SURETY REQUIRING COLLATERAL SECURITY UNDER GENERAL AGREEMENT OF INDEMNITY

In order to procure bonds (payment and performance bonds), you need to sign a General Agreement of Indemnity (referred to as the “GAI”) with the surety (bonding company). It does not matter the surety issuing the bonds, the terms and conditions in the General Agreement of Indemnity are largely consistent. These terms and conditions are one-sided written in favor of the surety. This is because bonds are not insurance. When a surety issues such bonds, it is doing so under the premise that it will get reimbursed every penny that it incurs relative to its exposure- whether incurred in attorney’s fees, consulting costs, or remediating a default or claim under the applicable bond. The General Agreement of Indemnity is one of the most powerful contracts in construction and is a contract that is not to be taken lightly.  It provides the surety numerous rights in the event of a claim.

A recent case, Travelers Casualty and Surety Co. of America v. Hemmer Construction, 2026 WL 2164439 (M.D.Fla. 2026), serves as an example. A bonded contractor was terminated for default on a construction project. The surety entered into a takeover agreement and assessed its exposure at north of $15 Million. The surety demanded that the contractor post collateral with the surety in the amount of north of $15 Million. The contractor refused and the surety filed a lawsuit that included a preliminary injunction requiring the contractor to post collateral security and furnish financial records.  There were other asserted claims such as indemnification. The contractor and its indemnitors countered arguing that its affirmative defenses should apply to bar the preliminary injunction, with the key defense being that the surety engaged in bad faith in assessing exposure and entering into the takeover agreement.

The contractor lost and the court granted the preliminary injunction.  Here is why. These are important considerations if you are ever in a situation where your surety is demanding collateral:

 

(1) The contractor and its indemnitors bore the burden of proof as to its affirmative defenses and, in particular at the preliminary injunction stage, the likelihood of success. “So Indemnitors must demonstrate their likelihood of success on such defenses. They fail to do so.” Hemmer Construction, supra, at *3.

 

(2) The key defense of bad faith was irrelevant at the preliminary injunction stage. “Collateralization and indemnification are distinct concepts. The sole issue before the Court is whether [surety] is entitled to collateral security; [surety] does not seek indemnification in its motion for preliminary injunction. And courts have held that ‘[w]hile issues of bad faith may be relevant to Plaintiff’s claim for indemnification under the [Indemnity] Agreement, they are not relevant to Plaintiff’s contractual right to collateral security.” Hemmer Construction, supra, at *3 (citation omitted).

 

(3) The defense of bad faith won’t apply unless the contractor and its indemnitors post the collateral security. “Courts routinely hold that ‘defendants’ failure to post collateral precludes the defendants’ relying on the defense of bad faith.’” Hemmer Construction, supra, at *3 (citation omitted).

 

(4) And as an aside, the contractors and its indemnitors did not substantiate bad faith. “ ‘To show bad faith, an indemnitor must show that the surety acted with ‘deliberate malfeasance,’ which is an intentional wrongful act that the actor has no legal right to do or any wrongful conduct which affects, interrupts, or interferes with the performance of official legal duty.’ ‘[A] lack of diligence or negligence is not the equivalent of bad faith, and even gross negligence is not the same as bad faith.” Hemmer Construction, supra, at *3 (citations omitted). Stated differently, proving that the surety acted in bad faith is a very difficult burden of proof!

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

DEPRIVING A PERFORMANCE BOND SURETY OF COMPLETION OPTIONS WILL RESULT IN A BREACH OF THE BOND

The purpose of a performance bond is to guarantee the completion of the contract upon default by the contract.”  Arch Insurance Co. v. A3 Development, LLC, 2026 WL 632330 (S.D. Fla. 2026) (internal citations and quotations omitted).

If you are an obligee (beneficiary of a performance bond) looking to trigger the surety’s obligations COMPLETION OBLIGATIONS under the bond, make sure you properly comply with the terms of the bond.  Failure to do so will result in a breach of the bond meaning you are discharging the surety’s obligations. This is the exact thing you DO NOT want to do.

A recent case supports the proposition that supplementing and performing remedial work to the bond-principal’s work, and using the bond-principal’s contract money to do so, results in a a breach of the bond.  This is important, need-to-know information, because if you do this and then seek recourse from the surety, you could be sh*t out of luck!

Without going into all the facts in Arch Insurance Co., an obligee of a performance bond (AIA performance bond) undertook efforts and costs to remediate a subcontractor’s defective concrete work. Such costs depleted the subcontract balance as the subcontractor was backcharged and not paid to the subcontractor. The question was whether this resulted in a breach of the bond by the obligee. Yes, it did.

“Generally, an obligee’s action that deprives a surety of its ability to protect itself pursuant to performance options granted under a performance bond constitutes a material breach[.]”

Florida courts have consistently found that an obligee’s unilateral decision to hire an alternate contractor to complete a subcontract without first giving the surety proper notice of a default and an opportunity to exercise its completion options deprives a surety of its ability to protect itself and, therefore, such conduct constates a material breach of the bond.”

Arch Insurance Co., supra (internal quotations and citations omitted).

Here, the obligee breached the bond by performing remedial work before notification to the surety:

[Obligees] argue that the general prohibition against an obligee unilaterally hiring a contractor to perform remedial subcontract work does not apply to the Bonds here because there is no provision in the Bonds or Subcontracts that require [Obligees] to first give [Surety] notice or an opportunity to complete the Subcontracts before using an alternative contractor to supplement or remedy the subcontracted work.  Notwithstanding [Obligee’s] contention to the contrary, the plain language of the Bonds precluded [Obligees] from remedying [subcontractor’s] materially inadequate or incomplete work through any means other than those expressly provided under the Bonds.

The procedures outlined in § 3 and § 5 were the Bonds’ exclusive remedial tools in the event [Obligees] determined that [subcontractor] was in default and unable to complete the Subcontracts. No provision in the Bonds or the Subcontracts suggests that, in lieu of the notice and default procedures in § 3 and § 5, [Obligees] could instead select an alternative or supplemental remedy not expressly provided for under the Bonds. Obligees therefore lacked any contractual basis to unilaterally hire a replacement or supplementary contractor, even if they reasonably believed such a course of action was a more efficient and cost-effective means of completing the Subcontracts. Consequently, because the Bonds governed how the parties were permitted to handle a default, once [Obligees] considered declaring [subcontractor] in default (i.e., when [Obligees] determined they would likely need a replacement or supplemental contractor to complete Subcontracts), § 3.1 required [Obligees] to promptly provide notice to [Surety] of the potential default. And if [Obligees] ultimately determined that [subcontractor] had defaulted on the Subcontracts, § 3.2 required them to declare a default to ensure that [Surety] was afforded its right to investigate the default and elect one of its completion options under § 5.

Arch Insurance Co., supra (internal quotations and citations omitted).

Please make sure to work with counsel if seeking to exercise the completion obligations of a performance bond surety.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

COURT STRIKES EXPERT OPINION THAT SURETY ACTED AS A “DE FACTO CONTRACTOR”

Designating and admitting experts is a vital component of any construction dispute.  Many construction disputes require experts.  Many construction disputes can only be won with the role of an expert. Thus, experts and construction disputes go hand-in-hand. No doubt about it!  Time needs to be spent on developing the right expert opinions to support your burden of proof. This means you want to designate the right expert that can credibly and reliably render an expert opinion.

It is common for one party to move to strike the testimony and expert opinions of another party. This is referred to as a Daubert motion. Sometimes the motion is about gamesmanship. Sometimes it is to see how the judge rules on the issue. Sometimes there is a legitimate reason associated with the expert opinion. And, sometimes, it is a combination of the above. Regardless of the reason, parties know the weight expert opinions can have and, therefore, treat the opinions seriously prompting the Daubert motion.

A recent opinion out of the Southern District of Florida, Berkley Insurance Co. v. Suffolk Construction Co., 2023 WL 7010001 (S.D.Fla.2023), deals with the trial court striking a portion of a general contractor’s expert opinion. The dispute involved a general contractor and a subcontractor and subcontractor’s performance bond surety. The general contractor refused to pay the subcontractor and the subcontractor’s performance bond surety, in furtherance of mitigating damages, funded the subcontractor’s continued performance. The surety then sued the general contractor to recover losses and the non-payment.

One of the expert opinions the general contractor offered was that the subcontractor’s performance bond surety acted as a “de factor subcontractor.” This opinion was based off the surety “requesting all payment for [the subcontractor], from [the surety’s] agents’ presence at onsite meetings on the project, and from its decisions mandating certain manpower and other resources to be applied to the project after [the subcontractor] breached. [The surety] exercised complete control over [the subcontractor] to such extent that [the surety] became a ‘de factor subcontractor.’” Berkley Ins. Co., 2023 WL at *8.

The trial court, however, was not buying this expert opinion. At all. “Remarkably, however, [the expert] has never before attempted to develop the theory he advances of a surety becoming a ‘de facto contractor.’ His ‘customized’ expertise was allegedly generated to advocate for the specific legal arguments of counsel but without any objectively verifiable basis….”  Berkley Ins. Co., supra, at *8.  The trial court further explained:

An expert must show how his experience leads to the conclusion reached and why that experience is a sufficient basis for the opinion. But in this Report, [the expert] claims that a surety may become a “de facto contractor” even though he admitted that, in his entire career, there had not been one time where he had experience evaluating a surety as being a “de facto contractor.” Furthermore, [the expert] states that he has never seen, known, or even heard about a “de facto contractor” before this case. And as we stated before, he has no experience acting as a surety in any meaningful way.

To admit this opinion under Rule 702 [of the Federal Rules of Evidence] we must find there to be some showing of how his experience led to or reliably supported his conclusions. While [the expert] conveyed that he reviews industry standards and articles “every day, it’s just a normal course of my … daily routine”, he cannot cite a single industry standard or article that he has seen in his entire career that discusses the “de facto contractor” theory. With no experience to point to and no industry recognition of the “de facto contractor” theory, there is no link between his experience and his opinion besides “I think it’s just something that is understood in the industry.” [The expert] failed to show how his experience may render a reliable opinion before the trier of fact and nothing in our review of this record can save him on this score.

***

So, in short, we have an “expert opinion” that effectively clothes [the general contractor’s] legal conclusions that will be presented in the case. The facts supporting that legal conclusion can be, and certainly will be, presented at trial through testimony of fact witnesses with personal knowledge. To bolster that testimony with an expert opinion, [the general contractor] must present a witness with experience as a surety (which [the expert] does not have) or with practical experience of a contractor who has faced that dilemma (which [the expert] admits he also does not have). So the Court on this record has zero basis to find, preliminarily or otherwise, that a reliable expert opinion can be forthcoming through this expert. As to this “de facto subcontractor” opinion, he is not an expert at all. Hence, his testimony in this regard must be excluded.

Berkley Ins. Co., supra, at *8-*9 (internal citations omitted).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE REQUIREMENT TO POST COLLATERAL UNDER GENERAL AGREEMENT OF INDEMNITY IS REAL

In prior postings, I have discussed the all-powerful General Agreement of Indemnity (click here and here).  This is the document a bond-principal executes to obtain bonds (e.g., performance and payment bonds).  Not only does the bond-principal execute this General Agreement of Indemnity, but typically, so do other indemnitors such as the company’s principals and their spouses, other related companies, etc.  The objective is that the surety has financial comfort that if a claim is made against the bond, there are avenues where it will get reimbursed and indemnified for any cost it incurs, or payment it makes, relative to that claim against the bond. When a surety issues bonds, the objective is that all losses it incurs gets reimbursed because the bonds are NOT insurance policies.

One of the powerful tools the surety can exercise in the General Agreement of Indemnity is to demand the bond-principal and other indemnitors to post collateral in an amount the surety deems sufficient to cover any losses it may incur.  This is a right in any General Agreement of Indemnity I have seen and is a right the surety can rightfully exercise.

A recent example is shown from the opinion in Philadelphia Indemnity Ins. Co. v. Quinco Electrical, Inc., 2022 WL 1230110 (M.D.Fla. 2022), which pertains to the surety’s motion for preliminary injunction.

An electrical subcontractor obtained bonds for a project in Orlando.  In obtaining these bonds, the electrical subcontractor executed a General Agreement of Indemnity that allowed the surety to require the bond-principal and indemnitors to post collateral to cover losses and potential losses the surety may incur.  The provision read as follows (and is similarly worded in many General Agreements of Indemnity):

Indemnitors agree to deposit immediately upon demand by Surety an amount equal to the greater of: (a) the amount of anyreserve established by Surety in its sole discretion to cover any actual or potential liability for any Loss or potential Loss for whichIndemnitors would be obliged to indemnify Surety hereunder; or (b) the amount of any Loss or potential Loss (including legal,professional, consulting, and expert fees and expenses) in relation to any claim or claims or other liabilities asserted against Surety as a result of issuing any Bond, as determined by the Surety in its sole discretion.

The general contractor declared the electrical subcontractor in default and made a claim against the subcontractor’s bond. The surety hired a consultant to monitor the subcontractor’s progress.  A few months later, the surety demanded for the bond-principal and indemnitors to submit $1.8 Million in collateral or relieve it from its obligations (which really means for the subcontractor to resolve the dispute with the general contractor that gives the surety a release.  Typically, this is not a valid option when the default and/or termination is contested).   Almost a year later, the general contractor notified the surety that the electrical subcontractor remains in default and owes its supplier significant money. The surety then notified its bond-principal and indemnitors that they were in default of the bond.  At this point, the surety demanded $600,000 in collateral.

The surety filed a lawsuit against the bond-principal and indemnitors and moved for a preliminary injunction to require them to post collateral in the amount of $600,000 and refrain from transferring or encumbering any assets until collateral was posted.

After a hearing on the surety’s motion for injunction, the court ordered the bond-principals and indemnitors to post collateral in the amount of $521,250.84.  The amount represented legal fees and consulting fees that had been incurred, and pending supplier claims including a portion of a claim paid to a supplier. (The order included other components regarding the transferring of assets until the collateral was posted.)

Here is the key because parties oftentimes want to dispute the surety’s right, despite that right existing in the General Agreement of Indemnity and this General Agreement of Indemnity CONTROLS.  Quinco Electrical, supra, at *3. “This obligation [to require collateral] applies ‘regardless of whether [The Principals or Indemnitors] dispute their liability for any Loss or potential Loss or assert any defenses to the validity or enforcement’ of the [General agreement of Indemnity].”  Id. at *2.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

 

 

 

 

 

PERFORMANCE BOND SURETY’S EQUITABLE SUBROGATION CLAIM AGAINST OWNER

There are circumstances where a performance bond surety will pursue a claim against an owner – such as a government owner—and assert an equitable subrogation claim.  A performance bond surety may assert an equitable subrogation claim to recover contract funds that are still in the government’s control after the contract is completed or to recover from the government when the government improperly disburses progress payments to the defaulted contractor (principal of the performance bond).   Capitol Indemnity Corp. v. U.S., 2020 WL 877687, n.7 (Fed.Cl. 2020).  As to the improper disbursement of progress payments, a performance bond surety is asserting a claim against the owner in this fashion when it has had to pay under the bond and believes certain rights of it were prejudiced based on improper payments by the owner — it would have had to pay less based on the contractors’ default had the owner not impermissibly paid the defaulted contractor.

[A]n equitable subrogation claim is based on the theory “that the triggering of a surety’s bond obligation gives rise to an implied assignment of rights by operation of law whereby the surety ‘is subrogated to the [principal obligor’s] property rights in the contract balance.’ ” “[A] legally enforceableduty can arise between the government and a surety if the surety notifies the government that its principal is in default of the bond agreement.” Thecourt in a case affirmed by the Federal Circuit has also recognized that notice to the government that the contractor “is in danger of defaulting under the bond” from other sources besides the surety may be adequate to trigger the assignment of rights to the surety.  Finally, a surety’s equitable subrogation rights can be triggered where the government “had knowledge of the default … and so informed the surety.”

Capitol Indemnity Corp., supra, at *7 (internal citations omitted).

An example of a performance bond surety asserting an equitable subrogation claim against the government can be found in Capitol Indemnity Corp.   Here, a contractor was hired to renovate a building and complete the renovation by September 30, 2015.    After numerous letters to the contractor including cure notices relating to non-conforming work, on December 30, 2015, the government notified the contractor’s performance bond surety that the contractor’s work was not complete and the surety should be receiving payment bond claims from unpaid subcontractors.  A few days later, the government suspended the contract and copied the surety.   The surety claims that after this date, the government impermissibly made payment to the contractor even though the surety requested any such payment to the contractor be in the form of joint checks to the contractor and corresponding subcontractor.  A couple of months later, in March 2016, the government declared the contractor in default.  The surety entered into a takeover agreement with the government to complete the defaulted contractor’s work, which reserved certain rights of the surety to pursue claims against the government.

Around the time the takeover work was complete, the surety sued the government.  One of the arguments the surety raised was equitable subrogation as to impermissible payments the government made to the contractor.  Stated differently, the surety claimed that the government abused its discretion (and prejudiced the surety) in making payment to the contractor when it knew the contractor was in default.  The government moved to dismiss the surety’s equitable subrogation claim.

Initially, as to a jurisdictional argument, the US Court of Federal Claims held that the surety can sue the government in equitable subrogation without having to first raise this issue to the contracting officer through submitting a claim under the Contract Disputes Act.

Next, the US Court of Federal Claims found that the alleged facts raised by the surety as to payment to the contractor shortly before the contractor was defaulted was enough to trigger a surety’s equitable subrogation claim against the government.  The surety raised facts to support that its equitable subrogation rights were triggered on December 30, 2015 when (i) the government notified the surety that the contractor’s work was not complete and the surety should expect to receive payment bond claims, (ii) the government then suspended the contractor’s performance a few days later, (iii) the surety requested that the government issue joint checks to the contractor and unpaid subcontractors, and (iv) the government refused to issue joint checks and paid the contractor directly only to default the contractor a couple of months later.   The direct payment to the contractor was an impermissible payment, and through equitable subrogation, the government may owe the surety the amount of that payment irrespective of the fact that the government already paid that amount to the defaulted contractor.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DRAFTING THE BOND FORM, PARTICULARLY THE PERFORMANCE BOND FORM


Oftentimes, when it comes to payment and performance bonds (in particular), the bond forms are drafted by the obligee.  For example, an owner (as the obligee) may draft the bond forms that it wants its general contractor’s surety to execute.  And, a general contractor (as the obligee) may draft the bond forms that it wants its subcontractors’ sureties to execute.   As an obligee, it is always beneficial to draft the bond form (particularly the performance bond) that you want the surety to execute.  The bond is to benefit you—the obligee—so having a hand in creating conditions to trigger the application of the bond is important, specifically when it comes to triggering a performance bond upon the bond-principal’s default.

 

What if the surety executes a bond form prepared by the obligee and there is an ambiguity in the bond?  Should the ambiguity be interpreted against the obligee as the drafter of the bond?

 

This issue was addressed by the Fourth District Court of Appeal in The School Bd. Of Broward County v. Great American Ins. Co., 807 So.2d 750 (Fla. 4th DCA 2002) where the School Board owner prepared the performance bond form.  The surety argued there was an ambiguity with the bond form and wanted the ambiguity to be interpreted against the School Board as the drafter of the bond.  The court rejected this argument explaining:

 

Florida’s policy is to construe any ambiguity in a bond in favor of granting the broadest possible coverage to those intended to be benefitted by protection of the bond [e.g., the obligee]. This policy recognizes that the purpose of a bond is to protect a party to a contract; the burden is on the surety, who is in the business, to include the appropriate language in its bonds if it seeks to narrow its obligations after default.

The School Board of Broward County, 807 So.2d at 752 (internal citations and quotations omitted).

To reiterate, it is always beneficial as the obligee to prepare the bond forms (particularly the performance bond) that you want the surety to execute since the bond is designed to benefit you. Work with counsel to ensure the bond form provides you the broadest or best coverage based on the anticipated risks.    

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DON’T MESS WITH THE GENERAL AGREEMENT OF INDEMNITY


I have previously posted articles about the all mighty General Agreement of Indemnity (“Agreement of Indemnity”) that a surety requires a contractor bond-principal and designated guarantors to execute before issuing payment and performance bonds to the contractor. In cases forming the basis of the articles, the surety demands rights under the Agreement of Indemnity such as the right for collateral security to protect the surety from anticipated or pending claims and the contractor bond-principal refuses. In these cases, the surety files a lawsuit and moves for an injunction which, among other things, requires the principal to post the very collateral security it refused to post to begin with. As reflected in these cases, the surety gets the injunction granted because the Agreement of Indemnity is designed to protect the surety’s interests. In other words, don’t mess with the Agreement of Indemnity because the surety will typically get the recourse it pursues.

 

Recently, another opinion came out further supporting the rights of a surety under the Agreement of Indemnity and why it is beneficial to figure out an avenue to work with the surety instead of against it. In this case, Travelers Casualty and Surety Co. of America v. Design Build Engineers and Contractors Corp., 2014 WL 7274803 (M.D.Fla. 2014), the contractor bond-principal was working on two public projects. On one project, a dispute with a subcontractor resulted in a claim that the surety paid plus substantial attorney’s fees awarded to the subcontractor by the court. Although the contractor reimbursed its surety for the principal amount of the claim, it refused to reimburse the surety for the substantial attorneys’ fees awarded to the subcontractor. And, on the other project, the contractor was terminated resulting in pending performance bond and payment bond claims against the surety.

 

The contractor, in furtherance of trying to shield major property and assets, did some creative asset transfers forming holding companies, etc. This did not work.  The surety filed a lawsuit against the contractor and guarantors under the Agreement of Indemnity and moved for a preliminary injunction to require the contractor to post collateral security and to prevent the contractor from disposing of assets. Guess what? The surety prevailed on its motion for an injunction and the Middle District Court ordered that the contractor post the requested collateral that included properties the contractor tried to shield and prevented the contractor and certain holding companies it formed from disposing or encumbering of assets (inclusive of the real property is was ordered to post as collateral).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SURETY BONDING – THE NUTS & BOLTS


Surety bonding is necessary in construction, particularly on federal and Florida public projects where the contractor is required to furnish a payment and performance bond.  Even certain owners of large-scale private projects want their contractor to obtain a payment and performance bond.  Understanding the nuts and bolts of surety bonding is valuable for the contractor that wants to increase job opportunities and/or increase their bonding capacity.

 

 

There are three main parties to the surety bond:

 

1. The surety– the entity (typically, a division of an insurance company) that issues the payment or performance bond for the contract price; the surety guarantees obligations on behalf of its principal, whether it is the performance of the contract (performance bond) or the payment to those entities working under the contractor providing labor, services, or materials (payment bond)

 

2. The principal – the entity (contractor) that procured the bond from the surety and who the surety is issuing the bond on behalf of; the principal along with personal and corporate guarantors will execute a General Agreement of Indemnity before the bond is issued outlining the rights and remedies of the principal/guarantors and the surety

 

3. The obligee – the entity (or entities) that can make a claim against the bond and who the bond is ultimately designed to benefit

 

Not every contactor can get a payment and performance bond.  This means that not every contractor can perform public work that requires a bid bond to be furnished with the bid/proposal and then a payment and performance bond upon the award of the contract.  This is because sureties undertake rigorous underwriting to best assess their risk before issuing bonds. And, many contractors, even if bonds are issued, will have a bonding capacity meaning the surety will not issue an unlimited dollar amount for the bond(s) issued or will not issue an unlimited number of project bonds at the same time. Rather, it will issue a bond or bonds totaling the bonding capacity of the contractor.

 

To obtain a bond, a contractor will go to a surety bond agent/broker, commonly referred to as the producer.  The producer represents select sureties.  Certain sureties cater to certain market niches or contractors and the producer tries to fit the contractor with the surety that best fits the needs, strengths, and qualifications of the contractor. The producer will work with the contractor to fill out required forms and review and collect the material and information that will be needed by the surety in the underwriting process. As a contractor, it is important to develop a strong relationship with a producer that understands your construction business and capabilities and can assist you with obtaining bonding capacity.

 


In the underwriting process, the surety will want to determine the financial strength, creditworthiness, and condition of the contractor by analyzing extensive financial documentation along with the contractor’s operational ability to perform a contract based on the contractor’s history, equipment, personnel, etc.  Underwriting needs to obtain and assess financial and operational material to best assess the surety’s risk (based on the surety’s appetite or market) because if the surety has to pay out a claim on the bond it will absolutely be looking to recoup the costs it incurs from the bond principal as well as the guarantors that executed the General Agreement of Indemnity.  Among other things, the surety will run a credit check for the principal and likely the owners/guarantors; will analyze balance sheets, income statements, and other financial information to understand the contractor’s cash flow, working capital, net worth, and profitability history and forecasts; will want to know of judgments and lawsuits; will likely contact references; and will want to specifically understand past projects completed and current projects underway, including the project in which the bond is being requested, from an estimating and accounting standpoint, personnel and management standpoint, insurance standpoint, and possibly a scheduling standpoint.  The surety will do its homework because the very last thing a surety wants to do is pay a claim or expose itself to massive liability with a bond claim from a contractor that failed to pay its subcontractors or abandoned a job without any true recourse to recoup money expended.  The surety will consider the personal and corporate guarantors it requires from a contractual indemnity standpoint per the General Agreement of Indemnity and may require cash collateral or property collateral to be pledged for underwriting approval.   Again, developing the relationship with the producer that understands your business is crucial as the producer will understand the underwriting process and facilitate the transmission of information and material between the contractor and the surety.

 

 

The surety charges a premium for the issuance of the bond.  Payment and performance bonds are often single premium bonds.  Depending on the producer you ask, the premiums typically range from 1-3% of the bond amount.   Naturally, there are contractors that will have to pay in excess of 3% of the bond amount based on the associated credit risk with issuing the bond.

 

Once underwriting runs its course and the contractor is approved for the requested bonds, the producer typically signs the bonds on behalf of the surety.  The producer is given a power-of-attorney to sign bonds as an attorney-in-fact on behalf of the surety.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE ALL MIGHTY GENERAL AGREEMENT OF INDEMNITY WITH THE SURETY


Sureties do not issue bonds (e.g., payment or performance bonds) unless the principal and the principal’s personal guarantors execute a General Agreement of Indemnity (“Indemnity Agreement”).  The Indemnity Agreement routinely requires that the principal / guarantors: (1) defend and indemnify the surety for all losses, liability, claims, attorney’s fees, and expenses that the surety may incur and (2) post collateral security into a reserve account set up by the surety to cover any claim on the bond; the surety may seek an injunction to compel such collateral if the principal / guarantors refuse.  Yes, these are powerful provisions in favor of the surety if a claim is asserted against the principal’s bond (especially a performance bond claim) or if the surety, to offset liability or exposure, pays a claimant on behalf of the principal.  The leverage lies with the surety with respect to the provisions in the Indemnity Agreement and the worst thing a bond principal can do when a claim is asserted against the bond is to outright refuse to work with and cooperate with the surety (based on the powerful provisions in the Indemnity Agreement).

 

 

The opinion in Developers Surety and Indemnity Co. v. Hansel Innovations, Inc., 2014 WL 2968138 (M.D.Fla. 2014), exemplifies what can happen if a bond principal refuses to cooperate with a surety even if the principal has potentially meritorious arguments.  In this case, a surety issued a performance bond to a fire protection subcontractor.  During the course of construction (and, arguably due to the general contractor’s nonpayment), the subcontractor experienced cash flow problems.  The general contractor expressed concerns as to the subcontractor’s financial wherewithal to complete the contract work and made demand on the surety.  The subcontractor requested financial assistance from its performance bond surety and the surety agreed to pay the subcontractor and its vendors in excess of $100,000 provided the subcontractor execute a separate financing and collateral agreement (as the surety expected to recoup its “loan”).  Subsequently, the general contractor advised the surety and subcontractor of performance issues with the subcontractor’s work.  The subcontractor, however, refused to complete its work and address the performance issues unless the surety continued to fund the subcontractor’s work, released the guarantors from personal liability, and pursued claims against the general contractor.  Based on the subcontractor’s stance, the surety retained another subcontractor to complete the work and incurred additional costs.  The surety filed a lawsuit to, among other rights afforded under the Indemnity Agreement, require the subcontractor and guarantors to post $200,000 in collateral security into a reserve account.  The subcontractor and guarantor failed to post collateral upon demand.

 

 

The surety, as it customarily will do, moved for a preliminary injunction in accordance with the Indemnity Agreement for the court to order the subcontractor and guarantors to post collateral.   One of the requirements for a court to order a preliminary injunction is for the surety to establish that it is substantially likely to succeed on the merits.  This is not a challenging hurdle for a surety given the powerful provisions in the Indemnity Agreement. (Please see the following articles for more information on a surety’s right to demand collateral security and the requirements for a preliminary injunction in federal court: https://floridaconstru.wpengine.com/a-suretys-right-to-demand-collateral-security/ and https://floridaconstru.wpengine.com/a-suretys-right-to-demand-collateral-security/.)

 

 

The subcontractor argued that bad faith or unclean hands, evidenced by an improper motive, extinguished the surety’s substantial likelihood that it would succeed on its claim.  The subcontractor argued this because it did not want to post collateral.  In support of bad faith, the subcontractor contended that when the general contractor raised performance issues the subcontractor was 99% done with its work with the remaining work simply commissioning the fire sprinkler system and completing as-built drawings.  It further argued that the general contractor placed it in a dire financial position because the general contractor did not pay it for over one year and did not pay it for change order work that was performed at the general contractor’s direction.  (Not an uncommon subcontractor argument!)  The subcontractor also stated that it only signed the financing and collateral agreement because the surety assured it that the surety would assist the subcontractor in collection efforts against the general contractor if the subcontractor signed the agreement and continued with the work.  Then, the surety discontinued funding the subcontractor at the eleventh hour to help the subcontractor complete the work while contemporaneously failing to assist the subcontractor in collecting any money from the general contractor.  The Magistrate, though, was not persuaded by the subcontractor’s bad faith argument taking the position that it cannot be bad faith for the subcontractor to be induced into completing its work on a project it was hired to complete.

 

 

The subcontractor may have very strong arguments that it was truly placed in a cash flow crunch because the general contractor refused to pay for contract work plus additional work.  Thus, the subcontractor was forced to finance a job that it was never in a financial position to finance.  Then, when it agreed to complete its work with the surety’s assistance, it did so with the understanding that the surety would assist the subcontractor in recovering monies that the subcontractor should have been paid all along for contract and change order work that would also be used to reimburse the surety.  But, as shown in this case, truly establishing bad faith is very, very difficult and should not be sugarcoated with the sentiment that the provisions in the Indemnity Agreement do not have any teeth, because they do!

 

 

Keep in mind that a performance bond guarantees performance under a contract.  Once a bond is furnished, it is rarely advisable to abandon a job or refuse to perform because it puts the surety in a compromising position where it will likely need to complete the subcontractor’s performance in order to mitigate its exposure and liability.  Here, the subcontractor’s surety was willing to finance the subcontractor’s work until the subcontractor was virtually complete.  All the subcontractor had to do was complete its work when it was 99% complete and work with and cooperate with the surety since the best course of action in the long run may have been for these entities to work together to recover monies that the general contractor owed the subcontractor and/or figure out how the subcontractor would reimburse the surety.  However, based on what the surety may have construed as an obstinate position by the subcontractor, the surety incurred additional expenses and elected to pursue its options against the subcontractor and guarantors under the all mighty Indemnity Agreement.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

PRESERVING PERFORMANCE BOND CLAIMS

Performance bonds can be a valuable source of protection to owners that want their general contractors to provide a performance bond and, likewise, to general contractors that want certain subcontractors to provide a performance bond. The performance bond is designed to benefit the obligee in the event the contractor that issues the bond defaults under its contractual obligations. It is absolutely crucial that parties take the proper steps under the terms of the performance bonds to preserve their rights and arguments under the bond. To do this requires an unequivocal formal default of the contractor that issued the bond and that the party will be looking solely to the surety to complete the defaulted party’s contractual obligations. Otherwise, a court will rule in favor of the surety finding that the obligee of the bond did not comply with conditions precedent to preserve the performance bond claim and/or breached the terms of the bond by not allowing the surety to investigate and complete performance. This is exactly the situation in two federal district court summary judgment opinions relying on Florida law: North American Specialty Insurance Co. v. Ames Corp., 2010 WL 1027866 (S.D.Fla. 2010) and CC-Aventura, Inc. v. Weitz Co., 2008 WL 2699577 (S.D.Fla. 2008). Both of these cases illustrate the importance of formally and unequivocally declaring the party that issued the performance bond in default irrespective of whether the issue arises pre-completion or post-completion. Both cases also pertain to a subcontractor that provided a performance bond identifying the general contractor as the obligee (or beneficiary) of the bond.

 

I. North American Specialty Ins. Co. v. Ames Corp. (Pre-Completion)

 
In this case, a general contractor hired a roofer for a federal project. The roofer provided performance bonds identifying the general contractor as the obligee. The bonds provided as follows (which is common language in performance bonds):

 

“Whenever Principal shall be, and be declared by Obligee to be in default under the subcontract, the Obligee having performed Obligee’s obligations thereunder:

(1) Surety may promptly remedy the default …;

(2) Obligee after reasonable notice to Surety may, or Surety upon demand of Obligee may arrange for the performance of Principal’s obligation under the subcontract …;

(3) … If the Surety arranges completion or remedies the default, that portion of the balance of the subcontract price as may be required to complete the subcontract or remedy the default and to reimburse the Surety for its outlays shall be paid to the Surety at the times and in the manner as said sums would have been payable to Principal had there been no default under the subcontract.”

Ames Corp., 2010 WL at *1.

 

During construction, the general contractor notified the surety that the roofer was refusing to perform and that the general contractor will look to the surety for costs incurred above the roofer’s subcontract amount. A follow-up notice advised the surety that expenses were being incurred to finish the roofer’s subcontract amount and no one from the surety visited the jobsite. The surety then commenced an investigation while advising the general contractor that the “prior letters were not accompanied by supporting documentation and/or prior notice to the principal of default and/or potential default.” Ames Corp., 2010 WL at *3. A meeting was coordinated with the owner, the general contractor, the roofer, and the roofer’s surety at which time the surety represented it would need up to 5 months to assume responsibility and take action. After this meeting, the general contractor sent another letter to the surety and the roofer explaining that the roofing subcontract was not terminated or declared in default and that the surety needed to appreciate the short time allotted for completing the roofer’s contract. The surety responded that because the general contractor had not declared the roofer in default, the surety had no obligation to act under the performance bonds.

 

Notwithstanding the general contractor never formally declaring the subcontractor in default, it supplemented the roofer’s scope of work. Both the roofer and the surety objected; the surety even advised that such efforts would be a material breach of the bonds. However, due to leaks with the roofing system (the manufacturer of the roofing system inspected the roof and found that there were installation defects), the general contractor incurred substantial costs to complete the roofer’s scope of work which exceeded the roofer’s subcontract balance. In addition, the general contractor incurred delay damages associated with completing the roofer’s scope of work.

 

The surety initiated this lawsuit based on the monetary demands from the general contractor. The surety moved for summary judgment based on the argument that a condition precedent to the bonds obligations was never triggered, that being that the general contractor never declared the roofer in default. The surety also argued that the general contractor breached the bonds by not allowing the surety the right to remedy any default and by not making available to the surety the unpaid subcontract balance in connection with the surety remedying the default.

 

Relying on Florida law, the Southern District found:

 

[A] surety’s liability on a bond is determined strictly from the terms and conditions of the bond agreement. The purpose of a performance bond is to guarantee completion of the contract upon default by the contractor.

***

A declaration of default sufficient to invoke the surety’s obligations under the bond must be made in clear, direct, and unequivocal language. The declaration must inform the surety that the principal has committed a material breach or series of material breaches of the subcontract, that the obligee regards the subcontract as terminated, and that the surety must immediately commence performing under the terms of the bond.

Ames Corp., 2010 WL at *6 (internal citations and quotations omitted).

 

Based on this law, the Southern District held that none of the letters the general contractor sent to the surety defaulted the roofer in clear, direct, and unequivocal language. While the letters urged the surety to become involved and threatened default, they did not formally and unequivocally default the roofer. Accordingly, the court granted summary judgment in favor of the surety.

 

Furthermore, the Southern District agreed with the surety that the general contractor breached the bond by completing / supplementing the subcontract without giving the surety the opportunity to remedy any default under the subcontract. As the court explained: “‘[O]nce Ames/Dawson [general contractor] engaged in the supplementation of work without allowing NAS [surety] to perform, its conduct constituted a material breach that voided the bond.” Ames Corp., 2010 WL at *9.

 

II. CC-Aventura, Inc. v. Weitz Co. (Post-Completion)

 

In this case, the general contractor was hired to construct a senior living facility. The general contractor hired a painter with a subcontract that contained an indemnification provision and a provision that required the painter to correct defective work. The painter provided a performance bond identifying the general contractor as the obligee.

 


After completion of the project, the owner sued the general contractor for water intrusion and damage. The general contractor sued subcontractors including its painting subcontractor. The general contractor also asserted a claim against the painting subcontractor’s performance bond surety for breach of the bond. The surety moved for summary judgment arguing that the bond obligations were never triggered because the general contractor never formally declared the painting subcontractor in default.

 

The general contractor argued that it did provide default notices when it transmitted the owner’s expert and its expert reports regarding the paint that the painter applied. In the notices, the general contractor demanded that the surety correct the defects and that the painter’s failure to take corrective action will be a default under the subcontract.

 

The surety took the position that these types of notices were insufficient. The Southern District of Florida agreed and granted summary judgment in favor of the surety finding:

 

“Both of Weitz’s [general contractor] letters do state that Delta [subcontractor] is in ‘default’ of its Subcontract-and had Weitz maintained that position and indicated that Weitz now looked to American Casualty [surety] alone, both of its letters could reasonably be interpreted as declarations of default sufficient to trigger American Casualty’s liability on the Bond. However, in its December 30, 2005 letter Weitz also advised Delta to ‘please accept this letter as The Weitz Company’s final written demand that Delta Painting or its Surety take appropriate corrective action’….In its April 11, 2006 letter, Weitz reiterated that it had made ‘numerous demands upon both Delta and American to correct [the painting] deficiency.’ Weitz then stated its intention to perform the corrective work itself and announced that ‘Weitz will seek such costs and all other damages from Delta and American.’ If Weitz wanted to trigger American Casualty’s obligations on the Bond, it would have had to clearly and unambiguously notify American Casualty that it now looked to it to complete Subcontract obligations, in accordance with the Bond.”

CC-Aventura, 2008 WL at *4.

 

 

As illustrated above, there are certainly procedural hurdles that are required to take place in order to properly default a contractor that provided a performance bond. Not doing so can be fatal to the performance bond claim. Default is always viewed as a last resort because parties do not want to be in material breach for incorrectly defaulting or terminating a party. However, by not defaulting a party, the performance bond’s obligations are not triggered. Due to these hurdles, general contractors are now obtaining subguard (subcontractor default insurance) instead of requiring individual subcontractors to provide performance bonds. This allows the general contractor to be more involved in the process since it is the one obtaining subguard and it eliminates subcontractors from having to obtain the bond (which could be problematic for certain subcontractors).

 

For more on performance bonds, please visit: https://floridaconstru.wpengine.com/statute-of-limitations-on-performance-bond-claims/

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.