CONSTRUCTION LIEN FORECLOSURE ACTION MUST BE BROUGHT IN COUNTY WHERE PROPERTY LOCATED

A construction lien foreclosure action is an action against the real property and MUST be brought in the county where the property is located. It is an action concerning subject matter jurisdiction (the jurisdiction of the court to hear the matter) and, thus, can be raised at any time in a proceeding.  If you are looking to foreclose a construction lien, please make sure 1) the lien is recorded in the right jurisdiction and 2) the lien is foreclosed on in the right jurisdiction.

In a recent case, Prime Investors & Developers, LLC v. Meridien Companies, Inc., 2020 WL 355930 (4th DCA 2020), a dispute arose between a general contractor and subcontractor on a hotel project in Miami-Dade County. The general contractor filed suit against the subcontractor for untimely and defective installation in Broward County. The subcontractor counter-sued the general contractor for breach of contract and asserted a claim against the developer of the hotel to foreclose a construction lien. Remember, the property was located in Miami-Dade County but the lawsuit was in Broward County.

The trial court granted summary judgment in favor of the subcontractor and against the developer and contractor. The trial court entered a money judgment against the contractor and the developer, but did not initiate any foreclosure proceedings.

The appellate court reversed the summary judgment because there were genuine issues of material fact. The subcontractor, in its motion for summary judgment, did not address the general contractor’s affirmative defenses. (“When a party raises affirmative defenses, a summary judgment should not be granted where there are issues of fact raised by the affirmative defenses which have not been effectively factually challenged and refuted. The movant must disprove the affirmative defenses or show they are legally insufficient.”). Prime Investors & Developers, LLC, 2020 WL at *4 (citation omitted).

The appellate court did address the construction lien foreclosure issue by reminding “that “[a] lien against property is in rem, affecting title to the property, and must be brought in the circuit with jurisdiction over the property.” Prime Investors & Developers, LLC, 2020 WL at *4 (citation omitted).  In other words, the subcontractor filed the construction lien foreclosure lawsuit in the WRONG jurisdiction. Oops!

However, the appellate court did not seem to challenge the right of the subcontractor to obtain a monetary judgment, absent the foreclosure proceedings, against the developer. While the subcontractor cannot foreclose its construction lien, it may have a basis to obtain a monetary judgment that excludes foreclosure against the developer if it prevails at trial. This is certainly not the same leverage the subcontractor wanted when it recorded the lien and initiated a construction-lien foreclosure.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CIRCUMSTANCES IN WHICH DESIGN PROFESSIONAL HAS CONSTRUCTION LIEN RIGHTS

If you are a design professional (architect, landscape architect, interior designer, engineer, surveyor, or mapper) you have construction lien rights in the event you are not paid.   This does not mean your lien rights are absolute so it is important to understand the circumstances which allow you to record a construction lien on a project.  These circumstances are contained in Florida Statute s. 713.03:

(1) Any person who performs services as architect, landscape architect, interior designer, engineer, or surveyor and mapper, subject to compliance with and the limitations imposed by this part, has a lien on the real property improved for any money that is owing to him or her for his or her services used in connection with improving the real property or for his or her services in supervising any portion of the work of improving the real property, rendered in accordance with his or her contract and with the direct contract.

(2) Any architect, landscape architect, interior designer, engineer, or surveyor and mapper who has a direct contract and who in the practice of his or her profession shall perform services, by himself or herself or others, in connection with a specific parcel of real property and subject to said compliances and limitations, shall have a lien upon such real property for the money owing to him or her for his or her professional services, regardless of whether such real property is actually improved.

The first circumstance pertains to design professionals that do NOT have a direct contract with the owner of the property.  In this circumstance, you have lien rights for your services “used in connection with improving the real property” or your services “in supervising any portion of the work of improving the real property” that you perform under your contract and with the direct contract, presumably between the owner and your client.  The important, operative word in this circumstance involves improving the real property.

The second circumstance pertains to design professionals hired directly by the owner.  In this circumstance, you have broader lien rights as you have lien rights for your services “regardless of whether such real property is actually improved.”  Hence, improving the real property is of no moment.

A design professional does not need to serve any preliminary notice (such as a notice to owner) in order to preserve their lien rights.  However, a design professional still needs to record a construction lien within 90 days from their final furnishing date.

A construction lien from a design professional is less common than a lien from a contractor, subcontractor, or supplier. Nonetheless, design professionals do have construction lien rights that an owner should be cognizant of and a design professional should understand in furtherance of best ensuring payment.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

FILLING OUT THE CONTRACTOR’S FINAL PAYMENT AFFIDAVIT

When preparing a contractor’s final payment affidavit, I always suggest for a contractor (or anyone in privity of contract with the owner) to identify the undisputed amounts their accounting reflects is owed to ALL subcontractors, etc., regardless of whether that entity preserved their lien rights.  If the contractor provided a payment bond, I footnote this simply to support that none of the lower-tiered subcontractors have lien rights or are the traditional “lienor.”   (Thus, there is no prejudice to the owner if an entity is inadvertently omitted from the affidavit.)

There are times, however, where a contractor does not identify a subcontractor that did not serve a notice to owner and, therefore, has no valid lien rights.  Or, a contractor omits a lienor that actually did serve a notice to owner and preserve its lien rights; this happens.

There was an older First District Court of Appeals case that harshly (and, quite, unfairly) held that the contractor must identify everyone in the final payment affidavit regardless of whether that entity timely served a notice to owner or their lien is invalid.  This case, however, predated, a 1998 statutory change to Florida’s Lien Law.

Today, the statute (in Florida Statute s. 713.06) currently provides:

(d) When the final payment under a direct contract becomes due the contractor:

1. The contractor shall give to the owner a final payment affidavit stating, if that be the fact, that all lienors under his or her direct contract who have timely served a notice to owner on the owner and the contractor have been paid in full or, if the fact be otherwise, showing the name of each such lienor who has not been paid in full and the amount due or to become due each for labor, services, or materials furnished….

The contractor shall have no lien or right of action against the owner for labor, services, or materials furnished under the direct contract while in default for not giving the owner the affidavit; however, the negligent inclusion or omission of any information in the affidavit which has not prejudiced the owner does not constitute a default that operates to defeat an otherwise valid lien. The contractor shall execute the affidavit and deliver it to the owner at least 5 days before instituting an action as a prerequisite to the institution of any action to enforce his or her lien under this chapter, even if the final payment has not become due because the contract is terminated for a reason other than completion and regardless of whether the contractor has any lienors working under him or her or not.

Fla. Stat. s. 713.06(d)(1).

The Fourth District Court of Appeals in Fetta v. All-Rite Paving Contractors, Inc., 50 So.3d 1216 (Fla. 4th DCA 2010), claimed that the purpose of the statute is for the contractor to identify all lienors who have timely served a notice to owner that has not been paid in full.  (Hence, you do not need to identify those that did not timely serve a notice to owner even though, from a practical standpoint, identifying all makes sense as a just-in-case.). Further, even if there was an omission, that would not render a lien invalid unless the owner can prove prejudice and prejudice is not so easy to prove.

When in doubt, consult counsel when finalizing or filling out a contractor’s final payment affidavit.  Rights can be preserved and items footnoted as appropriate for clarification purposes, such as the fact that the amount in the affidavit may not include amounts that are not available under the lien law (i.e., delay damages).

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION LIEN DOES NOT INCLUDE LATE FEES SEPARATE FROM INTEREST

Construction liens can include unpaid finance charges.   But, what about late fees?  You know, the late fees that certain vendors like to include in their contract or purchase order unrelated to finance charges.  An added cost for being delinquent with your payment.  Can a late fee be tacked onto the lien too?

In a recent case, Fernandez v. Manning Building Supplies, Inc., 2019 WL 4655988 (Fla. 1st DCA 2019), a residential owner hired a contractor for a renovation job.  The contractor entered into a contract with a material supplier.  The terms of the supplier’s contract with the contractor provided that there would be a 1.5% delinquency charge for late payments and it seemed apparent that the delinquency charge was separate from finance charges.

Florida Statute s. 713.06(1) provides in relevant portion:

A materialman or laborer, either of whom is not in privity with the owner, or a subcontractor or sub-subcontractor who complies with the provisions of this part and is subject to the limitations thereof, has a lien on the real property improved for any money that is owed to him or her for labor, services, or materials furnished in accordance with his or her contract and with the direct contract and for any unpaid finance charges due under the lienor’s contract.

The supplier in this case recorded a construction lien and filed a lien foreclosure lawsuit.  The issue was whether a 1.5% per month “delinquency charge” or late fee, as set forth in the contract, should be factored into the lien amount.   The First District Court of Appeal held no:

[A] ate payment fee is not a “finance charge” as that term is generally understood…[T]he difference between a finance charge and delinquency fee is recognized by Black’s Law Dictionary (10th ed. 2014) which defines a “finance charge” as “[a]n additional payment, usu. in the form of interest, paid by a retail buyer for the privilege of purchasing goods or services in installments.” As such, a finance charge is the cost of credit — not the cost of paying late. The 1.5% fee required by the [the supplier’s] contract is to be paid only upon default; it is not a cost of credit per se.

Fernandez, supra

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: TIMELY RECORDING CONSTRUCTION LIEN

A construction lien needs to be recorded within 90 days from a lienor’s final furnishing date.  This date is exclusive of punchlist or warranty-type work (i.e., repairs to lienor’s own work).   A lienor’s final furnishing date will be included in the construction lien as the lienor’s last date on the job.

 

A lienor’s final furnishing date is a question of fact to be decided by the trier of fact.  In other words, if an owner (or party challenging the enforcement of the lien) argues that the lien was untimely recorded, the party will be arguing that the lienor failed to timely record its lien within 90 days of its final furnishing date.  The application of this fact-driven issue, as further discussed in this article, is: whether the work was: 1) performed in good faith; 2) performed within a reasonable time; 3) performed in pursuance of the lienor’s contract; and 4) necessary for a completed project.  Just remember, a final furnishing date will not include punchlist or warranty work a lienor is performing on the project.   If a lien is recorded outside of this 90-day window, the lien will be deemed unenforceable.  It is always a good practice to ensure a lien is recorded, at a minimum, weeks before the 90-day period expires to avoid any issue or argument with the lien being untimely recorded.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: A CONSTRUCTION LIEN IS NOT INTENDED TO LAST INDEFINITELY

A construction lien is not intended to last forever.  A construction lien must be foreclosed within one year from its recording date because a construction lien only lasts for one year by operation of law.   You will not be able to foreclose a construction lien after this one-year period expires.  This is why it is always good practice to calendar the expiration of this one-year period when a construction lien is recorded.   There is never a good reason to engage in a last minute scramble to file a foreclosure lawsuit on the expiration date (or shortly before).      While I always believe a lienor should work with counsel to record a construction lien, regardless, I would certainly recommend a lienor to work with counsel to ensure lien rights are properly perfected so that when it becomes necessary to foreclose the lien, the strategy is in place to file the foreclosure lawsuit.

 

Importantly, an owner can shorten the one-year period for a lienor to foreclose its construction lien by properly recording a Notice of Contest of Lien.  A Notice of Contest of Lien will shorten the period for a lienor to foreclose its construction lien to sixty days.   It is always beneficial to record the Notice of Contest of Lien sooner than later because it puts the onus on the lienor to either foreclose the construction lien or lose its lien and ability to foreclose its lien by operation of law.  That’s right – if the lienor does not foreclose its lien within the sixty-day window, it will have lost its lien rights.   There are times where an owner of real property records a Notice of Contest of Lien without the use of counsel.  I do not suggest this for a couple of reasons.  First, you want to ensure this is done right and, second, there may be other strategic decisions that may be better implemented based on the circumstances of the dispute.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: NOT IN CONTRACT WITH THE OWNER? SERVE A NOTICE TO OWNER.

A subcontractor or supplier not in direct contract with an owner must serve a Notice to Owner within 45 days of initial furnishing to preserve construction lien rights.  Of course, the notice of commencement should be reviewed to determine whether the subcontractor or supplier has construction lien or payment bond rights so that it knows how to best proceed in the event of nonpayment.   Serving a Notice to Owner should be done as a matter of course — a standard business operation; no exceptions.  

 

However, if a supplier specially manufactures or fabricates material for purposes of a construction project, it must serve the Notice to Owner within 45 days from the actual start of fabrication, and not from when the materials are delivered to the site.  A reason for this is that a supplier of specially fabricated material can lien for the unpaid material even if the material is NOT incorporated into the construction project.  This is different than a supplier liening for other material which does require the material to be incorporated into the project.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: DON’T FORGET TO SERVE THE CONTRACTOR FINAL PAYMENT AFFIDAVIT

If you are a contractor in DIRECT CONTRACT with an owner, serve a contractor final payment affidavit on the owner, as a matter of course, and without any undue delay, particularly if you are owed money and have recorded a construction lien.  In numerous circumstances, I like to serve the contractor final payment affidavit with the construction lien.

 

The contractor final payment affidavit is not a meaningless form.  It is a statutory form (set forth in Florida Statute s. 713.06) required to be filled out by a lienor in direct privity of contract with an owner and served on the owner at least 5 days prior to the lienor foreclosing its construction lien.  The contractor final payment affidavit serves as a condition precedent to foreclosing a construction lien.  Failure to timely serve a contractor final payment affidavit should result in a dismissal of the lien foreclosure lawsuit, presumably by the owner moving for a motion for summary judgment.  This should not occur.  

 

I always suggest working with a lawyer to finalize a contractor final payment affidavit (as well as the lien in order to utilize the advice of counsel defense) for two reasons.  First, you will ideally want the amount in the affidavit to be the same as the lien amount.  Second, you may want to include certain clarifications or exceptions in the final payment affidavit for amounts not included in the lien (e.g., delay-type damages or certain disputed change orders that you do not feel comfortable including in the lien).  

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: REMEMBER TO TIMELY FORECLOSE LIEN AGAINST LIEN TRANSFER BOND

When a construction lien is transferred to a lien transfer bond pursuant to Florida Statute s. 713.24, instead of foreclosing the lien against the real property, you are foreclosing the lien against the lien transfer bond.  This is not a bad deal and, oftentimes, is probably ideal.   Remember, however, just because a construction lien was transferred to a lien transfer bond (pre-lawsuit) does not mean you get more time to file your lien foreclosure lawsuit.  A lawsuit must still be filed within one year (short of that period being specifically shortened under operation of the law).  The only exception is that if the lawsuit is filed and the lien transfer bond is then recorded (post-lawsuit), the lienor has one year to amend its lawsuit to sue the lien transfer bond.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

PAROL EVIDENCE CAN BE USED TO DEFEAT FRAUDULENT LIEN

shutterstock_162610553Parol or extrinsic evidence can be used to defeat an argument that a lien is a fraudulent lien.  And, just because a lien amount exceeds the total contract amount does not presumptively mean the lien is willfully exaggerated or recorded in bad faith.  Finally, a ruling invalidating a construction lien can create the irreparable harm required to support a petition for writ of certiorari.  All of these issues are important when dealing with and defending against a fraudulent lien and are explained in a recent case involving a dispute between an electrical subcontractor and its supplier.

 

In Farrey’s Wholesale Hardware Co., Inc. v. Coltin Electrical Services, LLC, 44 Fla.L.Weekly D130a (Fla. 2d DCA 2019), there were various revisions to the supplier’s  initial purchase order, both from a qualitative and quantitative perspective, and a ninth-revised purchaser order was issued and accepted.  The electrical subcontractor claimed that deliveries were late, unassembled, and did not include the required marking (likely the UL marking), to pass building inspections.  As a result, the subcontractor withheld money from the supplier and the supplier recorded a lien in the amount of $853,773.16 and filed a foreclosure lawsuit.

 

The subcontractor moved for a motion for partial summary judgment that the lien should be deemed a fraudulent lien and invalid because it was overstated by approximately $32,000.  The subcontractor argued that taking the amount of the ninth-revised purchase order and deducting the undisputed amount paid to the supplier would result in a lien amount of $825,417.06, approximately $32,000 less than the supplier’s lien amount.  The supplier, through an affidavit, argued this delta is nothing more than a good faith dispute and can be explained because the total cost of materials furnished to the job site was based on its initial purchase order and its revised purchase order.  The subcontractor countered that the affidavit is  parol evidence and should be disregarded because the parties agreed on the total amount of the supplies through the ninth-revised purchase order and the supplier was trying to create a new contract through the affidavit.  The trial court agreed and found the lien fraudulent, and issued a partial summary judgment invalidating the supplier’s lien.  The subcontractor moved for a petition of writ of certiorari.

 

Parol Evidence Rule

 

“[T]he parol evidence rule prevents the terms of a valid written contract or instrument from being varied ‘by a verbal agreement or other extrinsic evidence where such agreement was made before or at the time of the instrument in question.’” Farrey’s Wholesale, supra(citation omitted). The parol evidence rule, however, is not applied to exclude evidence of subsequent agreements modifying the original agreement, or of fraud, accident, or mistake.  Id.  

 

The appellate court, reversing the trial court, found that the parol evidence rule “does not bar extrinsic evidence offered for the purpose of showing whether the filing of a construction lien was made in good or bath faith.  This is a separate and distinct inquiry that does not trigger the parol evidence rule.”   Hence, the appellate court maintained there were disputed issues of material fact as to whether the lien was fraudulent.

 

The appellate court further found that the trial court erred in finding the lien fraudulent in that just because the lien amount exceeded the ninth-revised purchase order does not mean it was willfully exaggerated.  In other words, even if the ninth-revised purchase order was the complete agreement, the lien, in of itself, is not willfully exaggerated just because the lien exceeded the total amount of the contract. 

 

Appeal of Lien

 

On another important point in this case, because the appeal was based on a writ of certiorari (versus a final appeal of a final dispositive judgment), there had to be irreparable harm to justify the basis of the appeal.  The appellate court held there would be irreparable harm if the supplier had to wait until the end of the litigation to appeal because its judgment would then be unsecured (it would be without a remedy to pursue its lien which had been transferred to a lien transfer bond).  See Farrey’s Construction Wholesale, supra  (“This means that on remand [back to the trial court], all matters pertaining to Farrey’s construction lien, which includes the status of the lien transfer bond, will be returned to their prejudgment postures.”). 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.