RELEASE OF “UNKNOWN” CLAIM DOES NOT BAR RELEASE OF “UNACCRUED” CLAIM: FAIR OR UNFAIR?

A general release of “unknown” claims through the effective date of the release does NOT bar “unaccrued” claims.   This is especially important when it comes to fraud claims where the facts giving rise to the fraud may have occurred prior to the effective date in the release, but a party did  not learn of the fraud until well after the effective date in the release.  A recent opinion maintained that a general release that bars unknown claims does NOT mean a fraud claim will be barred since the last element to prove a fraud had not occurred, and thus, the fraud claim had not accrued until after the effective date in the release.  See Falsetto v. Liss, Fla. L. Weekly D1340D (Fla. 3d DCA 2019) (“The 2014 [Settlement] Agreement’s plain language released the parties only from “known or unknown” claims, not future or unaccrued claims. Because there is a genuine issue of material fact as to whether the fraud claim had accrued — that is, whether Falsetto [party to Settlement Agreement] knew or through the exercise of due diligence should have known about the alleged fraud at the time the 2014 Agreement was executed — the trial court erred in granting summary judgment on those fraud claims.”).  

 

Fair or unfair?  In certain contexts, perhaps fair — such as when the facts giving rise to the fraud took place after the effective date of the release.   In other contexts, perhaps unfair — such as when the facts giving rise to the fraud occurred prior to the effective date in the release but were unknown.  

 

What are your thoughts?    However, modifying a release to now include “unaccrued” claims may not be the answer as this could have broad implications relating to future claims, which a party may be cautious about releasing in light of current or future relations between the parties.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: DON’T NEGLECT CONDITIONS PRECEDENT TO PAYMENT IN YOUR CONTRACT

imagesThere is a good chance your contract contains conditions precedent to payment.  Such conditions precedent to payment include waivers and releases of lien (and, perhaps, claims) and contractually required warranties.  Make sure to comply with conditions precedent to payment!

 

In a case where a subcontractor sued a payment bond surety, the court held the subcontractor’s lawsuit was premature because the subcontractor did not comply with a condition precedent to payment, that being the submission of a release in satisfactory form.  Until such condition precedent was satisfied, payment was not due and owing the subcontractor.  

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

RELEASES ON FEDERAL PROJECTS — MAYBE THE RELEASE IS NOT A FINAL RELEASE

imagesExecuting partial releases and a final release in consideration of payment are routine on construction projects.  Counsel will correctly tell you not to sign a release if you don’t intend to release all of your claims through the date of the release.  Counsel will also tell you to be sure to exempt those claims from a release that you do not intend on releasing.  The reason for this is that if you sign a release and then seek damages or costs pre-dating the release, the party you gave the release too will waive it in front of your face and say “tough luck; you released these claims and costs!” 

 

However, the opinion in H.J. Lyness Construction, Inc. v.  U.S., 120 Fed.cl. 1 (Fed.Cl. 2015) gives those contractors (or subcontractors), particularly federal government contractors, that sign a release and do not exempt certain claims or costs from the release some hope that not all is lost.  In this case, the federal government terminated a contractor for convenience.  After the termination for convenience, the contractor submitted a release and was paid in consideration for that release.  The contractor did not exempt or carve out any claims or costs from that release even though the release allowed the contractor to do so.    In other words, the release did not carve out any termination for convenience settlement costs that the contractor would be entitled to.  Notwithstanding, the government and contractor continued to discuss termination for convenience settlement costs and when an agreement could not be reached, the contractor filed suit.

 

The government moved for summary judgment that the contractor released the government for termination for convenience settlement costs because the contractor executed the unambiguous release after the termination for convenience.  The contractor countered that the release did not apply to termination for convenience settlement costs and, to show this, the government continued to entertain discussions regarding these costs after it received the release the government is arguing under.  Furthermore, the contractor argued that it timely and properly submitted its settlement costs in accordance with F.A.R. 52.249-2(e) that provides:

 

(e) After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer. The Contractor shall submit the proposal promptly, but no later than 1 year from the effective date of termination, unless extended in writing by the Contracting Officer upon written request of the Contractor within this 1–year period. However, if the Contracting Officer determines that the facts justify it, a termination settlement proposal may be received and acted on after 1 year or any extension. If the Contractor fails to submit the proposal within the time allowed, the Contracting Officer may determine, on the basis of information available, the amount, if any, due the Contractor because of the termination and shall pay the amount determined.

 

Based on these facts and circumstances, the contractor took the position that the  government never intended the release the contractor furnished post-termination for convenience to operate as a final release and release of its termination for convenience costs.  The Court of Federal Claims sided with the contractor:

 

The Court finds that through the affidavit provided by Mr. Lyness [contractor’s representative], the parties’ actions and course of conduct in this case creates a genuine issue of material fact regarding whether the release constituted a full and final release of claims given in exchange for a final payment, or was simply a routine payment application form that was used with respect to all applications for partial payments requested by HJL [contractor].

H.J. Lyness Construction, supra.

 

Now, why is this case helpful?  Because it goes directly to the argument on federal projects that even if a contractor executed an unambiguous release and does not exempt or carve out any claims, there may be an argument that the conduct of the parties reflects that the parties did not intend the release to operate as a final release of all claims.  In H.J. Lyness the argument was that the release was not intended to bar termination for convenience settlement costs even though the release was executed months after the termination for convenience.

 

Regardless of the holding in H.J. Lyness, it is important for contractors to read what they sign and be cognizant of those claims and costs they do not want to release.  This includes executing a release without properly exempting termination for convenience settlement costs if the contractor does not intend its release to be a final release of all claims.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

BE CAREFUL AND APPRECIATE THE RISK WHEN EXECUTING A RELEASE IN ADVANCE OF AN EVENT OR SITUATION

imagesThe Florida Supreme Court in a non-construction case recently issued an opinion regarding the scope of a release.  Parties expecting releases (“releasee”) need to ensure that the release they are giving others to execute (“releaser”) clearly and unambiguously reflects the scope of the release they are seeking.  Regardless of the reasoning for getting a release, the release will not serve the releasee’s purpose if it is ambiguous. 

 

In Eric Sanislo v. Give Kids the World, Inc., 2015 WL 569119 (Fla. 2015), the Florida Supreme Court answered the question whether a release that does not contain express language of the releaser releasing the releasee for negligence or negligent acts was enforceable to actually release the releasee for negligence claims. 

 

This case involved a non-profit company that organizes vacations for sick children and their families. In advance of the vacation participants need to execute a release in favor of the non-profit company that reads:

 

I/we hereby release Give Kids the World, Inc. [releasee] and all of its agents, officers, directors, servants, and employees from any liability whatsoever in connection with the preparation, execution, and fulfillment of said wish, on behalf of ourselves, the above named wish child and all other participants. The scope of this release shall include, but not be limited to, damages or losses or injuries encountered in connection with transportation, food, lodging, medical concerns (physical and emotional), entertainment, photographs and physical injury of any kind….

 

I/we further agree to hold harmless and to release Give Kids the World, Inc. [releasee] from and against any and all claims and causes of action of every kind arising from any and all physical or emotional injuries and/or damages which may happen to me/us….

 

During a vacation, the mother of a child injured herself due to a malfunction of a wheelchair lift they were on.  The family sued for negligence and the non-profit organization argued that such a negligence claim was barred by virtue of the release the family executed that released the non-profit company “from any liability whatsoever…”  which would be broadly understood to include all negligence claims.  The non-profit further argued if the release did not cover negligence claims, it would essentially be worthless since the obvious intent of the release was to bar these types of claims.  Conversely, the family argued that the release did not bar negligent acts because nowhere in the release does it even use the words “negligence” or “negligent acts.”

 

The Florida Supreme Court agreed with the non-profit company and the broad language that released the non-profit company “from any liability whatsoever…” expounding:

 

[W]e are reluctant to hold that all exculpatory [release]  clauses that are devoid of the terms “negligence” or “negligent acts” are ineffective to bar a negligence action despite otherwise clear and unambiguous language indicating an intent to be relieved from liability in such circumstances. Application of such a bright-line and rigid rule would tend to not effectuate the intent of the parties and render such contracts otherwise meaningless.

***

The wish request form and liability release form signed by the Sanislos [plaintiff] released Give Kids the World [non-profit company] and all of its agents, officers, directors, servants, and employees from “any liability whatsoever in connection with the preparation, execution, and fulfillment of said wish….” The language of the agreement then provided that the scope of the agreement included “damages or losses or injuries encountered in connection with transportation, food, lodging, medical concerns (physical and emotional), entertainment, photographs and physical injury of any kind….” This agreement clearly conveys that Give Kids the World would be released from any liability, including negligence, for damages, losses, or injuries due to transportation, food, lodging, entertainment, and photographs. With regard to Give Kids the World and the wish fulfilled for the Sanislos, it is unclear what this agreement would cover if not the negligence of Give Kids the World and its agents, officers, directors, servants, and employees, given that exculpatory clauses are unenforceable to release a party of liability for an intentional tort.

Sansislo, supra.

 

What exactly does this ruling mean?

 

It means, be careful, really careful, when executing a release, especially a release given in advance of an event or situation.  Naturally, when a release is given in advance of an event or situation, the release is routinely executed without a lot of consideration given to when the release would apply.  Before the event or situation, you do not foresee the other party committing a negligent act and/or getting hurt by such negligence.  But, it certainly could happen which is why the releasee wants to give you an advance release to execute.   Further, but for the execution of the release, the releasee (or company that wants the release) will probably not allow you to participate or attend the event, etc.  This is another reason the release is routinely executed without a lot of consideration given to the context of the release.

 

But, as demonstrated by the Florida Supreme Court, this advance release can come back to haunt a person that is injured by the negligence of the releasee simply because that person executed an advance release or release given BEFORE the negligence occurred.  Thus, be careful, and appreciate this risk, when executing a release in advance of an event or situation.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.