club Ass’n, Inc., 573 So.2d 889 (Fla. 2d DCA 1990), a condominium association filed suit against the architect among others.  The jury found that the architect was liable for violating the building code in the fire exit design even though the design had been approved by the building department upon the issuance of the building permit. To support this violation, the association had an expert testify regarding his interpretation regarding the building code. The architect testified that his design complied with the building code and had two supporting expert opinions.  The verdict form asked the jury if the fire exist design complied with the applicable code.  The Second District held that the interpretation of the code was a question of law that should not have been submitted to the jury.

 

They [the parties] instead presented conflicting opinions as to how the code should be interpreted. The jury was allowed to determine the meaning of the code and then whether Seibert [architect] violated the code by designing only one fire exit. This was error. An expert should not be allowed to testify concerning questions of law, and the interpretation of the building code presented a question of law.

 

 

It was the duty of the trial court to interpret the meaning of the code and instruct the jury concerning that meaning. Any conflicts in interpretation were for the court to resolve and their resolution was not a jury issue.

Edward J. Seibert, 573 So.2d at 891-9 (internal citations omitted).

 

Further, in Lindsey v. Bill Arflin Bonding Agency, Inc., 645 So.2d 565 (Fla. 1st DCA 1994), a personal injury plaintiff sued an owner for slipping on a wet spot on stairs.  The plaintiff claimed that the stairs lacked handrails in violation of the building code.  The owners relied on testimony from a building department official opining that handrails were not required based on his interpretation of the code / ordinance at-issue.   The First District, however, found:

 

Expert testimony as to the meaning of an ordinance is not appropriate when the disputed language consists of “ordinary words susceptible to being given plain effect consistent with their ordinary meaning.” The legal effect of a building code presents a question of law for the court, not a question of fact for the jury. While expert testimony may be relevant and helpful to the court where a statute or ordinance contains words of art or scientific and technical terms, even then such testimony cannot dictate the court’s construction of the enactment.

Lindsey, 645 So.2d at 568 (internal citations omitted).

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

UTILIZING EXPERT WITNESSES FOR CONSTRUCTION DISPUTES

untitledExpert witnesses are an integral part of construction disputes.  An expert assists a party in proving or disproving liability or damages. In construction disputes, an expert could be used relating to a construction or design defect, a delay, an inefficiency, the standard of care, building code violations, the repair protocol, etc.   Irrespective of the basis for retaining an expert, oftentimes the expert generates a report with his/her opinions (and documentation relied on to form those opinions), is deposed, and, if the case proceeds to trial, is relied on to provide expert opinion testimony.

 

Recently, I wrote an article about the Daubert test which is a court’s gatekeeping test to determine whether the expert opinion testimony is admissible.  Parties utilizing experts in construction disputes need to understand this Daubert test.  Please take a look at this article to familiarize yourself with Daubert to ensure you are engaging and preparing the right expert.

 

Additionally, I wrote another article on expert opinion testimony including the standard of appellate review if a court strike’s expert opinion testimony or allows an expert to testify subject to an objection.  Please take a look at this article because it is common for a party prior to trial to move to strike an opposing expert or portions of that expert’s opinion testimony.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.