VIOLATION OF BUILDING CODE CLAIM APPLIES TO “COMPLETED BUILDING”

In construction defect disputes, it is routine to see a claim known as a violation of building code claim.  It is a statutory claim brought under Florida Statute s. 553.84.

Section 553.84 provides:

Notwithstanding any other remedies available, any person or party, in an individual capacity or on behalf of a class of persons or parties, damaged as a result of a material violation of this part or the Florida Building Code has a cause of action in any court of competent jurisdiction against the person or party who committed the material violation; however, if the person or party obtains the required building permits and any local government or public agency with authority to enforce the Florida Building Code approves the plans, if the construction project passes all required inspections under the code, and if there is no personal injury or damage to property other than the property that is the subject of the permits, plans, and inspections, this section does not apply unless the person or party knew or should have known that the material violation existed. For purposes of this section, the term “material violation” means a Florida Building Code violation that exists within a completed building, structure, or facility which may reasonably result, or has resulted, in physical harm to a person or significant damage to the performance of a building or its systems.

A recent federal district case examined a violation of building code claim when the dispute did not center on a “completed building, structure or facility.”

In WP Property Holdings I, LLC v. JR&co, Inc., 2026 WL 3561832 (M.D. Fla. 2026), a warehouse owner hired a contractor to install roof membrane on its existing roof, i.e., a roof replacement project. During the course of the project, the roof failed causing water intrusion. The warehouse owner sued the contractor and included a violation of building code claim under Florida Statute s. 553.84.  The federal district court granted summary judgment on this claim in favor of the contractor because the claim did NOT involve a completed building:

Construction and repair work is generally a time-intensive affair. Until a job is done, the work will almost inevitably stand outside the building code. Take a roof replacement. The moment a contractor rips off an old roof, the building is obviously no longer code-compliant—and cannot become compliant again until the new roof is in place. Under [the owner’s] reading, every roofer would violate § 553.84 simply by starting the job, remaining perpetually liable until the final nail is driven. That makes no sense. Other legal doctrines—negligence, for one— more aptly govern how contractors manage an active job site. Section 553.84 does a different job: it ensures that the finished product complies with the code. Because [the contractor’s] work was still in progress, [the owner’s] statutory claim fails as a matter of law.

To bring the point home, [the owner] offers no precedent applying § 553.84 to ongoing repair or construction jobs. And every case the Court could find invoking this statute involved finished products.

WP Property Holdings, supra, at *2 (citations omitted).

Remember, when asserting a violation of building code claim, make sure the claim and dispute is focused on a “completed building, structure, or facility.”

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

VIOLATION OF THE BUILDING CODE IS A QUESTION OF LAW


In construction defect disputes, oftentimes the owner (or developer or association, as may be applicable) will assert a claim against the general contractor, and perhaps, subcontractors for a violation of the building code.  Such a claim is authorized pursuant to Florida Statute s. 553.84 that provides:

 

Notwithstanding any other remedies available, any person or party, in an individual capacity or on behalf of a class of persons or parties, damaged as a result of a violation of this part or the Florida Building Code, has a cause of action in any court of competent jurisdiction against the person or party who committed the violation; however, if the person or party obtains the required building permits and any local government or public agency with authority to enforce the Florida Building Code approves the plans, if the construction project passes all required inspections under the code, and if there is no personal injury or damage to property other than the property that is the subject of the permits, plans, and inspections, this section does not apply unless the person or party knew or should have known that the violation existed.

 

A violation of the building code serves as evidence of negligence by the offending party.  See Russ v. Wollheim, 915 So.2d 1285, n.1 (Fla. 2d DCA 2005) (“A building code is designed to protect the general public rather than a particular class of individuals, and therefore, violation of a building code is merely evidence of negligence.” )

 

But who determines whether an asserted defect, error, or omission constitutes a violation of the building code?  Is this a question of law for the judge?  Or, is this a question of fact for the jury (in a jury trial)?  Remarkably, cases have held that a violation of a building code, a complicated and rather specialized issue, is a question of law for the judge to determine.

 

In Edward J. Seibert, A.I.A. Architect and Planner, P.A. v. Bayport Beach and Tennis Club Ass’n, Inc., 573 So.2d 889 (Fla. 2d DCA 1990), a condominium association filed suit against the architect among others.  The jury found that the architect was liable for violating the building code in the fire exit design even though the design had been approved by the building department upon the issuance of the building permit. To support this violation, the association had an expert testify regarding his interpretation regarding the building code. The architect testified that his design complied with the building code and had two supporting expert opinions.  The verdict form asked the jury if the fire exist design complied with the applicable code.  The Second District held that the interpretation of the code was a question of law that should not have been submitted to the jury.

 

They [the parties] instead presented conflicting opinions as to how the code should be interpreted. The jury was allowed to determine the meaning of the code and then whether Seibert [architect] violated the code by designing only one fire exit. This was error. An expert should not be allowed to testify concerning questions of law, and the interpretation of the building code presented a question of law.

 

It was the duty of the trial court to interpret the meaning of the code and instruct the jury concerning that meaning. Any conflicts in interpretation were for the court to resolve and their resolution was not a jury issue.

Edward J. Seibert, 573 So.2d at 891-9 (internal citations omitted).

 

Further, in Lindsey v. Bill Arflin Bonding Agency, Inc., 645 So.2d 565 (Fla. 1st DCA 1994), a personal injury plaintiff sued an owner for slipping on a wet spot on stairs.  The plaintiff claimed that the stairs lacked handrails in violation of the building code.  The owners relied on testimony from a building department official opining that handrails were not required based on his interpretation of the code / ordinance at-issue.   The First District, however, found:

 

Expert testimony as to the meaning of an ordinance is not appropriate when the disputed language consists of “ordinary words susceptible to being given plain effect consistent with their ordinary meaning.” The legal effect of a building code presents a question of law for the court, not a question of fact for the jury. While expert testimony may be relevant and helpful to the court where a statute or ordinance contains words of art or scientific and technical terms, even then such testimony cannot dictate the court’s construction of the enactment.

Lindsey, 645 So.2d at 568 (internal citations omitted).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DEFERENCE GIVEN TO ARBITRATION PROVISIONS


The recent case of Pulte Home Corp. v. Bay at Cypress Creek Homeowner’s Association, Inc., 38 Fla. L. Weekly D1705a (Fla. 2d DCA 2012) involves a dispute by a homeowner’s association against its developer / homebuilder. In this case, the association sued the developer / homebuilder for building code violations under Florida Statute s. 553.84. The association did this in order to try to circumvent an arbitration provision in the developer / homebuilder’s limited warranty given in favor of initial purchasers. The developer / homebuilder moved to compel arbitration which was denied by the trial court. On appeal, the Second District Court of appeals reversed the trial court finding that statutory claims were covered by the arbitration provision.

 

The issue to remember is that deference is given to arbitration provisions and that statutory claims, breach of contract claims, warranty claims, and tort claims are all claims that may be submitted to arbitration pursuant to an arbitration provision. In Pulte Home, the association, for strategic reasons, did not want to arbitrate and tried to pursue a claim that did not subject it to arbitration.  Although the Second District did not recite the arbitration provision in the opinion, the Court maintained that the agreement to arbitrate in the limited warranty given to initial purchasers covered statutory claims.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.