DON’T FORGET TO INCLUDE TERMINATION LANGUAGE IN YOUR CONTRACT

A recent case explains why termination language or a basis to withhold contract sums is important in your contract. Don’t neglect this language or the negotiation that goes into having this language.

In a recent dispute, GSD Contracting, LLC v. All American Builders & Debris Removal, Inc., 2026 WL 3068422 (Fla. 4th CA 2026), a subcontract included language that said that 10% retainage would be paid  90 days after final completion of the project. The subcontract did NOT include termination for cause language; it only included termination for convenience language. Towards the end of the project, mold was discovered warranting mold remediation. The subcontractor refused to perform until the mold was remediated. The general contractor claimed it was remediated but the subcontractor argued the remediation was insufficient because the contractor did not engage an industrial hygienist. After the subcontractor refused to complete its work, the general contractor terminated the subcontractor for cause. The subcontractor then sued the general contractor for its 10% retainage claiming the general contractor breached the subcontract. The trial court, as affirmed by the appellate court, agreed.  The appellate court found that the contract required the general contractor to pay the subcontractor’s retainage 90 days after final completion and the project had long been completed. “Significantly, the subcontract does not contain a termination for cause provision or any pertinent provision permitting [the general contractor] to withhold or retain [the subcontractor’s] retainage following a termination…Nothing in the subcontract provides that [the general contractor] may thereafter withhold the retainage based on an alleged default by [the subcontractor].”  GSD Contracting, supra, at *2.

Think about this. Because the subcontractor contained no termination language or basis to withhold retainage / contract sum language, the general contractor had to pay the subcontractor the retainage. The court essentially found that subcontract required the general contractor to pay and then “chase” the subcontractor to recover such money stemming from a subcontractor default.  The moral to this issue, whether you agree with the court or not on the outcome, is spending the time on the frontend negotiation of the contract to ensure it has the language to protect interests. Naturally, if you are a subcontractor, excluding such language can be a blessing, as it was here.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: TIMING TO SUE PUBLIC PAYMENT BOND FOR RETAINAGE ON PUBLIC CONSTRUCTION PROJECTS

imagesYou are a subcontractor (or sub-subcontractor) on a public construction project.  The general contractor has a public payment bond per Florida Statute s. 255.05.  You finished your scope some time ago but you are still owed retainage.  When do you sue for retainage?  There is a statutory retainage exception that governs the timing of when to sue for retainage.  Check out this article for the applicable statutory language regarding the retainage exception.  Timing is important to ensure that you do not prematurely sue for retainage or, worse, sue for retaiange after the statute of limitations expired.  

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

HELPFUL PROVISIONS IN FLORIDA’S LOCAL GOVERNMENT PROMPT PAYMENT ACT


Florida’s Local Government Prompt Payment Act (Florida Statute s. 218.735) contains helpful provisions to contractors and subcontractors working on local government projects (or projects that are neither owned by a state agency nor private entity that would be governed under different prompt payment acts).  These provisions pertain to the generation of the punchlist and the release of retainage.

 

 

 

 

 

A. Punchlist

The contract between the general contractor and local governmental entity needs to provide for the generation of a single punchlist.  The contract needs to specify the process required to generate the punchlist including the responsibilities of both the local governmental entity and contractor.  For projects with estimated construction costs less than $10 Million, the punchlist needs to be generated within 30 days after substantial completion.  For projects with estimated construction costs of $10 Million or more, the punchlist needs to be generated within 30 days after substantial completion; although, this may be extended by contract to up to 60 days after substantial completion.

 

If the punchlist is not provided to the contractor by the required date (through no fault of the contractor), the contract time for completion needs to be extended by the number of days the punchlist is delayed.  Moreover, the contractor can submit its payment application for the retainage balance and payment of any undisputed amount must be paid.

 

If a dispute exists as to any item on the punchlist, the local governmental entity may only withhold up to 150% of the cost to complete such items.  Once the contractor completes the items on the list, it can submit its payment request for retainage.

 

Importantly…and I repeat, importantly…warranty items or items not identified on the (single) punchlist may not impact the local governmental entity’s final payment of retainage!   Also, if the local governmental entity is utilizing an Owner Controlled Insurance Program (known as “OCIP”), the local governmental entity cannot withhold retainage or delay final payment pending a final audit to determine the insurance premium.

 

B. Retainage

The local governmental entity is entitled to withhold 10% retainage on progress payments until the project is 50% complete. After the project is 50% complete, the local governmental entity must reduce the retainage on future progress payments to 5%.  The contractor may also submit a payment application to the local governmental entity for ½ of the retainage (5%) that the governmental entity was withholding until 50% completion (which must be paid unless there is a good faith dispute for withholding some or all of this retainage).

 

As it relates to subcontractors, the contractor can still withhold retainage greater than 5%; however, the “contractor shall notify the subcontractor, in writing, of its determination to withhold more than 5 percent of the progress payment and the reasons for making that determination, and the contractor may not request the reqlease of such retained funds from the local governmental entity.”  Fla.Stat. s. 218.735(8)(c).

 

(This retainage reduction does not apply to municipalities with a population of 25,000 or fewer or counties having a population of 100,000 or fewer, meaning these local governmental entities can withhold 10% retainage until final completion.)

Florida’s Local Government Prompt Payment Act gives the general contractor the argument that only a single punchlist needs to be generated versus a never-ending punch list that the local governmental entity continues to add to so that there is no end in sight to the punchlist completion.  It further allows the contractor to submit its payment application for its final contract balance of retainage if the punchlist is not timely generated through no fault of the contractor.  Additionally, Florida’s Local Government Prompt Payment Act not only authorizes a reduction in retainage to 5% at 50% completion, but allows the contractor to bill for half of the withheld retainage that the local government was withholding through 50% completion.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.