DETERMINING OCCURRENCE FOR INJURY UNDER COMMERCIAL GENERAL LIABILITY POLICY WITHOUT APPLYING “TRIGGER THEORY”

Oftentimes an occurrence in a commercial general liability policy is defined as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions.”   It is this occurrence that causes the bodily injury or property damage that may be covered by the policy.

An interesting non-construction case determined an occurrence under a commercial general liability policy occurred when the negligent act occurred irrespective of the date of discovery or the date the claim was discovered or asserted. See Certain Underwriters at Lloyd’s, London Subscribing to Policy No. J046137 v. Pierson, 46 Fla.L.Weekly D1288c (Fla. 4thDCA 2021). This is interesting because the appellate court did NOT apply a “trigger theory” to first determine the occurrence’s policy period.  The appellate court found it did not need to determine which “trigger theory” applied to determine the occurrence for the injury and relied on a cited case: “trigger theories are generally used in the context of deciding when damage occurred ‘in cases involving progressive damages, such as latent defects, toxic spills, and asbestosis’ because the time between the ‘injury-causing event (such as defective construction, a fuel leak, or exposure to asbestos), the injury itself, and the injury’s discovery or manifestation can be so far apart.”  Pierson, supra, citing and quoting Spartan Petroleum Co. v. Federated Mut. Ins. Co., 162 F.3d 805, 808 (4th Cir. 1998).

In Pierson, police officers were found civilly liable for civil rights violations that occurred twenty-years earlier when the officers physically and verbally forced a 15-year old boy to confess to a crime.  Many years later, DNA evidence proved the boy did not commit the crime he was forced to confess and was incarcerated for.   The officers sued the police department’s commercial general liability policy for failing to indemnify them in the civil lawsuit. The policy, however, was NOT in effect twenty years earlier when the officers verbally and physically forced the confession.  “Since it is undisputed that the Officers’ misconduct occurred twenty years prior to the execution of the policies, there can be no duty to indemnify in this case…. [T]he fact that [the boy] suffered the consequences of the Officers’ wrongful conduct throughout his incarceration, including while the subject policies were in effect, is irrelevant for purposes of determining whether the Insurer has a duty to indemnify. Likewise, the fact that [the boy] was exonerated while the 2009 policy was in effect is of no consequence.” Pierson, supra.

What does this holding mean?  It could likely mean outside of a latent defect scenario or a pollution liability issue–or property damage scenario–a “trigger theory” to determine when an occurrence occurred or is triggered is not applicable.  An occurrence will be deemed to occur when the accident causing the injury occurred, as defined by the policy.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

“OTHER INSURANCE” PROVISIONS TO LIMIT INSURER’S RISK

Insurance policies often contain an “Other Insurance” provision to limit or control an insurer’s risk if another insurer covers the same risk / loss.  See Pavarini Construction Co. (Se) Inc. v. Ace American Ins. Co., 161 F.Supp.3d 1227, 1234 (S.D.Fla. 2015) (“Other Insurance” provisions apply “when two or more insurance policies are on the same subject matter, risk, and interest.”).  This is an important provision to insurers and may be modified by an endorsement to your insurance policy.  It is designed to determine whether the policy, as discussed below, should serve as a primary policy or excess policy.  It is important to understand this “Other Insurance” provision and its application because it will come up, particularly in a multi-party construction defect dispute.

An example of an “Other Insurance” provision in a commercial general liability (CGL), subject to any modification through an endorsement to the policy, may provide something to the effect:

 

 

 

 

4. Other Insurance

If other valid and collectible insurance is available to the insured for a loss we cover under Coverages A or B of this Coverage Part, our obligations are limited as follows:

a. Primary Insurance

This insurance is primary except when b. below applies.  If this insurance is primary, our obligations are not affected unless any of the other insurance is also primary.  Then we will share with all that other insurance by the method described in c. below.

b. Excess Insurance

This insurance is excess over:

1. Any of the other insurance, whether primary excess, contingent, or on any other basis:

(a) That is Fire, Extended Coverage, Builder’s Risk, Installation Risk or similar coverage for “your work”;

2. Any other primary insurance available to you covering liability for damages arising out of the premises or operations for which you have been added as an additional insured by attachment of an endorsement.

c. Method of Sharing

If all of the other insurance permits contribution by equal shares we will follow this method also.  Under this approach, each insurer contributes equal amounts until it has paid its applicable limit of insurance or none of the loss remains, whichever comes first.

If any of the insurance does not permit contribution by equal shares, we will contribute by limits.  Under this method, each insurer’s share is based on the ratio of its applicable limit of insurance to the total applicable limits of insurance of all insurers.

If a policy is deemed as excess coverage, than “liability attaches only after a predetermined amount of primary coverage has been exhausted.”  Tudor Ins. Co. v. American Casualty Co. of Reading Pennsylvania, 274 F.Supp.3d 1278, 1283 (N.D.Fla. 2017) (quotation and citation omitted).  Hence, the “Other Insurance” provision allows an insurer to limit or control its risk by turning the policy into an excess policyId. (when excess provision applies than limits of the primary policy need to first be exhausted).

When deciding the priority of coverage among multiple insurers, Florida courts generally rely on the language of the several policies, with careful attention to the other insurance clauses.  Where two insurance policies contain conflicting excess other insurance clauses, those clauses cancel one another out….  [W]here a court must allocate between two policies at the same level that contain incompatible excess clauses, the majority rule is that the two excess clauses cancel each other out, and the loss is pro-rated between the two policies. The proper method of allocation is to disregard the other insurance clauses, treat the two excess insurers as co-excess insurers, and pro-rate the loss between the two policies.

***

Florida law recognizes an exception to the rule governing competing “Other Insurance” provisions where a right of indemnification exists between the parties insured under the respective policies of insurance, especially where … one of the policies happens to cover the indemnity obligation. In this circumstance, a clear majority of jurisdictions give controlling effect to the indemnity obligation of one insured to the other insured over the ‘other insurance’ or similar clauses in the policies of insurance.  Florida cases have consistently recognized that where a loss is covered by two or more primary policies of insurance, the operation of an indemnification agreement between the common insureds has the result of shifting responsibility for the entire loss to the carrier for the indemnitor. [U]nder Florida law an indemnity agreement control[s] all the rights and obligations of the parties and their privies (the insurers), and the fact that the parties carried insurance did not ‘detract from or modify’ their indemnity agreement.

Amerisure Ins. Co. v. Auchter Company, 2017 WL 3601387, *24 (M.D.  2017) (internal quotations and citations omitted).   See also Pavarini Construction Co. (Se) Inc., 161 F.Supp.3d at 1235 (“Courts disregard “Other Insurance” provisions where…there is a contractual right or indemnification.”).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.