PERFORMANCE BOND SURETY’S EQUITABLE SUBROGATION CLAIM AGAINST OWNER

There are circumstances where a performance bond surety will pursue a claim against an owner – such as a government owner—and assert an equitable subrogation claim.  A performance bond surety may assert an equitable subrogation claim to recover contract funds that are still in the government’s control after the contract is completed or to recover from the government when the government improperly disburses progress payments to the defaulted contractor (principal of the performance bond).   Capitol Indemnity Corp. v. U.S., 2020 WL 877687, n.7 (Fed.Cl. 2020).  As to the improper disbursement of progress payments, a performance bond surety is asserting a claim against the owner in this fashion when it has had to pay under the bond and believes certain rights of it were prejudiced based on improper payments by the owner — it would have had to pay less based on the contractors’ default had the owner not impermissibly paid the defaulted contractor.

[A]n equitable subrogation claim is based on the theory “that the triggering of a surety’s bond obligation gives rise to an implied assignment of rights by operation of law whereby the surety ‘is subrogated to the [principal obligor’s] property rights in the contract balance.’ ” “[A] legally enforceableduty can arise between the government and a surety if the surety notifies the government that its principal is in default of the bond agreement.” Thecourt in a case affirmed by the Federal Circuit has also recognized that notice to the government that the contractor “is in danger of defaulting under the bond” from other sources besides the surety may be adequate to trigger the assignment of rights to the surety.  Finally, a surety’s equitable subrogation rights can be triggered where the government “had knowledge of the default … and so informed the surety.”

Capitol Indemnity Corp., supra, at *7 (internal citations omitted).

An example of a performance bond surety asserting an equitable subrogation claim against the government can be found in Capitol Indemnity Corp.   Here, a contractor was hired to renovate a building and complete the renovation by September 30, 2015.    After numerous letters to the contractor including cure notices relating to non-conforming work, on December 30, 2015, the government notified the contractor’s performance bond surety that the contractor’s work was not complete and the surety should be receiving payment bond claims from unpaid subcontractors.  A few days later, the government suspended the contract and copied the surety.   The surety claims that after this date, the government impermissibly made payment to the contractor even though the surety requested any such payment to the contractor be in the form of joint checks to the contractor and corresponding subcontractor.  A couple of months later, in March 2016, the government declared the contractor in default.  The surety entered into a takeover agreement with the government to complete the defaulted contractor’s work, which reserved certain rights of the surety to pursue claims against the government.

Around the time the takeover work was complete, the surety sued the government.  One of the arguments the surety raised was equitable subrogation as to impermissible payments the government made to the contractor.  Stated differently, the surety claimed that the government abused its discretion (and prejudiced the surety) in making payment to the contractor when it knew the contractor was in default.  The government moved to dismiss the surety’s equitable subrogation claim.

Initially, as to a jurisdictional argument, the US Court of Federal Claims held that the surety can sue the government in equitable subrogation without having to first raise this issue to the contracting officer through submitting a claim under the Contract Disputes Act.

Next, the US Court of Federal Claims found that the alleged facts raised by the surety as to payment to the contractor shortly before the contractor was defaulted was enough to trigger a surety’s equitable subrogation claim against the government.  The surety raised facts to support that its equitable subrogation rights were triggered on December 30, 2015 when (i) the government notified the surety that the contractor’s work was not complete and the surety should expect to receive payment bond claims, (ii) the government then suspended the contractor’s performance a few days later, (iii) the surety requested that the government issue joint checks to the contractor and unpaid subcontractors, and (iv) the government refused to issue joint checks and paid the contractor directly only to default the contractor a couple of months later.   The direct payment to the contractor was an impermissible payment, and through equitable subrogation, the government may owe the surety the amount of that payment irrespective of the fact that the government already paid that amount to the defaulted contractor.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

PERFORMANCE BOND SURETY TAKEOVER – USING TERMINATED CONTRACTOR TO COMPLETE THE WORK

When a contractor is defaulted under a performance bond, can its surety hire the same defaulted contractor to complete the work?  Stated differently, can the performance bond surety engage its defaulted bond-principal in taking over and completing the same work the contractor was defaulted under?   The answer is “yes” if you are dealing with a standard form AIA A312 performance bond (and other bond forms that contain analogous language), as demonstrated by the recent decision in Seawatch at Marathon Condominium Association, Inc. v. The Guarantee Company of North America, 2019 WL 4850194 (Fla. 3d DCA 2019).

In this case, a condominium association hired a contractor in a multi-million dollar contract to renovate condominium buildings.  The contractor provided the association, as the obligee, a performance bond written on an AIA A312 performance bond form.  During construction, the association declared the contractor in default and terminated the contractor. In doing so, the association demanded that the performance bond surety make an election under paragraph 4 of the AIA A312 bond form that gave the surety the following options:

4.1 Arrange for the CONTRACTOR, with consent of the OWNER, to perform and complete the Contract; or

4.2 Undertake to perform and complete the Contract itself, through its agents or through independent contractors; or

4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the OWNER for a contract for performance and completion of the Contract, arrange for a contract to be prepared for execution by the OWNER and the contractor selected with the OWNER’S concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the Bonds Issued on the Contract, and pay to the OWNER the amount of damages as described in paragraph 6 in excess of the Balance of the Contract Price incurred by the OWNER resulting from the CONTRACTOR Default; or

4.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances;

4.4.1 After investigation, determine the amount for which it may be liable to the OWNER and, as soon as practicable after the amount is determined, tender payment therefore to the OWNER; or

4.4.2 Deny liability in whole or in part and notify the OWNER citing reasons therefore.

Seawatch at Marathon Condo. Ass’n, 2019 WL at *1-2.

The surety elected the option under section 4.2, underlined and bolded above.  The surety wanted to complete the construction contract and provided the association with a surety takeover agreement, i.e., an agreement where the surety takes over the completion of the defaulted / terminated contractor’s contract.   The takeover agreement was predicated on the terminated contractor continuing to serve as the contractor to finish the contract.

The association rejected the takeover agreement largely because it was adamant that the terminated contractor cannot serve as the completion contractor under the takeover agreement.  The association also argued that the surety could not properly elect section 4.2 because it was not a licensed contractor and needed to be a licensed contractor in order to undertake the completion of the defaulted contract.  Because an agreement could not be reached, the association filed a lawsuit for declaratory relief on these issues seeking judicial intervention as to its rights under the performance bond.

A. The Performance Bond Surety Can Use the Defaulted Contractor to Complete the Work

The trial court, as affirmed on appeal, held that the surety was well within its rights under section 4.2 of the bond to complete the contract with the defaulted contractor (bond-principal).  Section 4.2 places NO restrictions on the surety in using the defaulted contractor or any other contractor, for that matter.   As noted by the appellate court:

Finally, “[i]t is common practice for a surety undertaking to complete the project itself to hire the original contractor, as [Guarantee] elected to do here.”  “By completing the project itself, the surety obtains greater control than it would have had if it elected to require the obligee to complete, because the surety can select the completing contractor or consultants to finish the project as well as control the costs of completion.”

Seawatch at Marathon Condo. Ass’n, 2019 WL at *4 (internal quotations omitted).

B. The Performance Bond Surety Does Not Need to be a Licensed Contractor to Enter into Takeover Agreement

The appellate court summarily rejected the argument by the association that the surety needed to be a licensed contractor to enter into a takeover agreement and undertake the completion of the defaulted contract.  Since the surety is not actually performing the completion, the court rejected this outright which would prohibit the surety from ever exercising rights under section 4.2 unless it was a licensed contractor.

One thing to consider after reading the outcome of the case is that there is nothing to prevent the obligee of a bond from modifying a standard form bond form, or my preference, creating its own manuscript performance bond form.  Creating your own performance bond form gives you more flexibility regarding rights to trigger a surety’s obligations under the bond and the recourse under the bond.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.