DIFFERING SITE CONDITIONS CLAIM REQUIRES A MISREPRESENTATION

If you are entertaining a differing site conditions claim, consider this Third District Court of Appeals case from the mid-90s.

In Hendry Corp. v. Metropolitan Dade County, 648 So.2d 140 (Fla. 3d DCA 1995), a contractor was hired by Dade County to demolish the old Rickenbacker Causeway in Miami. The original 1941 plans of the causeway were made available to contractors. The lowest bidding contractor that was awarded the project based its bid “on its conclusion that the pilings supporting the old bridge were made of concrete.” Hendry, supra at 141.  The contractor based this conclusion on the original plans, its visual observation, and experience.

The contractor did not deliver the project on time as it had problems with its demolition. Dade County withheld contract balance for the delayed completion, and the contractor sued Dade County due to differing site conditions:

Specifically, [the contractor] alleged that after it started work on the project, it encountered two differing site conditions that required an equitable adjustment of the contract price.  The first differing site condition alleged was the existence of wooden, rather than concrete pilings. [The contractor] contended that Dade County had an obligation to provide the bidders with the 1941 specifications for the bascule which would have shown the pilings were wooden. Demolition of structures supported by wood pilings is more difficult than demolition of structures supported by concrete pilings. The second differing site condition that [the contractor] alleged made demolition more difficult and therefore more expensive was subsurface debris that remained from the original construction project. [The contractor] claimed that Dade County was aware of the debris but failed to notify the bidders.

Hendry, supra, at 141.

The contractor wanted the trial court, as well as the appellate court, “to impose upon Dade County a duty heretofore not recognized in Florida—that Dade County had an obligation to disclose facts in its possession when its superior knowledge or silence would convey a false impression, even when it made no affirmative representation.”  Hendry, supra at 141.

Here’s the issue: did the owner / public body have a duty to make such an affirmative representation? NOPE.

The law in Florida also provides that where a contractor is misled by relying on inaccurate representations, a disclaimer clause requiring inspection of the site will not prevent the contractor from recovering additional costs under a differing site conditions clause.  However, a differing site conditions clause will be “triggered only where an inaccurate representation is relied on, not where there has been no representation.” Moreover, in the absence of such misrepresentation, there will be no recovery under the differing site conditions clause if the contractor relies on its own inadequate investigation. 

Hendry, supra, at 142 (internal citations omitted).

Here, Dade County made no affirmative representation and did not represent any inaccurate fact.

As to the contractor’s first differing site condition claim: “Although Dade County did not provide the 1941 specifications for the bascule, which indicated that the bridge was supported by wooded rather than concrete pilings, there is no evidence in the record that Dade County withheld the 1941 specifications from [the contractor].” Hendry, supra, at 142.

As to the contractor’s second differing site condition claim: “Dade County made no representations in the bid documents regarding the condition of the bay bottom. … Moreover, there was substantial competent evidence presented at trial that [the contractor] knew, or should have known, that it would encounter subsurface debris.”  Hendry, supra, at 143.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CONCEALMENT OR FRAUD PROVISION IN INSURANCE POLICY

It is common for insurance policies to have a concealment or fraud provision that ultimately says the policy is void if the insured engaged in fraudulent conduct, intentionally concealed or misrepresented material facts, or made false material statements.  In a nutshell, lying is bad, which includes intentionally withholding material facts.

An insured may make misrepresentations during the insurance application process.  Or, an insured may make misrepresentations after a loss occurs, referred to as the post-loss context. The misrepresentations require different burdens of proof.

With respect to misrepresentations (fraud) during the insurance application process, “an insurer can later void a policy based on an insured’s false statement without a showing of intent to mislead.”  Gracia v. Security First Ins. Co., 47 Fla.L.Weekly D1866a (Fla. 5th DCA 2022).

With respect to misrepresentations (fraud) during the post-loss context, there needs to be “proof of intent to mislead” by the insured.  Gracia, supra.

By way of example, in Gracia, summary judgment was entered in favor of the property insurer on a property insurance roof damage claim initiated by the insured based on misrepresentations the insured made regarding the pre-loss condition of her property. Prior to the issuance of the policy, there was an inspection report that indicated the property had prior roof and ceiling damage. During the insured’s deposition, the insured testified that the roof was in good condition during this time. The carrier, upon learning of this inspection report, raised the concealment or fraud provision in the policy claiming coverage should be voided and moved for summary judgment on this basis. Specifically, the insurer argued that the insured made false statements in her deposition concerning the pre-loss condition of her home supporting her coverage being voided. Yet, the insured’s position was that the loss subject of her claim occurred during the policy period, not before. Nonetheless, the trial court agreed with the insurer and granted summary judgment.  The appellate court reversed because the fraud in this post-loss context required the insurer to prove the insured’s INTENT. (The insurer needed to prove the element of intent.)  “Simply put, factual questions relating to fraudulent intent or state of mind are generally not ripe for summary judgment determination.” Gracia, supra.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

ASSERTING NON-DISCLOSURE CLAIM INVOLVING RESIDENTIAL REAL PROPERTY AND WHETHER FACTS ARE “READILY OBSERVABLE”

Under Florida law, there is a claim dealing with the purchase and sale of residential real property known as a Johnson v. Davis or a non-disclosure claim:  “[W]here the seller of a home knows of facts materially affecting the value of the property which are not readily observable and are not known to the buyer, the seller is under a duty to disclose them to the buyer.” Lorber v. Passick, 46 Fla.L.Weekly D1952a (Fla. 4th DCA 2021).   A seller’s duty to disclose extends to a seller’s real estate agent/broker.  Id.

A non-disclosure claim is asserted by the buyer of residential real property when the buyer discovers defects or damages with the real property that he believes materially affects the value of the property.  While there may be the sentiment these are easy claims to prove, they are not.

Remember, a non-disclosure claim deals with facts that materially affect the value of residential real property and are NOT readily observable.  The use of the language “readily observable” has been found to mean:

“[I]nformation [that] is within the diligent attention of any buyer.  To exercise diligent attention…a buyer would be required to investigate any information furnished by the seller that a reasonable person in the buyer’s position would investigate and take reasonable steps to ascertain the material facts relating to the property and to discovery them—if, of course, they are reasonably ascertainable.”

Lorber, supra, quoting Nelson v. Wiggs, 699 So.2d 258, 260-61 (Fla. 3d DCA 1997) (internal quotations and citations omitted).

When a buyer asserts a non-disclosure claim, the buyer should also consider adding a negligent misrepresentation claim.  “[E]ven when a defect can probably be discovered through the exercise of diligent attention, the requisite level of diligent attention is of less importance in claims involving misrepresentations – especially those involving fraud.”  Lorber, supra.  The issue appears to be one that involves comparative negligence and despite readily observable defects, a buyer is entitled to rely on a seller’s representations.  Id.

Lorber provides a good discussion of a residential real property non-disclosure claim and related claims for a seller’s misrepresentation.

In this case, a buyer did not move through with closing because he smelled an odor in the house and learned, right before closing, the home had experienced substantial water damage/ a prior flood event.  The buyer claimed this was never disclosed by the seller, was not readily observable, and materially affected the value of the property.

The seller sued the buyer for failing to close and the buyer countersued for breach of contract, fraudulent inducement, and negligent misrepresentation.

During the course of litigation, the seller moved for summary judgment.  Testimony established that the buyer knew there was a musty odor when he first stepped foot in the house and asked about the odor.  The buyer was told by the seller’s agent it was due to the air conditioning being off but acknowledged the odor might be mold.  Moreover, the buyer’s real estate agent testified the odor was similar to other properties he had seen that had water intrusion; although, the agent testified he did not inform the buyer that water intrusion was possible.  Based on this testimony, the seller argued the water intrusion and mold was readily observable thereby defeating a non-disclosure claim.   The buyer argued that while he was not denying he smelled the odor from the get-go, the seller’s real estate agent dismissed the odor and there was nothing readily observable that connected the odor to a prior flood, as supported by the seller’s disclosure form which indicated the property suffered no water intrusion or flood damage.  In other words, the buyer claimed how could he investigate a flooding condition he did not know existed and was not disclosed to him, and how could he have knowledge the odor’s existence was related to a past flood event.

The trial court granted summary judgment in favor of the seller.  The trial court held the fact that the buyer smelled the musty odor that could be mold made the fact there was a prior water intrusion event readily observable.   The Fourth District Court of Appeal disagreed.

Buyer’s Breach of Contract Claim

The buyer’s breach of contract claim against the seller was a non-disclosure claim.  Thus, the buyer’s failure to exercise diligent attention would be fatal to a non-disclosure claim because the facts would be readily observable.  In this regard, the Fourth District Court of Appeal noted that if the buyer’s claim was premised on mold, his non-disclosure claim would fail because he observed the musty odor.

However, the buyer’s claim was not predicated on the existence of mold, but on the existence of a past flood event/damage; the buyer testified “he was unaware of any steps he could have taken to investigate a prior flood about which he was never informed, and he had no knowledge that the mold’s existence was in any way related to a prior water intrusion event.”   For this reason, the Fourth District found that there was a genuine issue of material fact as to whether the prior flood event was readily observable.  There was also an issue of material fact as to whether the flood event/damage materially impacted the value of the property as the buyer testified the home was worth much less after having suffered a flood.

Buyer’s Fraudulent Inducement Claim

As to the buyer’s fraudulent inducement claim, the Fourth District Court of Appeal held there was a genuine issue of material fact as to whether the seller knew its representations concerning the property were false with the intent to induce the buyer to enter into the purchase-sale agreement.

While a party cannot recover for fraud that is contradicted or covered by the actual contract, the sale of residential real property creates an exception.  “The inclusion of an ‘as is’ clause in a contract for the sale of residential real property does not waive the duty imposed upon a seller under Johnson [v. Davis].”  Lorber, supra (citation omitted).

Buyer’s Negligent Misrepresentation Claim

As to the buyer’s negligent misrepresentation claim, the Fourth District Court of Appeal held that the “issue was one of comparative negligence.”  Lorber, supra.  Genuine issues of material fact remained “as to whether Seller knew or should have known about the Disclosure Form’s falsity, whether Seller intended to induce Buyer to rely on the Disclosure Form, and whether Buyer acted in justifiable reliance upon the Disclosure Form, in conjunction with seller’s agent’s statement that the smell was attributable solely to the air conditioning being off.”  Id.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CAVEAT EMPTOR (“BUYER BEWARE!”) EXCEPTIONS

There is value to a seller when it comes to entering into an as-is transaction and stating that the seller has NOT made any representation or warranty, all such representations or warranties are disclaimed, the buyer is NOT relying on any representation of the seller, and that the buyer is relying on its own inspection of the property.   This shifts the onus to the buyer to undertake the inspection or due diligence it needs to take relating to the property it wants to buy.

With respect to commercial property transactions:

The doctrine of caveat emptor, which Florida courts continue to apply, “places the duty to examine and judge the value and condition of the property solely on the buyer and protects the seller from liability for any defects.”  There are, however, three exceptions to this doctrine, including: “1) where some artifice or trick has been employed to prevent the purchaser from making independent inquiry; 2) where the other party does not have equal opportunity to become apprised of the fact; and, 3) where a party undertakes to disclose facts and fails to disclose the whole truth.” 

Florida Holding 4800, LLC v. Lauderhill Mall Investment, LLC, 46 Fla. L. Weekly D785b (Fla. 4th DCA 2021).

These three exceptions to caveat emptor, or the doctrine of buyer beware, are not easy to prove because it places a burden on a buyer to prove an active effort from the seller to conceal a material fact to skirt around the as-is language.  Again, this is not an easy burden to prove.

By way of example, in Florida Holding 4800, the buyer purchased commercial property and sued the seller after discovering roof leaks, HVAC issues, and mold.  The lawsuit was predicated on the seller’s misrepresentation or concealment of the condition of the property.  The problem was that the buyer purchased the property as-is and contractually agreed there were no representations or warranties from the buyer.  The trial court granted summary judgment in favor of the seller because of caveat emptor’s application to commercial transactions.

The appellate court affirmed the trial court because there was no evidence that the “Seller’s actions prevented it from conducting a thorough inspection of the property or that, but for Seller’s conduct, Buyer would have discovered that the roof was defective.”  Florida Holding 4800, supra.   The appellate court explained:

Unable to establish an exception to caveat emptor, Buyer is left with the PSA’s [purchase sale agreement] express language providing that Buyer was purchasing the property “based solely on Buyer’s own inspection, investigation and evaluation,” and that Seller made no representations regarding the property’s condition, or if it did, Buyer agreed it was not relying upon such representations. By these very terms, Buyer waived any claim of fraud on the undisputed material facts in this case.

Florida Holding 4800, supra.

As you can see, the doctrine of caveat emptor has teeth.  Likewise, specific language in as-is transactions has teeth and it is important to include this disclaiming language in as-is transactions, even if the transaction does not concern real property.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CLAIMS BASED ON MISREPRESENTATION MUST BE INDEPENDENT OF CLAIMS BASED ON A CONTRACTUAL BREACH

While misrepresentation-type tort claims (fraudulent inducement, fraudulent misrepresentation, or negligent misrepresentation) sometimes sound like attractive claims, they are oftentimes not appropriate claims, particularly when there is a contract between the parties.  The reason being is the the same damages for the breach of contract and misrepresentation-type tort claims are pursued and the claims rely on the same conduct as the breach of contract claim.  This is wrong.  As explained further in this article, the misrepresentation forming the fraudulent inducement, fraudulent misrepresentation, or negligent misrepresentation claim (1) must be pled with specificity in the operative pleading (complaint or counter-claim), (2) are not a substitute or way to navigate around the burden of proof of a breach of contract claim, and (3) must be based on conduct independent of the breaches of contract, i.e., a breach of the actual contract is not a misrepresentation.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DEMONSTRATING A FRAUDULENT INDUCEMENT CLAIM OR DEFENSE

In a recent case, Florida’s Fourth District Court of Appeal reversed a trial court’s denial of a motion for a temporary injunction sought by an employer due to an independent contractor’s violation of a non-compete and non-solicitation provision in an employment / independent contractor agreement (“employment agreement”). You can find more on this case and the enforcement of the non-compete and non-solicitation clause here.

A worthy discussion in this case centers on the independent contractor’s fraudulent inducement defense. Specifically, the independent contractor, as a defense to the injunction, claimed that he was fraudulently induced into entering into the employment agreement because the employer promised he would make a certain amount of money and he would work predominantly in one geographic location. The employment agreement contained NO such representations. Instead, the employment agreement contained a fee and services schedule and the independent contractor would be compensated based on that schedule. It stated nothing as to the independent contractor only having to work, or predominantly working, in one geographic location, or that the independent contractor would be guaranteed “X” amount of money working in that location. Why is this important?

In order to support a claim or defense of fraudulent inducement, a party must prove the following elements: “1) a false statement concerning a material fact, 2) knowledge by the person making the statement that the representation is false, 3) intent by the person making the statement that the representation will induce another to act upon it, and 4) [justifiable] reliance on the representation to the injury of the other party.” GEICO General Ins. Co. v. Hoy, 136 So.3d 647, 651 (Fla. 2d DCA 2013 (citation omitted); see also Hillcrest Pacific Corp. v. Yamamura, 727 So.2d 1053, 1055 (Fla. 4th DCA 1999). “[T]o satisfy the element of an injury, the claimant must establish that he or she has sustained pecuniary damage or injury by which he or she has been placed in a worse position than he or she would have been absent the fraud.” Hoy, 136 So.3d at 651.

However, and this is a BIG however, “[A] party cannot recover in fraud for oral misrepresentations that are [covered or] later contradicted in a written contract.” Picture It Sold Photography, LLC v. Bunkelman, 45 Fla. L. Weekly D74a (Fla. 4th DCA 2020).

The employment agreement stated it was the entire agreement between the parties. (There is a reason why agreements contain language that states that the agreement is the final and complete agreement between the parties and supersedes prior agreements and representations between the parties. Such provision is not for naught!)

Hence, the independent contractor’s claim that he was induced into entering the agreement based on making a certain amount of money was covered by the agreement that contained a schedule for services and the corresponding fees.  As mentioned, the agreement did not promise a certain amount of money and/or the money would be based on the independent contractor working in a certain location.   In other words, you cannot claim fraud in the inducement if your contract contradicts what you are claiming or the agreement covers that issue.

Further, even if there was an argument that there were misrepresentations as to money and location, the independent contractor would still need to demonstrate that he justifiably relied on the misrepresentations. “Without justifiable reliance, there can be no actionable fraud.” Bunkelman, supra (citation omitted).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.