PAY-WHEN-PAID AND THE PREVENTION OF PERFORMANCE DOCTRINE


The pay-when-paid doctrine is a standard provision in subcontracts to shift the risk of the owner’s nonpayment to the subcontractor. The owner’s payment to the contractor is a condition precedent to the contractor’s payment to the subcontractor. However, if there is a payment bond in place, a surety in Florida cannot rely on this contractual defense to defeat a subcontractor’s claim. (Notably, in other jurisdictions, a surety can rely on this defense.) The pay-when-paid doctrine has been discussed numerous times in the following articles: https://floridaconstru.wpengine.com/pay-when-paid-provisions-and-payment-bonds/ and https://floridaconstru.wpengine.com/subcontractors-and-unjust-enrichment-claims/ and https://floridaconstru.wpengine.com/careful-drafting-of-pay-when-paid-provisions/.

Sometimes, there is not a payment bond in place and the subcontractor is forced to assert a direct claim against the contractor. Or, perhaps, the subcontractor may not have properly preserved its lien / bond rights and its best recourse is to assert a claim against the contractor. In this situation, the contractor will be able to rely on the pay-when-paid provision in its subcontract assuming it can prove that it was not paid for the subcontractor’s work that is the subject of the dispute. This defense, however, may not be absolute. There is a legal doctrine known as the “prevention of performance” doctrine.

Florida law provides:

“Under the doctrine of prevention of performance, one who prevents the happening of a condition precedent upon which his liability is made to depend, cannot avail himself of his own wrong and thereby be relieved of his responsibility to perform under the contract.” Florida Ins. Guar. Ass’n v. Somerset Homeowners Ass’n, Inc., 83 So.3d 850, 852, n.1 (Fla. 4th DCA 2011) (internal quotation omitted).

 

 

This doctrine really has not been analyzed in the context of a pay-when-paid defense under Florida case law. Yet, now and again, a case outside of Florida addresses interesting points that are worthy of discussion.

 

In Moore Brothers Co. v. Brown & Root, Inc., 207 F.3d 717 (4th Cir. 2000), the Fourth Circuit (interpreting Virginia law) analyzed the prevention of performance doctrine in the context of a contractor raising the pay-when-paid defense. In this case, the contractor entered into a contract to build a private toll road in Virginia. (The contractor was also an equity partner in the ownership group.) During the drafting of the prime contract, several design issues were referenced that would result in additional payment to the contractor. One of those issues was changing the thickness of the pavement subbase material. There was strong uncertainly over the initial pavement design and it was anticipated that the thickness of the pavement subbase material would change. The construction lenders wanted to contain construction costs and insisted on certainty in determining the costs. The lenders did not want to authorize a prime contract that did not provide this certainty and the draft prime contract with examples of additional costs the lenders may have to fund did not sit well with them. To appease the lenders, the owner and the contractor agreed to remove examples of design changes or issues that would result in increased construction costs. The owner and contractor further assured the lenders that they did not anticipate substantial changes in the work (such as a change in the pavement subbase thickness). Of course, what the contractor and owner assured the lenders was not really what they believed because they anticipated a design change regarding the thickness of the pavement subbase material. Thus, the owner and contractor entered into a side agreement that was not shared with the lenders concerning the design changes / issues that would result in increased costs to the contractor.

The contractor then hired subcontractors to perform scopes of work relative to the road construction. The subcontracts contained pay-when-paid provisions. The contractor did not advise the subcontractors that design changes such as a potential change in the thickness of the pavement subbase material were hidden from the lenders and that such a change would likely not be funded by the lenders. The contractor did not seem as concerned with this because it had pay-when-paid language shifting the risk of nonpayment to the subcontractors (although the contractor did have a payment bond in place). Naturally, there was a design change that changed the thickness of the pavement subbase material and this work was performed by the subcontractors. A payment dispute originated in arbitration involving the owner, contractor, and subcontractors regarding this additional work. The arbitrator ruled that the owner must pay the contractor for this additional work and the contractor, after receiving payment, must pay the subcontractors. The owner did not pay so the contractor never paid the subcontractors contending that the pay-when-paid language does not contractually require it to pay.

 

Since the arbitration award was never paid, the subcontractors filed suit in federal district court which was appealed to the Fourth Circuit. Among other issues discussed in the case, the Fourth Circuit analyzed whether the contractor was required to pay the subcontractors for the additional work associated with the pavement subbase thickness in light of the pay-when-paid provision. The Fourth Circuit found that the trial court correctly applied the prevention of performance doctrine to hold the contractor responsible for the payment of the additional work.  The Fourth Circuit agreed that the contractor could not rely on the pay-when-paid language in the subcontract because it was responsible for the non-payment or non-occurrence of the condition precedent (i.e., owner’s payment). Specifically, the contractor knew that the additional work would most likely need to be performed which is why this design change was called out in the draft prime agreement. However, because of lender issues, it removed this language from the final prime contract and assured the lenders that additional work was not anticipated. It then contemporaneously entered into a side agreement with the owner that was not shared with the lenders regarding the same anticipated additional work (that it assured the lenders it was not anticipating). The Fourth Circuit held:

“The prevention [of performance] doctrine does not require proof that the condition would have occurred ‘but for’ the wrongful conduct of the promisor; instead it only requires that the conduct have ‘contributed materially’ to the non-occurrence of the condition.” Moore Brothers, 207 F.3d at 725.

 

It is easy to see how the facts in this case as presented by the Fourth Circuit warrant the application of the “prevent of performance” doctrine. It is uncertain from this case what the lenders would have done if construction costs were increased to specifically cover the highly anticipated design change to the pavement subbase thickness or why this change was not funded through any contingency funds / line item in the loan (perhaps there was none because the lenders insisted on certainty with the costs). It is also uncertain what the lenders would have done (or what they did) regarding the submission of these additional work costs since the parties could not dispute that the work was additional contractual work. And, it is uncertain why the contractor did not obtain bids for the additional work from the subcontractors before hiring them and try to negotiate perhaps a more palatable cost knowing this additional work was likely going to occur. Even though the contractor appeared to try to appease the lenders so this project could move forward, it knew funding for the additional work would be a huge concern and it was not up front with its subcontractors regarding this potential lack of funding. Had it been up front with the subcontractors, perhaps this risk could have been specifically accounted for in the subcontract through specific language or better pricing that could have been presented to the lenders.

Notwithstanding, in the event a contractor raises a pay-when-paid defense, a subcontractor may be able to rebut this defense by arguing the “prevention of performance” doctrine, that being that the contractor caused the very non-occurrence of the payment and, therefore, should not be entitled to rely on this defense. Although this argument seems like a tough hurdle for the subcontractor since not all facts will be as egregious as the facts in this case, the contractor should still take steps to eliminate this argument by showing that it took steps to obtain payment from the owner. Subcontractors, on the other hand, that may not have bond / lien rights or want to pursue substantial claims for additional work against the contractor, may want to rely on this argument in furtherance of trying to get around the expected pay-when-paid defense.

  

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

MILLER ACT – CONSIDERATIONS INVOLVING SUBCONTRACTOR WHEN GOVERNMENT ASSESSES LIQUIDATED DAMAGES


Prime contractors and subcontractors that work on federal construction projects often find themselves in the garden variety payment dispute dealing with (1) entitlement and liability for additional work and  (2) project delays, especially when the government assesses liquidated damages. These issues can put the prime contractor in the undesirable position because it may not have been paid for the additional work items and the government may be assessing liquidated damages against the prime contractor for the delays.

 

The case of U.S. ex rel. W.W. Gay Mechanical Contractor, Inc. v. Walbridge Aldinger Co., 2013 WL 5859456 (11th Cir. 2013), illustrates this garden variety construction payment dispute scenario between a subcontractor and prime contractor on a delayed federal project. This case involves a subcontractor asserting a Miller Act payment bond claim (pursuant to 40 U.S.C. s. 3133) against the prime contractor’s surety for unpaid retainage and additional work items, as well as a breach of contract claim against the prime contractor for the same amounts. The prime contractor argued that it was entitled to withhold payment from the subcontractor due to delays to the completion date of the project that the subcontractor was responsible for causing. In particular, the prime contractor was being assessed sizable liquidated damages from the government (Navy) and although it was appealing the liquidated damages exposure through the Contract Disputes Act, it wanted to offset monies that were owed to the subcontractor based on its potential liquidated damages exposure. The prime contractor relied on subcontract provisions that contained that “time is of the essence” as to the subcontractor’s performance; that it was entitled to withhold sums from the subcontractor for its breach of contract; and that the subcontractor may be liable for liquidated damages and other damages for causing delays in the progress of the project.

 

At the trial court level, the district court granted partial summary judgment in favor of the subcontractor finding that the subcontractor was entitled to payment for the retainage and additional work. Attorneys‘ fees were also granted to the subcontractor.

 

On appeal, the Eleventh Circuit first discussed the purpose of the Miller Act and what a party needs to do to assert a Miller Act claim:

 

“The MIller Act protects subcontractors on federal projects by requiring contractors to post a bond to ensure payment to their subcontractors. To establish a Miller claim, W.W. Gay [subcontractor] must show (1) that it supplied labor and materials for work in the particular contract at issue; (2) that it is unpaid; (3) that it had a good faith belief that the materials were for the specified work; and (4) that jurisdictional requisites are met.” Walbridge Aldinger, 2013 WL at *1 (internal citations omitted).

 

Irrespective of favorable contractual provisions, the Eleventh Circuit held that the prime contractor “has failed to produce more than a ‘scintilla of evidence’ that W.W. Gay’s alleged delays resulted in the liquidated damages assessed against it by the Navy.” Walbridge Aldinger, 2013 WL at *2.  Although the prime contractor tried to rely on deposition testimony that correspondence was sent to the subcontractor regarding the delays, this was not proof that the subcontractor actually caused delays to the project. This is especially true because the prime contractor was also arguing that the Navy caused delays to the project, i.e., the likely reason it was appealing the liquidated damages assessment.

 

The Eleventh Circuit further analyzed the issue of whether the subcontractor was entitled to monies for additional work pertaining to re-routing an underground storm pipe. The Court found that the record reflected that when the subcontractor learned of the issue regarding the planned location of the storm pipe it notified the prime contractor and the prime contractor directed the subcontractor to install the pipe in the planned location. The prime contractor then waited six weeks before sending a request for information to the government and the government responded telling the prime contractor to re-route the pipe. The prime contractor then directed the subcontractor to re-route the pipe (through the constructive change directive provision or CCD provision in the subcontract). The subcontractor then notified the prime contractor that it expects to get paid for this work and the prime contractor indicated it would pay. The government, however, only paid for a fraction of the additional work item. For this reason, the prime contractor argued that even though it directed the extra work it was only responsible for paying the subcontractor the amount allowed by “applicable provisions” of the prime contract (agreement with the government). In support of this, the prime contractor relied on the following language in its subcontract:

 

“Contractor may, without invalidating the Subcontract or any bond given hereunder, order extra and/or additional work, deletions, or other modifications to the Work, such changes to be effective only upon written order of Contractor. Any adjustment to the Subcontract Price or the time for completion of the Work shall be made in accordance with the applicable provisions of the Agreement between Owner and Contractor and the lump sum or unit prices set forth in Exhibit E or, in the absence of such provisions on an agreed, equitable basis. Notwithstanding any inability to agree upon any adjustment or the basis for an adjustment, Subcontractor shall, if directed by Contractor, nevertheless proceed in accordance with the order, and the Subcontract shall be adjusted as reasonably determined by the Contractor with any dispute to be resolved after the completion of the Work. If requested by the Contractor, the Subcontractor shall perform extra work on a time and material basis, and the Subcontract price shall be adjusted based on time records and materials checked by the Contractor on a daily basis.”

 

Yet, the prime contractor never advised what “applicable provisions” of the prime contract supported its argument. Thus, the Eleventh Circuit maintained that the subcontractor should be entitled to be paid for its work on a time and materials basis based on time sheets per the very provision the prime contractor relied upon. Notably, the Eleventh Circuit minimized the significance of the contractual language by stating:

 

“Even assuming that the interpretation of the contract raises issues of material fact, Walbridge is still liable, as the district court found, under the duty of good faith and fair dealing implied in all contracts. Walbridge ordered W.W. Gay to install the storm pipe despite the problem that W.W. Gay had promptly called to Walbridge’s attention; Walbridge then waited six weeks to ask the Navy for advice; and after W.W. Gay had already finished installing the pipe, Walbridge ordered W.W. Gay to reroute the pipe. W.W. Gay understandably insisted that it receive full compensation for its work, and Walbridge accepted, or at least manipulatively encouraged, this expectation. Moreover, the only reason that the Navy did not pay for W.W. Gay’s work is because of Walbridge’s initial error in judgment. Thus, Walbridge cannot now invoke the Navy’s refusal to pay to avoid its obligations to W.W. Gay.” Walbridge Aldinger, 2013 WL at *5.

 

 

CONSIDERATIONS:

  • It’s hard to play both sides of the fence. In this case, the prime contractor wanted to play both sides by arguing on one hand that the Navy (government) caused delays it was assessing liquidated damages for and on the other side arguing that the subcontractor caused delays. It takes more than “conjecture” or argument to establish an actual delay. If a party argues delay, it needs to prove the delay (to the critical path that contributed to the overall delay to the project’s schedule) and not just that it “may” have caused delay or that it “could” have caused the delay based on the outcome of the dispute with the government over the assessment of liquidated damages. If the prime contractor wants to employ this tactic, it should include a provision that would allow it and its surety to withhold sums for any potential delay, although unsupportable, if the government assesses liquidated damages until the government’s assessment of liquidated has been resolved and that all claims between the parties regarding such sums shall be stayed pending the resolution. Naturally, such a clause needs to be ironed out with much more specificity and thoroughly considered because there are pros and cons to the provision including whether such a provision would be enforceable against a Miller Act surety (considering suits against the surety must be filed within a year from the subcontractor’s final furnishing). Otherwise, playing both sides can be challenging unless the prime contractor is taking the position with supportable schedule analysis that the subcontractor actually caused delays to the critical path.

 

  • The entitlement to additional work items is a common dispute between subcontractors and prime contractors. Thus, it is important to ensure that there are good notice provisions in the subcontract and that the subcontract clearly specifies what a subcontractor needs to do to be entitled to additional work. In this case, the subcontractor did send notice and was directed to proceed with the work and maintained time sheets verifying its additional work amounts. Too often subcontractors do not keep track of such amounts on a time and materials basis as specified in the subcontract and/or fail to submit timely notice.

 

  • The Eleventh Circuit’s discussion of the implied obligation of good faith and fair dealing is an interesting discussion. The reason being is that it creates an argument that a subcontractor could be entitled to additional work items even if it did not truly comply with contractual provisions, especially if the subcontractor was directed to perform the work pursuant to a construction change directive or another provision.

 

For more information on the a Miller Act payment bond, please see https://floridaconstru.wpengine.com/522/ and https://floridaconstru.wpengine.com/an-argument-to-recover-attorneys-fees-against-a-miller-act-payment-bond/

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

PAY-WHEN-PAID PROVISIONS AND PAYMENT BONDS


Pay-when-paid (also known as pay-if-paid) provisions are customary in subcontract agreements. These provisions provide that the contractor must be paid by the owner for the subcontractor’s work as an express condition precedent to the contractor’s payment to the subcontractor. Thus, if the contractor does not get paid by the owner, the subcontractor does not get paid by the contractor. This is a must-include provision to contractors as it shifts the risk of the owner’s nonpayment to the subcontractor.

 

However, on public projects and even many large-scale private projects, the contractor is required to obtain a payment bond that guarantees the contractor’s payment to subcontractors. Importantly, the pay-when-paid language does not protect a payment bond surety; it is not a defense to a payment bond surety. See OBS Co., Inc. v. Pace Construction Corp., 558 So.2d 404 (Fla. 1990) (finding that pay-when-paid language in subcontract does not prevent subcontractor from suing payment bond); see also Everett Painting Co. v. Padula& Wadsworth Const., Inc., 856 So.2d 1059, 1061 (Fla. 4th DCA 2003) (“However, this [pay-when-paid] contract provision is not a defense that is available to Surety.”).

 

From a subcontractor’s perspective, it is important on the front-end to know whether a payment bond is in place and, if so, what steps need to be taken to preserve a payment bond claim in the event of nonpayment. If there is any concern as to whether the general contractor was paid by the owner, it may be advisable to pursue the payment bond directly (instead of the contractor) unless there are reasons not too such as issues with the subcontractor’s compliance with statutory conditions precedent to sue on the bond. (Also, if there are concerns with the venue provision in the subcontract, pursuing a claim against the bond may create an argument to sue in a venue outside of the venue provision in the subcontract.)

 

From the general contractor’s perspective, if there is a payment bond in place, it needs to appreciate that the pay-when-paid defense will not apply to its surety.  One thought is to include a provision in the subcontract that references that the subcontractor understands that the surety is an intended-third party beneficiary of pay-when-paid language and can utilize the pay-when-paid defense in the event the general contractor is not paid for the subcontractor’s work. There is, however, a strong argument that this language would not be enforceable based on caselaw set forth above that does not allow a surety to benefit from the pay-when-paid defense. The leading Florida Supreme Court case, OBS Co. (cited above), that finds that a surety cannot benefit from this pay-when-paid defense, states:

 

“The payment bond is a separate agreement, and any inability to proceed against the general contractor does not necessarily prevent recovery against the sureties under the bond. In this case recovery under the payment bond is in no way conditioned on the owner making final payment to Pace [general contractor]. Nor does the bond incorporate the payment terms of the subcontract.”

 

Based on that bolded language, it is an uphill battle to create an argument that the surety can be protected by the pay-when-paid defense because the payment bond does not incorporate each and every subcontract and such language would merely turn the bond into a conditional payment bond, i.e., a bond conditioned on the owner’s payment to the contractor.  Including language in the subcontract that says the surety is an intended third-party beneficiary of the pay-when-paid language is definitely a tough sell, but it has little downside, as the worst that happens is that the pay-when-paid defense does not apply to claims against the surety no matter what, which is likely the case.

 

Notably, it is advisable for the general contractor to include language in subcontracts that provides to the extent the pay-when-paid provision conflicts with language in the prime contract, the pay-when-paid language shall govern. The reason being is to avoid any argument that the pay-when-paid language is ambiguous because it conflicts with language in the prime contract (that is incorporated into the subcontract) which would not have a pay-when-paid provision.

 

For motion information on pay-when-paid provisions, please see: https://floridaconstru.wpengine.com/careful-drafting-of-pay-when-paid-provisions/

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

VENUE FOR PAYMENT BOND DISPUTES IN FLORIDA


Two main Florida payment bond statutes are Florida Statute s. 713.23 (payment bonds for private projects) and Florida Statute s. 255.05 (payment bonds for Florida public projects-not federal projects). Both statutes prohibit a payment bond issued after October 1, 2012 from restricting venue. In other words, if the payment bond contains a venue provision after this date, it is not enforceable.

 

This prohibition is important because there are times where the project is located in a venue that is not where the subcontractor resides and/or is contrary to the venue provision in the subcontract (typically, a venue where the general contractor resides).

 

It is good practice for the general contractor to include in its subcontract a venue provision that applies to its surety such that the subcontractor must sue the payment bond in the same venue that governs the subcontract. While it is uncertain how the new prohibition from restricting venue in a payment bond will apply in this context, the counter-argument is that the payment bond is not restricting venue, rather the “negotiated” subcontract governs the venue of any and all disputes between the parties including claims against the general contractor’s surety (and the general contractor is indemnifying and defending the surety). Worst case scenario is that the venue provision is deemed inapplicable to the surety. However, courts do not favor splitting causes of action (due to, among other things, the concern for conflicting results over the same facts) and should not favor a subcontractor lawsuit against the general contractor in one venue and a simultaneous subcontractor lawsuit against the general contractor’s payment bond surety in another venue. Indeed, courts have refused to enforce venue provisions in subcontracts in order to avoid splitting of causes of action. See, e.g., Miller & Solomon General Contractors, Inc. v. Brennan’s Glass Co., Inc., 837 So.2d 1182 (2003) (refusing to enforce subcontract venue provision when action as to lien transfer bond was filed in correct venue). Including a venue provision that also covers claims against the payment bond surety is useful in the event the general contractor wants to countersue the subcontractor or simply wants to create an argument that its subcontractor disputes should be confined to its preferred venue versus the subcontractor’s preferred venue.

 

On the other hand, there are situations where a subcontractor may not want to sue the general contractor and strategically prefers to just sue the payment bond surety. One situation may be the subcontractor knows the general contractor was not paid and the subcontract contains a pay-when-paid provision which would be enforceable as to the general contractor, but not against the payment bond surety. Another situation may be due to the venue provision in the subcontract; the subcontractor prefers to sue in a venue outside of the venue provision in the subcontract and has a better argument around the venue provision if it does not join the general contractor. There is caselaw that supports an argument to sue a payment bond surety in a venue where the subcontractor (lienor) resides that, depending on the dispute, could be appealing to the subcontractor. See, e.g., American Insurance Co. v. Joyner Electric, Inc., 618 So.2d 799 (Fla. 1st DCA 1993) (finding that action under s. 255.05 public payment bond was proper where lienor / subcontractor resided); Coordinated Constructors v. Florida Fill, Inc., 387 So.2d 1006 (Fla. 3d DCA 1980) (finding that venue was proper under s. 713.23 private payment bond action where lienor / supplier resided).

 

Venue is a pretty heavily litigated procedural strategic issue.   Just like any dispute, venue as to a payment bond claim should not be ignored and should absolutely be considered at the onset of a dispute.

 

For more information on venue provisions, please see:

https://floridaconstru.wpengine.com/venue-provisions-read-what-you-sign/

and

https://floridaconstru.wpengine.com/subcontractors-read-and-understand-the-implications-of-venue-provisions/

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

RECOVERING DELAY RELATED DAMAGES FROM PUBLIC PAYMENT BOND


One of the advantages to subcontractors of public payment bonds issued under the Federal Miller Act (or even the Little Miller Act) is that there is an argument for the recovery of unexecuted change orders and, and as it particularly pertains to this article, impact-related costs (whether delay or inefficiency / lost productivity). This should not be overlooked although language in the governing subcontract, etc. could dilute these arguments. However, having the argument and opportunity to recover impact-related costs from a payment bond is a huge upside.

 

If a subcontractor is owed money for inefficiency or delay, etc., and there is a public payment bond in place, it should not automatically forego pursuing these claims against the bond. Unlike a lien where these types of costs / damages are not lienable and could render an otherwise valid lien fraudulent in Florida, these are damages that could be pursued against a public payment bond. The subcontractor should carefully craft its argument in furtherance of maximizing its best chance to recover these types of damages.

 

For example, in the opinion of Fisk Elec. Co. v. Travelers Cas. and Sur. Co., 2009 WL 196032 (S.D.Fla. 2009), a subcontractor sought inefficiency / lost productivity damages against a payment bond surety that appeared to be issued under Florida Statute s. 255.05 (also known as Florida’s Little Miller Act). The payment bond surety moved to dismiss the subcontractor’s complaint arguing that these types of damages are not recoverable under the bond. The Southern District, relying on federal cases interpreting the Federal Miller Act, found that a subcontractor can pursue such damages against the payment bond for its out-of-pocket unreimbursed expenses. See, e.g, U.S. f/u/b/o Pertun Const. Co. v. Harvesters Group, Inc., 918 F.2d 915, 918 (11th Cir. 1990) (finding that subcontractor could recover under Federal Miller Act bond for out-of-pocket expenses resulting from prime contractor’s delay).

 

To maximize the recoverability for impact-related costs, the costs should be supportable costs that the subcontractor actually incurred in the performance of its contract work. Organizing the back-up supporting these costs and theory of the impact is critical and the subcontractor looking to pursue these costs from a public payment bond should consult counsel to best position its arguments to support recovery.  On the other hand, the prime contractor should ensure that its subcontract has contractual provisions that will make it challenging and provide hurdles for the subcontractor to recover such damages.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

ARGUMENTS TO RECOVER ATTORNEYS’ FEES AGAINST A MILLER ACT PAYMENT BOND


For those subcontractors and suppliers providing labor, services, or materials to federal construction projects, understanding your rights under the Federal Miller Act (40 USC s. 3131 et seq.) is important. Among other things, the Miller Act advises what a subcontractor and supplier need do to preserve a right against the prime contractor’s payment bond, from providing the prerequisite notice of nonpayment to the surety within 90 days from final furnishing / performance (if there is no privity of contract with the prime contractor) to ensuring suit is filed in federal court within a year from final furnishing / performance. Obtaining a copy of the payment bond and understanding these timeframes is critical to an unpaid subcontractor or supplier; otherwise, their claim will be barred against the payment bond.

 

One of the downsides to Miller Act bond claims is that there is no statutory right to the recovery of attorneys’ fees under the Federal Miller Act. This means that every dollar spent on lawyers is potentially reducing the amount in recovery because there is no avenue to recoup those attorneys’ fees under the Miller Act.  Unless this claim is significant, this downside often demotivates a supplier or subcontractor from filing suit in federal court against a Miller Act payment bond.

 

There are, however, arguments to recover attorneys’ fees in a Miller Act action.  The first argument is if there is an underlying contract involving the claimant relating to the project that provides for attorneys’ fees (such as the contract between the subcontractor and prime contractor), the claimant can recover its attorneys’ fees.  See, e.g., U.S. f/u/b/o Southeastern Mun. Supply Co., Inc. v. National Union Fire Ins. Co. of Pittsburg, 876 F.2d 92 (11th Cir. 1989) (finding that attorneys’ fees provision in contract between supplier and subcontractor was enforceable to enable supplier to recover attorneys’ fees against Miller Act surety).

 

There is also a second argument that attorneys’ fees should be recoverable in Florida against a Miller Act bond under a 1968 Fifth Circuit Court of Appeal’s decision in United States Fidelity and Guaranty Co. v. Hendry Corp., 391 F.2d 13, 20-21 (5th Cir. 1968). This case analyzed Florida law to fill in the gap to determine whether attorneys’ fees were recoverable under the Miller Act (since the Act is silent on the issue). In doing so, the Fifth Circuit analyzed Florida’s Insurance Code and maintained that provisions in Florida’s Insurance Code (still in effect today) allow for the recoverability of attorneys’ fees in a Miller Act bond dispute.

 

Parties pursuing Miller Act actions for Florida-based federal projects should plead for attorneys’ fees whether through a contractual provision and/or the Fifth Circuit’s ruling in Hendry Corp.  Now, it is uncertain whether the Fifth Circuit’s ruling would still apply today; however, it is an argument that should still be pursued in furtherance of trying to recover attorneys’ fees in an action against a Miller Act payment bond, especially if there is not an underlying contract that provides for attorneys’ fees.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

INDEMNITY AGREEMENTS BETWEEN A SURETY AND ITS BOND PRINCIPAL


Sureties that issue contractors payment and/or performance bonds obtain indemnity agreements with the contractor, or bond principal, prior to issuing such bonds. These indemnity agreements, besides requiring the bond-principal contractor to indemnify, defend, and hold harmless the surety in the event a claim is submitted on the bonds, are designed to fully protect the surety in the event the contractor fails to do so.

 

There are situations where a surety needs to protect its own interests and comply with the terms of the bond and pay a claim on a performance or payment bond (such as if the contractor gets into financial trouble, walks off a project, is not paying subcontractors, etc.). If the surety pays a claim, they typically assert a claim against the bond-principal contractor for breach of the indemnity agreement along with any person that personally guaranteed the agreement (which is often the case). The indemnity agreement will include a provision that provides that the bond-principal assigns certain collateral to the surety in the event the principal is in default of the agreement. Among those rights that are collaterally assigned to the surety would be all of the principal’s contract rights and causes of action for accounts receivable.

 

The case of Guarantee Co. of North America v. Mercon Construction Co., 2012 WL 1232104 (M.D.Fla 2012), exemplifies a surety’s rights under the indemnity agreement. This case involved a situation where a surety paid a performance bond claim on behalf of its principal contractor and sued the contractor, as well as others, under the indemnity agreement. The surety also exercised its right under the indemnity agreement and settled a claim the contractor had against another payment bond (issued by a different surety). In other words, the surety’s position was that the claim for an account receivable under the other payment bond was collaterally assigned to the surety due to the contractor’s default. The contractor asserted a counterclaim arguing, among other things, that the surety did not have the authority to settle its account receivable payment bond claim. The Middle District disagreed and dismissed the contractor’s counterclaim with prejudice!

 

If a bonded contractor is involved in a situation where its surety either paid a claim or will pay a claim, it is important for the contractor to consult an attorney to understand the surety’s rights under the indemnity agreement. Again, surety’s oftentimes have the indemnity agreement personally guaranteed so that the obligations under the agreement could not only impact the bond-principal contractor but also the guarantors to the agreement.

 

 

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CAREFUL DRAFTING OF PAY-WHEN-PAID PROVISIONS


The pay-when-paid provision is an important aspect of a contractor’s subcontract.  Under this provision, the risk of an owner’s nonpayment to a contractor for a subcontractor’s scope of work is shifted to the subcontractor.  In other words, a contractor is not responsible for paying the subcontractor unless the contractor was specifically paid by the owner for the subcontractor’s work–the owner’s payment to the contractor serves as an express condition precedent to the contractor’s payment to a subcontractor.  However, for pay-when-paid provisions to be enforceable, they need to be clearly drafted so that it is unequivocal that the owner’s payment to the contractor for a subcontractor’s work serves as the express condition precedent to the contractor’s payment to the subcontractor.

 

Subcontractors oftentimes look for arguments to circumvent the pay-when-provision.  If the contractor has a payment bond, then the subcontractor does not need to look to the contractor for payment, even if the owner has not paid the contractor for the subcontractor’s work.  When there is a payment bond, the subcontractor can sue the bond and the surety that issued the bond cannot raise the pay-when-paid provision as a defense.    See OBS Co. v. Pace Construction Corp., 558 So.2d 404 (Fla. 1990).

 

However, if there is no payment bond, or the subcontractor, for whatever reason, did not properly preserve its rights to pursue a payment bond claim, the recent case of International Engineering Services, Inc. v. Scherer Construction & Engineering of Central Florida, LLC, 2011 WL 5109306 (5th DCA 2011), provides another argument that a subcontractor can raise in an effort to escape the harsh effect of a pay-when-paid provision.  In this case, the subcontract incorporated by reference the contractor’s prime contract with the owner.  The prime contract provided:

 

“Neither final payment nor any remaining retained percentage shall become due until the Contractor submits to the Architect (1) an affidavit that payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the Owner or the Owner’s property might be responsible or encumbered (less amounts withheld by Owner) have been paid or otherwise satisfied.”

 

The subcontractor successfully argued that this provision in the prime contract, which was incorporated into its subcontract, created an ambiguity with the pay-when-paid provision.  The reason being is that this provision maintained that the owner was not responsible for paying the contractor until the contractor paid its subcontractors.  Well, this conflicts with a pay-when-paid provision which says a contractor is not responsible for paying a subcontractor until an owner has paid the contractor.  By the subcontractor arguing that this provision in the prime contract conflicts and creates an ambiguity with the pay-when-paid provision, the Fifth District held that the pay-when-paid provision was unenforceable because it was ambiguous.  Thus, the contractor was responsible for paying the subcontractor!

 

The outcome of this case is important for both contractors and subcontractors.  For contractors, it is important to ensure that language in the prime contract does not conflict with language in the subcontract, particularly the pay-when-paid provision.  Typically, all subcontracts incorporate by reference the prime contract.  One thing a contractor can do is to include a provision in the subcontract that says something to the effect: “If anything in the subcontract conflicts or creates an ambiguity with anything in the prime contract, the terms of the subcontract shall govern.  This includes anything that conflicts with the pay-when-paid provision included in this subcontract and subcontractor therefore understands that owner’s payment to contractor for subcontractor’s scope of work is an express condition precedent to contractor’s payment to subcontractor.”

 

For subcontractors, it is important to request a copy of the owner’s prime contract with the contractor since it is incorporated into the subcontract.  By looking for a provision in the prime contract that may conflict with the pay-when-paid provision in the subcontract–a provision similar to the one referenced above that requires the contractor to pay its subcontractors before the owner is obligated to pay the contractor final payment–can allow the subcontractor to argue that the pay-when-paid provision should be deemed unenforceable thereby making the contractor liable to the subcontractor for payment even if the contractor was not paid by the owner.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

CONTRACTORS AND SUPPLIERS-DO NOT NEGLECT THE NOTICE REQUIREMENTS IN FLORIDA’S LIEN LAW


Oftentimes, subcontractors, suppliers, and sub-subcontractors rely on companies to serve the statutory notices that are prerequisites to preserving a lien or bond claim under Florida’s Lien Law in the event of nonpayment.  However, if these notices are not served in accordance with Florida’s Lien Law, the outcome could be injurious to the subcontractor, supplier, or sub-subcontractor.  Stated differently, the outcome could mean a loss of lien or bond rights which may be the only true leverage the party has to secure payment.

 

The case of Stock Building Supply, Inc. v. Soares Da Costa Construction Services, LLC, 36 Fla. L. Weekly D2200a (Fla. 3d DCA 2011), illustrates the absolute importance of complying with the notice requirements in Florida’s Lien Law.

 

 

In this case, an owner hired a contractor to build a condominium.  The contractor subcontracted with a structural shell subcontractor which, interestingly, held a 40% ownership interest in the contractor.   The subcontractor engaged a supplier to provide rebar to the project.  The contractor also engaged the same supplier to provide certain materials to the project.  To graphically illustrate:

 

 

Contractor –> Shell Subcontractor –> Supplier

and

Contractor –> Supplier

 

 

Originally, there was no payment bond on the project.  Therefore, once the supplier was engaged to provide materials, it served a statutory notice to owner on the contractor and the owner stating that it was supplying materials under an order given by the subcontractor.  It served a second notice to owner on the contractor and owner stating it was supplying materials under an order given by contractor. (Notably, Florida Statute §713.06 requires lienors not in privity of contract with the owner to serve a notice to owner on the owner no later than 45 days after commencing services.  The notice should also be served on anyone up the chain to the owner the lienor is not in privity of contract with, i.e., the sub-subcontractor or supplier to the subcontractor should serve the notice on the contractor too.  This is a mandatory statutory notice if there is not a payment bond in place.)

 

 

Shortly after construction commenced, there was a funding problem that led to a halt in construction.  The supplier recorded 2 claims of lien for nonpayment: one for nonpayment by the subcontractor and the other for nonpayment by the contractor.

 

 

The owner then paid the supplier and had the liens satisfied and recorded a notice of termination of the initial notice of commencement which is a procedure under Florida’s Lien Law that allows an owner to terminate a notice of commencement that accurately states that all lienors were paid in full.  After the notice of commencement was terminated by law, the owner recorded a new notice of commencement that attached a payment bond, meaning the owner’s property was now exempt from all liens except that of the general contractor it hired.  (One of the main reasons an owner would terminate a notice of commencement and record a new notice of commencement is so a construction lender financing construction can record a mortgage and maintain a first priority encumbrance on the property in the event the owner did not repay the loan.)

 

 

Once construction restarted, the supplier continued supplying rebar to the structural shell subcontractor.  The supplier also continued to supply building materials to the contractor.  However, for whatever reason, the company the supplier hired to serve the statutory notices served only one statutory notice to contractor stating that the supplier was supplying building materials under an order given by the contractor.   Unlike the notice to owner mentioned above, when there is a payment bond in place, lienors not in privity of contract with the contractor must serve a notice on the contractor stating that they intend to look to the contractor’s payment bond for payment.  In other words, the supplier was required to serve a notice on the contractor that it was supplying materials under an order given by the subcontractor, but it really wasn’t required to serve the same notice for the supplies it was providing under an order given by the contractor.

 

 

The point or objective of the notices is so the owner, in a situation without a payment bond, and a contractor, in a situation with a payment bond, know specifically who is performing work on the project to ensure these entities get paid.  The reason why a contractor doesn’t need to serve a notice to owner (when there is no bond) or a subcontractor doesn’t need to serve a notice on the contractor (when there is a payment bond) is because the owner or contractor in these situations know the entities it hired to ensure these entities get paid.

 

 

Although the contractor paid the structural shell subcontractor for the rebar, the subcontractor did not pay the supplier.  The supplier then served a notice of nonpayment on the payment bond surety (another prerequisite to suing on a general contractor’s payment bond) and filed suit.

 

 

The main issue in this case was whether the supplier had properly preserved a payment bond claim for the rebar it supplied to the subcontractor that it was not paid for by virtue of its neglect in serving the proper notice on the contractor that it was supplying rebar under an order given by the subcontractor.  The trial court concluded that the supplier could NOT pursue a payment bond claim because it failed to serve this notice.  The Third District affirmed the trial court on this issue essentially holding that because lien and bond claims are creatures of statute, the supplier’s failure to comply with the lien law by serving this initial notice was fatal to its bond claim for rebar materials it supplied to subcontractor.

 

 

Unfortunately for the supplier, this is a hypertechnical argument that killed its claim against the payment bond for materials it supplied under the order given by the structural shell subcontractor. This ruling, however, does not seem to make sense in light of the specific facts of the case.  Again, the whole point of the notice is so the contractor in this situation knows that the supplier is supplying rebar to the subcontractor and that it will look to the payment bond if it is not paid so that the contractor can affirmatively ensure the supplier gets paid.  First, the contractor knew the supplier was supplying rebar because before the owner terminated the notice of commencement, the supplier was supplying the same rebar and the contractor was made aware of same. Second, after the owner recorded a new notice of commencement with a payment bond, the supplier served a notice on the contractor (although it was not legally required to do so) that it was serving materials to the contractor per an order given by the contractor.  Well, at this point in time, the contractor had continued knowledge the supplier was still involved in the project and still supplying materials, even though there may have been oversight in that another notice was not also provided by supplier for the materials it was providing under an order given by the subcontractor.  And, last, the subcontractor owned 40% of the contractor, thus, how could contractor not know that its minority owner was still utilizing and ordering rebar?  The Third District did not get into this, but I believe this fact is important because it would seem to impute some knowledge on the contractor under this fact pattern  that the subcontractor was still utilizing the supplier, which just so happened to an identical supplier that contractor was utilizing and ordering materials from.  Thus, where was the prejudice to the contractor??

 

 

Regardless of the equities of the Third District’s decision, the morale remains that it is absolutely critical to comply with Florida’s Lien Law, as in many circumstances, oversight or neglect will not be tolerated!!  Do not let this happen to you!

 

In this case, the supplier used an outside company to serve the required statutory notices and it was uncertain why the outside company did not serve the required notice on the contractor that supplier would look to the bond for protection if it was not paid for materials supplied to the subcontractor, especially when it served the unnecessary notice for materials being supplied directly to contractor.  The supplier or outside company’s oversight, whatever the case may be, resulted in a loss of its payment bond claim.

 

 

To prevent this from happening, it is always a good idea to utilize an attorney on the front end to ensure the proper notices are being served.  An attorney understanding construction will ask: 1) is it a private project or publicly funded project; 2) do you have a copy of the notice of commencement (to see whether there is or is not a payment bond in place); 3) who hired you; and 4) when did you first start commencing services.  In the event of nonpayment, the attorney will ask the follow-up questions: 5) when was your last day on the job and 6) how much are you owed and how did you arrive at this specific amount (e.g., retainage owed, contractual work owed, change order work owed, does this include delay-related damages or lost profit, etc.) in order to ensure the lien or payment bond claim comports with Florida’s Lien Law.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.