ARBITRATION PROVISION MUST BE INCORPORATED INTO A BOND FOR SURETY TO ELECT ARBITRATION

Sureties cannot exercise unilateral election rights that are reserved for the principal of the underlying contract.Anderson Service Corp. v. Old Republic Surety Company, 2026 WL 61436, *2 (Fla. 4th DCA 2026). This was the holding in a recent case dealing with arbitration.

In this case, a subcontractor entered into a contract with a contractor that gave the contractor the right to elect arbitration in Pennsylvania. A dispute arose and the subcontractor recorded a construction lien. The contractor transferred the lien to a lien transfer bond under Florida law. (The contractor was the principal of the lien transfer bond.) The lien transfer bond surety then moved to compel the subcontractor to arbitration based on the underlying subcontract. The trial court agreed to compel arbitration but this was reversed on appeal.

The lien transfer bond did NOT incorporate the underlying subcontract. Lien transfer bonds don’t do this so the election to arbitrate the dispute was in a separate document between the contractor and subcontractor. It was not in the lien transfer bond and the contractor was NOT a party to the dispute. “Here, as discussed above, the surety bond did not contain an arbitration agreement and did not incorporate the subcontract or the subcontract’s arbitration provision.Anderson Service Corp., supra, at *2.

The subcontractor knew about the arbitration provision which is presumably why it did not sue the contractor and only sued under the lien transfer bond. The subcontractor did not want to arbitrate and wanted an argument to move beyond that arbitration provision. This was the way to do it by only suing the lien transfer bond surety.  Now, if the contractor (principal) intervened and then moved the compel arbitration of a dispute it had with the subcontractor, perhaps that would have created the right argument to compel arbitration or stay the lawsuit involving the lien transfer bond surety pending the outcome of the arbitration. But that did not occur. See generally Anderson Service Corp. at *2 (“Further, [the contractor] is a nonparty which never elected to exercise or waive its right to arbitration under the subcontract.”).   Although this case deals with a lien transfer bond surety, the rationale should extend in other scenarios where the arbitration provision is not incorporated into the bond.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DON’T ASSERT AS A COUNTERCLAIM TO A LIEN FORECLOSURE LAWSUIT AN ORDER TO SHOW CAUSE CLAIM

If there is a construction lien on your property and you don’t like the lien, here are options to deal with the lien:

1. You negotiate a resolution a get a satisfaction of lien to record in the public records. Or, you can transfer the lien to the security of a lien transfer bond, but that just means the lienor would need to foreclose against the bond instead of the real property. In other words, the lien is collateralized by the lien transfer bond and not the real property so it does not resolve the lien.

2. You record a Notice of Contest of Lien to shorten the lienor’s statute of limitations to foreclose on the construction lien to 60 days. (See here.) If the lienor does not timely foreclose, then the lien is of no effect as a matter of law.  However, this does force the issue, meaning the lienor may file a lien foreclosure lawsuit sooner than later. (But, if they file the lawsuit sooner, then the lienor was always going to file the lawsuit later.)

3. You can file a lawsuit for an Order to Show Cause under Fla. Stat. s. 713.21(4) and force the lienor to file a lien foreclosure counterclaim within 20 days from service of the show cause summons. (See here.) The only time you’d really do this is if you want to initiate a lawsuit that you’d probably initiate no matter what. Otherwise, the Notice of Contest of Lien is more cost effective and more efficient.

In a recent case, Custom Homes By Triumph, LLC v. Sverdlow, 50 Fla.L.Weekly D1946a (Fla. 2nd DCA 2025), a lienor filed a lien foreclosure lawsuit.  The owner asserted a counterclaim that included the Order to Show Cause. The lienor didn’t timely respond to the counterclaim as the lienor was the one that initiated the lawsuit by filing the lien foreclosure lawsuit.  The trial court therefore dismissed the lien. Shocking outcome! The lienor appealed and prevailed for a couple of big reasons.

First, with the Order to Show Cause complaint, a lienor’s 20 days to respond is based on the receipt of a specifically worded show cause summons. Here, there was no summons because the owner asserted a counterclaim because, again, the lienor initiated the lawsuit.  Without the service of the summons, there is nothing that starts the 20-day clock.

Second, the lienor had already foreclosed. There was nothing for it to do. In response to an Order to Show Cause Complaint, a lienor needs to foreclose on the construction lien within the 20 days. But, here, the lienor already did so. (“The lienor’s obligation is to show cause “why his or her lien should not be enforced by action or vacated and canceled of record,” and the lien must be discharged only “[u]pon failure of the lienor to show cause why his or her lien should not be enforced or the lienor’s failure to commence such action before the return date of the summons.” [The lienor’s] complaint included a cause of action to foreclose its lien. And by seeking to foreclose its lien, [the lienor] was necessarily seeking to enforce it. So even if the clerk had issued a show-cause summons, [the lienor] had already completed one of the two alternative actions — “show cause . . . why [the] lien should not be enforced [by action]” or “commence such action” — that the summons would have directed it to accomplish, that is, commence an action to enforce its lien.” See Custom Homes By Triumph, supra (internal citations omitted))

Look, if you are considering the Order to Show Cause Complaint to deal with a construction lien, there is nothing to consider if the lien is already being foreclosed and you are not the plaintiff. You don’t get a “gotcha” after the lien is already foreclosed because the foreclosing lienor doesn’t respond to a needless claim. This was an appeal over an issue that should have never been an issue.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

FILING MOTION TO INCREASE LIEN TRANSFER BOND (BEFORE TRIAL COURT LOSES JURISDICTION OVER FINAL JUDGMENT)

If a construction lien is recorded against real property, the lien can be transferred to a lien transfer bond.  This transfers the security or collateral of the construction lien from the real property to the lien transfer bond. The lien transfer bond can be a bond posted by a surety company or it can be cash.  This is governed by Florida Statute s. 713.24.  The amount of the lien does not dictate the amount of the lien transfer bond.  Rather, the lien transfer bond needs to be in the amount of the lien, plus interest on that amount for three years, plus $1,000 or 25% of the amount of the lien (whichever is greater so factor in the 25%) to cover attorney’s fees. Fla. Stat. 713.24(1).

If you are looking to transfer a construction lien to a lien transfer bond, make sure to consult with counsel.

Keep in mind there is a statutory mechanism for a lienor to increase the lien transfer bond to cover attorney’s fees and costs and notice the word “must” in the statute below. Pursuant to Florida Statute s. 713.24(3):

Any party having an interest in such security or the property from which the lien was transferred may at any time, and any number of times, file a complaint in chancery in the circuit court of the county where such security is deposited, or file a motion in a pending action to enforce a lien, for an order to require additional security, reduction of security, change or substitution of sureties, payment of discharge thereof, or any other matter affecting said security. If the court finds that the amount of the deposit or bond in excess of the amount claimed in the claim of lien is insufficient to pay the lienor’s attorney’s fees and court costs incurred in the action to enforce the lien, the court must increase the amount of the cash deposit or lien transfer bond. Nothing in this section shall be construed to vest exclusive jurisdiction in the circuit courts over transfer bond claims for nonpayment of an amount within the monetary jurisdiction of the county courts.

In a recent case, Edmondson v. Tri-County Electrical Services, Inc., 2023 WL 2995420 (Fla. 4th DCA 2023), a lien was transferred to a cash bond by the real property owner.  The contractor-lienor moved to have the court increase the amount of the cash security to better cover attorney’s fees and costs accrued in the litigation. The court deferred ruling on the motion. Subsequently, the court had a bench trial and the contractor prevailed. The court entered final judgment in favor of the contractor and reserved ruling on attorney’s fees, interest, and court costs. The court thereafter entered an amended final judgment that included attorney’s fees, interest, and court costs.  The court then conducted a hearing to increase the cash bond and granted the contractor’s motion for the cash bond to be increased.  The issue was that the court no longer had jurisdiction to require the owner to increase the cash bond:

The action here was not ‘pending’ under section 713.24(3). The general rule is that an action remains pending in the trial court until after a final judgment and such time as an appeal is taken or time for an appeal expires. By the time the trial court had ruled on the motion to increase the bond, the time for an appeal had passed. Therefore, because the matter was no longer pending, the trial court lacked authority to consider the motion.

The trial court was without jurisdiction to grant Contractor’s motion to increase the bond.

Edmondson, supra, at *2 (internal citations omitted).

Here, the contractor should have requested the trial court rule on the deferred motion to increase the cash bond BEFORE the amended final judgment was entered. Or, at a minimum, the contractor should have timely filed a motion for rehearing as to the amended final judgment to address this deferred motion to increase the cash bond. Once the rehearing period expired, “the trial court no longer has jurisdiction over a final judgment.” Edmondson, supra, at *1 (“Contractor did not file a timely motion for rehearing, which would have been the time to raise the bond increase issue.”). Id.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

HUH? ACTION ON CONSTRUCTION LIEN “RELATES BACK” DESPITE NOTICE OF CONTEST OF LIEN

Not every case law you read makes sense. This sentiment goes to the uncertainty and grey area of certain legal issues.  It is, what you call, “the nature of the beast.”  You will read cases that make you say “HUH?!?” This is why you want to work with construction counsel to discuss procedures and pros / cons relative to construction liens.

An example of a case that makes you say “HUH” can be found in Woolems, Inc. v. Catalina Capstone Creations, Inc., 2023 WL 2777506 (Fla. 3d DCA 2023) dealing with a construction lien foreclosure dispute.

Here, a contractor filed a lawsuit against a subcontractor with a summons to show cause why the subcontractor’s construction lien should not be discharged.  This is a specific complaint filed under Florida Statute s. 713.21(4). This statute requires the lienor to essentially foreclose on its construction lien within 20 days after it was served with a “show cause” summons.  The subcontractor filed its answer and counterclaim but did NOT assert a claim to foreclose its construction lien.

Around the time of subcontractor’s answer and counterclaim, the contractor transferred the subcontractor’s lien to an all-cash lien transfer bond in accordance with Florida Statute s. 713.24. Once the lien transfer bond was recorded, the owner recorded a notice of contest of lien under Florida Statute s. 713.22. The notice of contest of lien shortens the limitations period to foreclose on a lien to 60 days.

The subcontractor did NOT timely foreclose its lien against the lien transfer bond and the general contractor moved to have its all-cash lien transfer bond returned, as it should do. The subcontractor filed its lien foreclosure against the lien transfer bond AFTER the 60-day window expired. The trial court, and affirmed by the appellate court, denied the general contractor’s request to have the lien transfer bond returned and allowed the subcontractor to assert its (dilatory) claim against the lien transfer bond claiming it related back in time to the subcontractor’s initial counterclaim.  HUH?!?

ISSUES GIVING RISE TO THE HUH

Here are the issues with this ruling:

  1. The subcontractor should have foreclosed its construction lien with the 20-day time period from receiving the summons to show cause. The case reflected the subcontractor asserted claims, but not the lien foreclosure claim subject to the summons to show cause. (The appeal did not discuss this point for reasons currently unknown.)
  2. Regardless of (1), the lien was transferred to a bond and a notice of contest of lien was recorded shortening the time period to foreclose the lien (as to the bond) to 60 days. There is case law referencing this procedure. Yet, the subcontractor still did not timely assert its claim against the lien transfer bond.
  3. The trial court applied the relation back doctrine which does nothing but completely water down the statutory purpose of a notice of contest of lien (not to mention the summons to show cause complaint).

RECOMMENDATIONS IN LIGHT OF RULING

In light of this ruling, here are my recommendations:

  1. If you are going to transfer a lien to a lien transfer bond, do it from the get-go. Then, record the notice of contest or pursue the summons to show cause complaint.
  2. If filing the summons to show cause complaint, wait for the 20-day time period to expire. If the time period expires, move to have the lien discharged before making the decision to transfer the lien to a lien transfer bond.
  3. If recording a notice of contest of lien, wait for the 60-day time period to expire before taking action.

The reality is that the procedure implemented in this case should have been fine but for the application of the relation back doctrine that makes you say HUH?!?

As mentioned, if dealing with a lien, please make sure to discuss strategic considerations with a construction counsel that can help navigate the process and advise on the pros and cons.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

MOVING FOR CERTIORARI RELIEF IF THE TRIAL COURT IMPROPERLY DISMISSES / DISCHARGES YOUR LIEN

Your construction lien oftentimes is your leverage to secure payment because the lien collateralizes the amount you are owed against real property, a leasehold interest, or alternative security if the lien is transferred to alternate security.  Having a court dismiss or discharge your construction lien claim is no good.  This is true even if a court dismisses or discharges a construction lien transferred to alternative security such as a lien transfer bond.  Without the lien, there is nothing securing the nonpayment—not the real property, not the leasehold interest (as discussed below), and not the alternative security if the lien is transferred.   But there is valuable recourse–moving for a petition for a writ of certiorari in the appellate court.  “Losing the benefit of a recovery under a bond on a claim to enforce a lien constitutes the type of irreparable harm necessary to entitle a party to certiorari relief.”  James B. Pirtle Construction, Co., Inc. v. Warren Henry Automobiles, Inc., 46 Fla.L.Weekly D2290a (Fla. 3d DCA 2021).

In James B. Pirtle, a contractor recorded a construction lien against a leasehold interest.   The property was owned by the City of Miami (public property) and the City leased the property to an entity, which in turn, entered into a ground lease with the defendant to construct and operate a car dealership. A dispute arose between the contractor and the defendant-tenant regarding the construction of the car dealership and the contractor recorded a construction lien against the leasehold interest.  The defendant transferred the contractor’s lien to a lien transfer bond and the contractor moved to foreclose its lien against the bond.

The defendant-tenant came up with an argument that the contractor could not even foreclose its lien against the leasehold interest because the real property was public property which is NOT lienable.  The trial court bought this argument (not sure why because the reasoning does not seem all that logical!) and the contractor’s lien was discharged.  This was reversed on appeal without a lengthy discussion because the contractor’s lien was NOT against the real property owned by the public body, but against the defendant-tenant’s leasehold interest.

The appellate court explained:

At common law, a leasehold interest was considered a type of personal property, not realty. This concept is incorporated into section 713.11, Florida Statutes, titled, ‘Liens for improving land in which the contracting party has no interest.’ In this section, Florida’s construction lien law explicitly states that ‘[w]hen the person contracting for improving real property has no interest as owner in the land, no lien shall attach to the land….

***

States and municipalities lease public property to private tenants in order to operate their facilities (e.g., parks, airports), and contractors doing work for those tenants have lien rights not on the property, but on the leasehold interest of that tenant.

James B. Pirtle, Inc., supra (internal citations omitted).

The trial court’s ruling would have ultimately meant that contractors performing work for tenants of publicly owned real property have no lien rights or ability to collateralize their nonpayment.  This naturally does not make much sense as it would simply dilute the fundamental purpose of being able to lien the tenant’s leasehold interest.  Recognizing this huge loss, the tenant moved for certiorari relief and the appellate court reversed the discharge of the lien keeping this important right alive — the lien against the defendant-tenant’s leasehold interest!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: THE NOTICE OF CONTEST OF LIEN IS A POWERFUL TOOL

If you receive a Notice of Contest of Lien, do NOT ignore it.  The Notice of Contest of Lien is a powerful tool that shortens the limitations period for a linear to foreclose on a construction lien to 60 days or else the lien is discharged by operation of law.   Conversely, if you receive a construction lien, consider recording a Notice of Contest of Lien based on its utility.

As an example of the usefulness of the Notice of Contest of Lien, in Rabil v. Seaside Builders, LLC, 226 So.3d 935 (Fla. 4th DCA 2017), a contractor filed a construction lien foreclosure lawsuit on a residential project.  The homeowners then transferred the lien to a lien transfer bond and recorded a Notice of Contest of Lien.  The contractor did not amend the lawsuit to sue the lien transfer bond surety within the 60-day window.  Consequently, the homeowners moved to dismiss the lien foreclosure lawsuit, release the lien transfer bond, and discharge the corresponding lis pendens.  The trial court denied the motion.  On appeal, the Fourth District reversed holding that “[b]ecause the contractor did not file suit against the surety within sixty days [in response to the Notice of Contest of Lien], the lien was automatically extinguished by operation of law, and the clerk was obligated to release the bond.” Rabil, 226 So.3d at 937.

This case exemplifies the utility of recording a Notice of Contest of Lien and how it benefitted the homeowner upon filing the Notice of Contest of Lien after recording the lien to a lien transfer bond post-initiation of the lawsuit.  The is exactly why a Notice of Contest of Lien should not be ignored.  If you receive one, the smart play is to immediately consult with counsel, just like the smart play if you receive a construction lien is to consult with counsel.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: REMEMBER TO TIMELY FORECLOSE LIEN AGAINST LIEN TRANSFER BOND

When a construction lien is transferred to a lien transfer bond pursuant to Florida Statute s. 713.24, instead of foreclosing the lien against the real property, you are foreclosing the lien against the lien transfer bond.  This is not a bad deal and, oftentimes, is probably ideal.   Remember, however, just because a construction lien was transferred to a lien transfer bond (pre-lawsuit) does not mean you get more time to file your lien foreclosure lawsuit.  A lawsuit must still be filed within one year (short of that period being specifically shortened under operation of the law).  The only exception is that if the lawsuit is filed and the lien transfer bond is then recorded (post-lawsuit), the lienor has one year to amend its lawsuit to sue the lien transfer bond.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

THERE IS VALUE RECORDING A NOTICE OF CONTEST OF LIEN


If you receive a construction lien on your property, I have preached the value in recording a Notice of Contest of Lien to shorten the lienor’s statute of limitations to foreclose on the lien from 1 year to 60 days.  If the unwary lienor fails to foreclose its lien within the shortened 60-day window, its lien is extinguished under the law. Ouch! (Check out this article and this article for more on Notice of Contest of Liens.)

 

Now, what if a lienor timely forecloses its lien and during the lien foreclosure lawsuit the lien is transferred from the real property to a lien transfer bond.  Typically, if a lien foreclosure lawsuit is underway and the lien is transferred to a lien transfer bond, the lienor has one year from the date of the transfer to amend its lawsuit to sue the lien transfer bond.   Could the owner record a Notice of Contest of Lien to shorten the lienor’s statute of limitations to amend its lawsuit from one year from the date of the transfer to 60 days?

 

In a recent case, the Second District held that an owner could record a Notice of Contest of Lien AFTER the lienor filed its lien foreclosure lawsuit to shorten to limitations period for the lienor to amend its lawsuit to sue the lien transfer bond to 60 days.   In this case, because the lienor failed to amend its lawsuit within 60 days, the Second District held that the lienor lost its right to sue the lien transfer bond.  This means the lienor no longer gets to foreclose its lien (against the real property or the lien transfer bond) all because a Notice of Contest of Lien was recorded after the lien foreclosure lawsuit was filed and after the lien was transferred to the bond.  This case serves as a huge “W” for owners that appreciate the value of the Notice of Contest of Lien! See Hiller v. Phoenix Associates of South Florida, Inc., 41 Fla.L.Weekly D881d (Fla. 2d DCA 2016) (“It is undisputed Phoenix [lienor] took no action in this case within sixty days after Hiller [owner] transferred the lien to a bond and served the notice of contest.  It is this failure on the part of Phoenix that compels reversal in this case.  The fact that Phoenix had a proceeding pending against the lien at the same time of the transfer did not excuse compliance with the other provisions of Chapter 713 [Lien Law]).”)

 

Remember, there is oftentimes a strategic value recording a Notice of Contest of Lien  if you are dealing with a construction lien.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

RECORDING THE NOTICE OF BOND TO TRANSFER THE CONSTRUCTION LIEN TO THE PAYMENT BOND


If a contractor furnishes a payment bond for a private project (per Florida Statute s. 713.23), a copy of that bond should be recorded with the Notice of Commencement recorded in the official records of the county where the project is located. A contractor furnishes a payment bond on a private project in order to exempt the owner’s real property from construction liens.

 
There are times, though, where a subcontractor or a supplier will still go ahead and record a lien against the owner’s real property even though there is a payment bond that was recorded with the Notice of Commencement. This is a frustrating scenario because the point of paying for the payment bond and furnishing the bond is to prevent this very scenario from occurring. No worries, however, because Florida’s Lien Law efficiently addresses this scenario by allowing the contractor or owner to record in the official records and serve on the lienor a verified Notice of Bond (attaching a copy of the payment bond) that will operate to transfer the lien to the payment bond. Fla. Stat. s. 713.23(2). A copy of the Notice of Bond form is provided below.

 
Moreover, this Notice of Bond procedure would apply even if the contractor furnished a payment bond, but for whatever reason, that payment bond was not recorded with the Notice of Commencement. When this happens, and it does happen, the subcontractor or supplier may honestly not know that the contractor actually furnished a payment bond and will move forward and record a lien. Again, no worries, because the contractor or owner should implement the same procedure by recording and serving the lienor with a Notice of Bond. Every lien recorded AFTER the execution and delivery of the payment bond will be transferred to the payment bond through the recording of the Notice of Bond (attaching a copy of the payment bond).

 

Now, if the contractor did NOT furnish a payment bond BEFORE the lien was recorded, the contractor could move to transfer the lien to a lien transfer bond pursuant to Florida Statute s. 713.24. This is different than a payment bond. The lien transfer bond is simply a mechanism where a contractor through a statutory procedure procures and records a lien transfer bond that is designed to transfer a specific lien to the security of the bond. (When a contractor procures a lien transfer bond, the bond must be for the principal amount of the lien, plus the greater of $1,000 or 25% of the principal amount to cover potential attorney’s fees and court costs, plus three years worth of interest on the principal amount at the prevailing statutory rate.)

 

 

NOTICE OF BOND

To (Name and Address of Lienor)
You are notified that the claim of lien filed by you on ___, ___, and recorded in Official Records Book ___ at page ___ of the public records of ___ County, Florida, is secured by a bond, a copy being attached.
Signed: (Name of person recording notice)

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.