RECOVERING ATTORNEY’S FEES AND ARGUING THE FEES ARE INEXTRICABLY INTERTWINED

Attorney’s fees are a big part of any dispute. And the attorney’s fees should be because fees are a factor and can ultimately drive the outcome of a dispute. No one wants to spend $100,000 in fees to recover $100,000, so the conversation regarding attorney’s fees needs to be had early.

Generally, a party can recover reasonable attorney’s fees if authorized by contract or by statute. So, there would need to be a prevailing party attorney’s fees provision in a contract, if suing on a contract, or there would need to be a statute authorizing the recovery of attorney’s fees, if suing on a statute. Then, there is authority that the party still needs to prevail on the significant issues in the dispute, as determined by the trial court (or binding arbitrator), in order to be the prevailing party for purposes of attorney’s fees. (Absent that, you are dealing with a proposal for settlement to create a procedural basis to recover fees, which is explained here.) Reasonable attorney’s fees, however, does not mean you will recover 100% of your attorney’s fees. Some percentage will presumably be discounted meaning becoming 100% whole when factoring in attorney’s fees is not always a practical outlook.

Why am I discussing this? This is why.

In a recent dispute, Nova Southeastern University, Inc. v. Garratt-Callahan Co., 50 Fla.L.Weekly D2247a (Fla. 4th DCA 2025), a university sued three professionals for deficiencies in its complex cooling system. The university sued the mechanical engineer as well as two consultants engaged to oversee the treatment and maintenance of this cooling system. Claims sounded in professional negligence as to the engineer and professional negligence and breach of contract as to the consultants. The University settled with the engineer and one of the consultants. The issue with the remaining consultant was attorney’s fees.  The University sought ALL of its attorney’s fees incurred in connection with the dispute claiming the fees against the remaining defendant were inextricably intertwined with the settling defendants. This was a significant cost as the University was seeking more than $1.2 Million in fees alone, which was an amount that had been discounted by its own attorney’s fees expert. The trial court, however, only awarded the University about $177,000 in attorney’ fees, which was a sizeable reduction to the attorney’s fees being claimed.  The reason being was that the fees were NOT inextricably intertwined. I think we can all agree that not recovering more than $1 Million in attorney’s fees is a big consideration!

The University appealed…and lost…with the appellate court containing an important discussion on attorney’s fees when suing multiple parties and claiming the fees are inextricably intertwined:

  “[T]he party seeking fees has the burden to allocate them to the issues for which fees are awardable or to show that the issues were so intertwined that allocation is not feasible.” “Claims are ‘inextricably intertwined’ when a ‘determination of the issues in one action would necessarily be dispositive of the issues raised in the other.’ ”  “In other words, where the claims involve a ‘common core’ of facts and are based on ‘related legal theories,’ a full fee may be awarded unless it can be shown that the attorneys spent a separate and distinct amount of time on counts as to which no attorney’s fees were sought.”  In contrast, “claims are separate and distinct when they could support an independent action and are not simply alternative theories of liability for the same wrong.

We find that the trial court did not err in finding that the claims against the defendants were not inextricably intertwined. The claim against [the mechanical engineer] was for professional negligence based on [the engineer’s] defective and deficient design. In contrast, the claims against [the two consultants] were for breach of contract and professional negligence relating to servicing the system. Additionally, [the two consultants] had different servicing contracts with [the University] that encompassed different periods of time and imposed different obligations. The agreement with [one consultant] required it to “furnish all the water quality testing and treatment services to ensure and maintain optimum operation of [the University’s] chilled water air conditioning systems.” In contrast, the agreement with [the other consultant] included a bid proposal, which reflected its obligation “to supply a high quality water chemical treatment service program to maintain peak operating efficiencies, with no deposition, corrosion, and biological growth prevention.” The proposal included detailed pages of specific water treatment services, encompassing areas of chemical feed and monitoring equipment, equipment inspection, various corrosion inhibitors, steam boiler treatment, corrosion monitoring, microbiological control, biocide treatment, chemical delivery, salt delivery and application, water/coupon/deposit analysis, and on-site service requirements. As [the remaining consultant’s] expert testified, there was a massive contamination during the time that [the other consultant] performed its obligations under the agreement. As a result, [the remaining consultant] inherited that contamination when it signed its agreement in 2016.

The claims would only be inextricably intertwined where a “determination of the issues in one action would necessarily be dispositive of the issues raised in the other.”  Since a finding that [the engineer] negligently designed the system would not necessarily have any bearing on whether [the two consultants] breached their respective contracts or were negligent, then these claims, as a result, would not be intertwined. Similarly, a finding that [one consultant] breached its contract or negligently maintained the system would not necessarily be dispositive as to whether [the remaining consultant] breached its contract or negligently maintained the system, which occurred after [the other consultant’s] maintenance term. The claims were “separate and distinct” because “they could support an independent action and are not simply alternative theories of liability for the same wrong.” 

Nova Southeastern University, Inc., supra (internal citations omitted).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

RECEIVING A $0 VERDICT AND STILL BEING DEEMED THE PREVAILING PARTY FOR PURPOSES OF ATTORNEY’S FEES

shutterstock_336450779Low and behold, a party can be the prevailing party for purposes of attorney’s fees even if that party is awarded $0.  That’s right, even if the party is awarded a big fat zero, they can still be the prevailing party for purposes of being entitled to attorney’s fees.   This is because a party is the prevailing party if they prevail on the significant issues in the case.  A party can prevail on the significant issues even if that party is awarded $0. Whoa!

 

For example, in Coconut Key Homeowner’s Association, Inc. v. Gonzalez, 43 Fla.L.Weekly D1045a (Fla. 4th DCA 2018), a homeowner sued her homeowner’s association claiming the association breached its governing documents. There was a basis for fees under Florida’s homeowner’s association law (and there likely was a basis under the governing documents).  At trial, the jury held that the association breached its governing documents, but awarded the homeowner nothing ($0). The trial court also issued injunctive relief in favor of the homeowner.  The homeowner claimed she should be deemed the prevailing party for purposes of attorney’s fees; however, this was denied by the trial court  based on the $0 verdict and no fees were awarded to the homeowner.

 

On appeal, however, the Fourth District took a different stance.  The Court, relying on other Florida appellate decisions, maintained that the homeowner could be deemed the prevailing party despite receiving no monetary award:

 

While the prevailing party determination does not depend solely on the magnitude of relief Gonzalez [homeowner] obtained, she was required, at the least, to secure some relief on the merits of her claim to achieve such status. “ [P]laintiffs may be considered a ‘prevailing party’ for attorney’s fees purposes if they succeed on any significant issue in litigation which achieves some of the benefit the parties sought in bringing suit.’ ”  Although there is ongoing debate in the courts on whether a plaintiff who recovers no money damages can be a prevailing party, a party who receives affirmative judicial or equitable relief is clearly considered a prevailing party under the law. Gonzalez was indisputably a prevailing party on her injunctive claim in equity, regardless of her marginal victory on the breach count. Thus, prevailing party attorney fees should be awarded to Gonzalez in this dispute. 

Gonzalez, supra (internal citations omitted).

 

The Fourth District  justified declaring the homeowner the prevailing party because an injunction was also issued in her favor.  Hence, she did receive some benefit by bringing the suit even if she recovered no monetary damages.  However, even if the homeowner did not bring a claim for injunctive relief, it is highly likely the same result would have been reached by the Fourth District.  Since the jury found that the association breached the governing documents, the homeowner would have achieved some benefit in bringing the suit and, therefore, prevailed on the significant issues.  Gonzalez, supra (“When there is a prevailing party statute or contract, reasonable attorney fees must be awarded.”). 

 

As of now, it is uncertain how this would be reconciled with the significant issues test to determine the prevailing party in a construction lien action.  Case law has held that a court has discretion to determine no party is the prevailing party for purposes of attorney’s fees in a construction lien action.  Putting this aside, however, this holding should apply to breach of contract cases and to other potential statutory claims that afford a basis for attorney’s fees to the prevailing party. Despite a party receiving no monetary award, they may still be deemed the prevailing party for purposes of attorney’s fees if they prevail on the significant issues in the case (e.g., the jury determined the other party committed a breach). 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

APPRECIATING THE RISKS OR FRUSTRATIONS OF ARBITRATION


Arbitration, just like litigation, can come with its own risks and frustrations. Once an arbitration award is rendered, the prevailing party will usually file an action or move to compel a circuit court to confirm the arbitrator’s award so that the award is turned into a judgment. However, a party that does not like the arbitrator’s award, will try to move to modify or vacate the award in accordance with Florida’s Arbitration Code (Florida Statutes Chapter 682). Although there are specific statutory grounds in order to move to modify or vacate an arbitrator’s award (and the motion must be filed within a specific window of time – typically, 90 days after delivery of the award), non-prevailing parties will still make an effort to vacate or modify the award with the circuit court within their required time parameters. The bases to modify or vacate an award are different than appellate rights afforded to litigants in court because an arbitration award is not supposed to be vacated or modified if an arbitrator erred as to the law.

 

The case of Wells v. Castro, 38 Fla. L. Weekly D1509a (Fla. 3d DCA 2013), illustrates certain frustrations. Without going into the factual details of the dispute, an arbitrator entered an award in favor of a claimant (party demanding arbitration) against one respondent (party responding to the demand for arbitration) and against the claimant as to another respondent. All of the parties agreed that the arbitrator is vested with the authority to determine the prevailing party for purposes of being entitled to attorneys’ fees. The respondent that prevailed as to the claimant’s claim wanted to be the prevailing party in order to recover its attorneys’ fees. However, the arbitrator found that neither party was the prevailing party meaning neither the respondent nor claimant would be entitled to recover their attorneys’ fees (as to the claimant’s claim against the prevailing respondent). Notably, under the Florida Supreme Court’s decision in Trytek v. Gale Indus., Inc., 3 So.3d 1194 (Fla. 2009), a court is to look at which party prevailed on the significant issues in the case for purposes of determining the prevailing party and has discretion to determine that there is not a prevailing party; stated differently, there is now uncertainty as to whether a party will be deemed the prevailing party and be entitled to their attorneys’ fees under the “significant issues” standard.

 

The respondent that prevailed moved the circuit court to essentially modify the arbitration award arguing that the arbitrator erroneously concluded that neither party was the prevailing party and that the respondent should have been deemed the prevailing party because it prevailed as to the claimant’s claims. The trial court granted the motion and deemed the respondent the prevailing party for purposes of being entitled to attorneys’ fees.

 

On appeal through a petition for a writ of mandamus (in this case, an appeal for the appellate court to order the trial court to confirm the arbitrator’s award), the Third District reversed the trial court maintaining: (a) the parties agreed to have the arbitrator determine the issue of prevailing party for purposes of attorneys’ fees (and need to live by that determination) and (b) an arbitrator’s error of law is not a basis to vacate or modify an award.   Thus, if the arbitrator erred in determining the prevailing party under Florida caselaw, the parties need to live with that determination because they agreed to have the arbitrator determine this issue in their arbitration.

 

While there are certain benefits to arbitration, it can come with its own risks and frustrations.  Again, the reasons to modify or vacate the award are limited under Florida statute and not designed to correct an arbitrator’s potential errors in law.  Also, if the parties want the arbitrator to determine the prevailing party for purposes of attorneys’ fees (which makes sense since the arbitrator will be the most familiar with the factual nature of the dispute), the parties will more than likely have to live by that determination.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

FURTHER CONFUSION TO RECOVERING ATTORNEYS’ FEES IN A LIEN ACTION


Recovering attorneys’ fees in a lien action is becoming more and more convoluted. Recent caselaw has made it more challenging for a party prevailing in a lien action to recover their attorneys’ fees. Now, the test to recover attorneys’ fees is the “significant issues test,” i.e., which party prevailed on the significant issues in the case. In other words, a party could win the lien action yet still not be entitled to recover their attorneys’ fees. Plus, the determination of the significant issues is in the discretion of the judge, meaning it is very difficult to predict whether a party will recover any attorney fees even if they prevail on the lien action.

 
The case of GMPF Framing, LLC v. Villages at Lake Lily Associates, LLC, 100 So.3d 243 (Fla. 5th DCA 2012), illustrates the challenges in recovering attorneys’ fees. In this case, a lienor recorded a claim of lien and filed a lien foreclosure action. However, instead of just suing to foreclose the lien, the lienor also sued for unjust enrichment and for an equitable lien (both counts which are difficult counts for a lienor / contractor to prevail on against an owner). The owner prevailed on the lien claim and the trial court awarded the owner attorneys’ fees. However, on appeal, the Fifth District Court of appeal reversed because it was undetermined which party won on the significant issues because the equitable lien and unjust enrichment claims remained pending even though the trial court discharged the lien. In particular, the Fifth District found that it is possible that the lienor could prevail on these remaining counts and be deemed the prevailing party by prevailing on the significant issues in the case.

 
This decision complicates how attorneys’ fees are awarded in a lien action and, to that end, which party will be deemed the prevailing party. A lien action is a statutory action that statutorily entitles a party to prevailing party attorneys‘ fees. See Fla.Stat. s. 713.29. The other counts in this lawsuit (unjust enrichment and equitable lien) have no statutory or contractual basis for attorneys‘ fees. Thus, they really should not factor in as to which party won on the significant issues of the lien action–the action that entitles a party to attorneys‘ fees. Unfortunately, this is not how the GMPF Framing Court ruled (nor does it appear to be how other Florida appellate courts will rule), which may have the undesirable effect of motivating lienors to sue on otherwise improper liens by simply coupling their lien claim with another claim and hope they are still able to prevail on the significant issues even if the lien claim is discharged.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.