NOT SO FAST DEVELOPER WITH YOUR CREATIVE EFFORT TO WIPE OUT THE CONTRACTOR’S (INFERIOR) LIEN!

imagesTwo things are certain in construction: (1) developers will obtain construction loans to finance the construction of their project and (2) there will unfortunately be bad projects where the developer’s lender forecloses on the (first priority) mortgage given in connection with the construction loan.   Not only is this bad for the developer, but it is bad for contractors because the lender will look to foreclose (and wipe out) all inferior liens, such as unpaid contractors and suppliers’ liens (which will be inferior to the lender’s mortgage).

 

 

The case of CDC Builders, Inc. v. Biltmore-Sevilla Debt Investors, LLC, 39 Fla. L. Weekly D1997a (Fla. 3d 2014) illustrates a bad project where a lender moved to foreclose on a construction loan.  But, unlike a more traditional example of the construction lender foreclosing, this case involved a hyper-creative attempt by the developer to purchase its own construction loan and then foreclose on the corresponding mortgage for the sole purpose of intentionally wiping out its general contractor’s lien.

 

 

In this case, the developer hired the contractor to build luxury homes.  The contractor completed the homes, but the developer failed to pay the contractor for the last eight homes.  The contractor recorded construction liens to collateralize its nonpayment.  The developer was unable to pay off its construction loan due to a lack of luxury home sales. To avoid the lender foreclosing, the developer negotiated loan extensions where the developer was required to pay money to reduce the lender’s exposure on the loan. However, the developer did not want its payments to reduce the principal of the loan.  Why? Because the developer wanted to ensure there would be no equity in the real property to satisfy the contractor’s liens.  So, the developer negotiated with its construction lender to treat any money it paid the lender for loan extensions as junior liens against the property.   The developer then had another company created. This other developer-related company purchased the construction loans from the construction lender in exchange for loan assignments. (This was done so the other company maintained a first priority interest with the real property since it purchased the original construction loans.)  Once this other developer-related company purchased the construction loans, it moved to foreclose on the loans.  Why?  Because, by doing so, the developer could wipe out the contractor’s liens as inferior liens on the real property.  Very creative and it actually worked as the trial court entered a final summary judgment of foreclosure in favor of this  developer-related company (meaning the contractor’s inferior liens would be valueless based on the equity in the real property).

 

 

The Third District Court of Appeal reversed the trial court’s foreclosure judgment (as there were questions of fact as to whether the developer-related company was actually created by the same investors that controlled the developer).  The Third District, employing a policy of fairness,  held that:

 

The law does not permit a person to borrow money from a bank, give the bank a mortgage, incur additional liens and junior mortgages on the property, purchase the mortgage back from the bank, and then foreclose on the mortgage for the primary purpose of eliminating the additional liens and junior mortgages.

***

[I]nvestors cannot grant mortgages, contract for the improvement of the property mortgaged, and then use a network of companies to purchase and foreclose the mortgage for the primary purpose of extinguishing the construction liens that increased the value of the property.  To hold otherwise would undermine the long-standing principle…persons cannot do indirectly what they are not permitted to do directly.

CDC Builders, supra

 

 

Stated differently, and less eloquently then the Third District, the law does not permit a developer to undertake creative avenues to purchase the very mortgage and loan it originally obtained to finance its construction for the sole purpose of cheating its contractor out of payment for improving the real property.  To find otherwise would simply give the developer a windfall since it would not have to pay for construction improvements that it wanted and which improved the value of its property.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

THE IMPORTANCE OF AN EFFECTIVE NOTICE OF COMMENCEMENT ON YOUR LIEN RIGHTS

imagesContractors, subcontractors, and suppliers need to appreciate the importance of an EFFECTIVE Notice of Commencement.    This recorded document, among other things, governs the priority of YOUR lien rights on a private construction project because a construction lien RELATES BACK in time to an effective Notice of Commencement.

 

The Notice of Commencement is recorded in the public records where the project is located.  It is a statutory form (per Florida Statute s. 713.13) and gives the lienor the required information about the project so that the lienor can preserve its lien / bond rights.  A copy of the Notice of Commencement form is included at the bottom of this posting.   The Notice of Commencement must be recorded within 90 days of construction otherwise the Notice is invalid.

 

The Notice of Commencement is effective for 1 year unless a different expiration date is specified.  If a project is going to last longer than a year, a more realistic expiration date should be specified.  However, the Notice of Commencement can be amended at any time within its effective period to extend the expiration date.  The amended Notice of Commencement should reflect that it is amending the original Notice of Commencement that is recorded (and specify the book and page of the recording) and a copy must be served by the owner on the contractor and any other lienor that served a Notice to Owner to preserve its lien rights “before or within 30 days after the date the amended notice is recorded.”  Fla. Stat. s. 713.13(5)(b).

 

In demonstrating the importance of an effective Notice of Commencement, Section 713.13(6) provides:

 

Unless otherwise provided in the notice of commencement or a new or amended notice of commencement, a notice of commencement is not effectual in law or equity against a conveyance, transfer, or mortgage of or lien on the real property described in the notice, or against creditors or subsequent purchasers for a valuable consideration, after 1 year after the date of recording the notice of commencement.”

 

 

What does this mean?  The best way to explain is to apply this statutory language to the following facts of a condominium project:

 

Construction loan recorded on 1/1/09.

Notice of Commencement recorded on 5/1/09.  It is only effective for 1 year and an amended Notice was never recorded.

On 6/15/10 a mortgage is recorded on a condominium unit.  When this is recorded, the unit owner’s mortgagee secures a release from the construction lender relating to the lender’s mortgage relating to the unit.

On 7/1/10 a construction lien is recorded.

 

Under this factual pattern, the lienor that recorded a lien would absolutely want its lien to take priority over the unit owner’s mortgage.  The lienor will argue it takes priority since the lien should relate back to the Notice of Commencement that was recorded prior to the mortgage on the unit.  But, wait.  The Notice of Commencement expired before the lien was recorded and an amended Notice of Commencement was never recorded.  This means the lien takes priority as of the date it is recorded and, thus, the mortgage on the condominium unit takes priority.

 

Now, let’s add another realistic wrinkle to this fact pattern.  Let’s say the Declaration of Condominium (the instrument creating the condominium) is recorded on 6/1/10, before the lien is recorded.

 

The Declaration of Condominium would need to be recorded before mortgages are recorded on individual units.  For the construction of a new condominium, the lien would apply to the ENTIRE condominium property provided the lien relates back to the Notice of Commencement.  This is because the lien would take priority before the Declaration of Condominium was even recorded.  But, if the Notice of Commencement expired, then the Declaration of Condominium would take priority over the lien since the Declaration of Condominium would have been recorded first (since the lien would not relate back to the Notice of Commencement).  This means that the lien would not apply to the entire condominium property, but would more equitably apply to each unit based on the unit’s pro rata share of the common expenses. See Fla. Stat. 718.121.  In other words, if the lien is $100,000 and there are 100 units each responsible for 1% of the condominium association’s budget, each unit would be responsible for the principal amount of $1,000 in order to discharge the lien relating to the unit. And, mortgages on the individual units may take priority over the lien potentially nullifying the value of the lien based on the equity in the units.

 

Notably, even if a lien relates back to the Notice of Commencement and takes priority over the Declaration of Condominium, a court may still find the equitable result is that each unit is only liable for its pro rata share of common expenses.  See Southern Colonial Mortgage Co., Inc. v. Medeiros, 347 So.2d 736 (Fla. 4th DCA 1977).  However, this equitable approach should arguably not apply because the lien would attach to the entire condominium property and the lienor should be entitled to foreclose that property including all units since the lien would have priority over any mortgage and deed associated with those units.  At this point, the unit owner should look to its title insurance policy.

 

UnknownTake-aways:

 

  • Make sure the Notice of Commencement is recorded within 90 days from the start of construction.  If not, there will be a strong argument that the Notice is not valid.  This means that a lien would not be able to relate back to the Notice.

 

  • Make sure the lien is recorded within an effective Notice of Commencement.  If not, the lien will not relate back to the Notice, but will take priority as of the date it is recorded.  This is a big difference.

 

  • If the Notice of Commencement is on the verge of expiring, prepare and send a letter to the owner advising the owner that it needs to record an amended Notice of Commencement to ensure the parties are performing construction within an effective Notice of Commencement.

 

  • Understand the potential priority of your lien based on the recording of the Notice of Commencement, any amended Notice of Commencement, the Declaration of Condominium, and other recordings that may impact the priority of your lien if the Notice of Commencement expired.

 

 

 

 

NOTICE OF COMMENCEMENT

State of _____

County of _____

The undersigned hereby gives notice that improvement will be made to certain real property, and in accordance with Chapter 713, Florida Statutes, the following information is provided in this Notice of Commencement.

1. Description of property: (legal description of the property, and street address if available).

2. General description of improvement: __________.

3. Owner information or Lessee information if the Lessee contracted for the improvement:

a. Name and address: __________.

b. Interest in property: __________.

c. Name and address of fee simple titleholder (if different from Owner listed above): __________.

4. a. Contractor: (name and address) .

b. Contractor’s phone number: _____.

5. Surety (if applicable, a copy of the payment bond is attached):

a. Name and address: __________.

b. Phone number: _____.

c. Amount of bond: $_____.

6. a. Lender: (name and address) .

b. Lender’s phone number: _____.

7. Persons within the State of Florida designated by Owner upon whom notices or other documents may be served as provided by Section 713.13(1)(a) 7., Florida Statutes:

a. Name and address: __________.

b. Phone numbers of designated persons: __________.

8. a. In addition to himself or herself, Owner designates __________ of __________ to receive a copy of the Lienor’s Notice as provided in Section 713.13(1)(b), Florida Statutes.

b. Phone number of person or entity designated by owner: _____.

9. Expiration date of notice of commencement (the expiration date will be 1 year from the date of recording unless a different date is specified) _____.

WARNING TO OWNER: ANY PAYMENTS MADE BY THE OWNER AFTER THE EXPIRATION OF THE NOTICE OF COMMENCEMENT ARE CONSIDERED IMPROPER PAYMENTS UNDER CHAPTER 713, PART I, SECTION 713.13, FLORIDA STATUTES, AND CAN RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY. A NOTICE OF COMMENCEMENT MUST BE RECORDED AND POSTED ON THE JOB SITE BEFORE THE FIRST INSPECTION. IF YOU INTEND TO OBTAIN FINANCING, CONSULT WITH YOUR LENDER OR AN ATTORNEY BEFORE COMMENCING WORK OR RECORDING YOUR NOTICE OF COMMENCEMENT.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

LIEN RIGHTS FOR PROFESSIONAL (DESIGN) SERVICES

imagesDesign professionals  (e.g., architect, engineer, interior designer, surveyor, and mapper) have lien rights for professional services they perform under Florida’s Lien Law.

 

 

Florida Statute s. 713.03 governs liens for professional services and provides:

 

(1) Any person who performs services as architect, landscape architect, interior designer, engineer, or surveyor and mapper, subject to compliance with and the limitations imposed by this part, has a lien on the real property improved for any money that is owing to him or her for his or her services used in connection with improving the real property or for his or her services in supervising any portion of the work of improving the real property, rendered in accordance with his or her contract and with the direct contract.

 

(2) Any architect, landscape architect, interior designer, engineer, or surveyor and mapper who has a direct contract and who in the practice of his or her profession shall perform services, by himself or herself or others, in connection with a specific parcel of real property and subject to said compliances and limitations, shall have a lien upon such real property for the money owing to him or her for his or her professional services, regardless of whether such real property is actually improved.

 

 

This statutory language is important to the design professional.  Paragraph 1 says that a design professional shall have lien rights for their professional services rendered pursuant to their contract and the direct contract (or contract with the owner of the real property, typically the owner-architect contract in the design-bid-build scenario) in connection with improving the real property.  This would be the paragraph relied on by design professionals NOT in privity of contract with the owner.  On the other hand, Paragraph 2 would apply to design professionals that enter into a direct contract with the owner of the real property for professional services (such as the architect in the design-bid-build scenario).  Under this paragraph, the design professional has lien rights for their professional services regardless of whether the real property is even improved.  This means that the owner can decide not to use the professional services (the design) or abandon the project and the design professional in direct contract with the owner has lien rights even though the real property has not been improved.   Now, if a design professional enters into a contract with a developer or person that never had an interest in the real property, the design professional is not going to be able to use this statute to create lien rights because it never entered into a contract with the actual owner of the real property.  See Grossman v.  Pollack, 100 So.2d 660 (Fla. 3d DCA 1958) (finding that architect could not enforce lien for leasehold interest that never came into being because there was no privity between architect or anyone with interest in the real property).

 

Design professionals have flexibility preserving lien rights since they do not have to comply with all of the technical requirements that a general contractor, subcontractor, or supplier must comply with.  Design professionals do NOT need to serve a Notice to Owner (within 45 days of initial furnishing) unlike the supplier or subcontractor not in privity of contract with the owner.  And, the design professional in privity of contract with the owner does NOT need to serve a contractor’s final payment affidavit (at least 5 days before filing a lawsuit) unlike the contractor hired directly by the owner.   The ONLY thing the design professional needs to do to secure its lien rights is to record a lien within 90 days of its final furnishing of professional services (and serving a copy of the lien on the owner).

 

 

images-1The downside, however, is that a design professional’s lien maintains a priority standpoint from the date the lien is recorded.  So, anything that is recorded before the design professional’s lien will be superior to the lien.  This is different than a lien recorded by a general contractor, subcontractor, or supplier in that their lien relates back to an effective notice of commencement, which is important from a lien priority standpoint.

 

For example, let’s assume there is a new construction project.  The owner obtains financing and a mortgage securing the construction loan is recorded.  This mortgage should have superior priority to any other encumbrance on the property (if not, lenders would never lend money!).  After the mortgage is recorded, and before construction commences, a notice of commencement is recorded (which lasts for 1 year unless a different expiration date is specified; although, the notice of commencement can be amended).  Within the effective period of the notice of commencement, the structural engineer records a lien; the next day the architect records a lien.  Months later, and within the effective period of the notice of commencement, the framing subcontractor records a lien.  What is the priority of these liens? The framing subcontractor’s lien will have priority because it will relate back to the notice of commencement.  Then, the structural engineer’s lien will have priority over the architect’s lien because it was recorded the day before the architect’s lien.  Remember, design professional’s liens do not relate back to the notice of commencement and their priority is dictated as of the date/time they are recorded. Any other contractor or supplier that records a lien within the effective notice of commencement will have priority over the design professional’s lien since these liens will relate back to the earlier recorded notice of commencement.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION RENTAL EQUIPMENT SUPPLIERS AND THE ENFORCEMENT OF LIEN RIGHTS

imagesConstruction rental equipment suppliers play a large role in the performance of construction projects, whether it is through furnishing a crane, barge, excavator, scissor lift, scaffolding, loader, compressor, generator, shoring, pump, etc. Routinely, the trade subcontractor that needs the equipment to perform its contractual scope of work procures the rental equipment.

 

Well, how do these rental equipment suppliers enforce lien rights on private projects if they remain unpaid?

 

To begin with, they need to serve preliminary notices such as the Notice to Owner within 45 days from initial furnishing, which is the date rental equipment is delivered to the site.  The lien must then be recorded within 90 days from final furnishing, which is the last date the rental equipment is on the job site and available for use.  These dates should (hopefully) be pretty easy to determine as suppliers document the date rental equipment was delivered to the job site and the date the equipment was picked-up from the job site.  If not, these dates should be obtained by the renting party’s records.

 

Before recording the lien, the rental equipment supplier needs to determine the lien amount. The rental equipment supplier will typically lien for the entire amount of the rental equipment it furnished to the renting party / lessee for the project pursuant to the contractual rate(s) in the rental agreement.  This is generally the appropriate strategy because Florida’s Lien Law provides in pertinent part:

 

The delivery of rental equipment to the site of the improvement is prima facie evidence of the period of the actual use of the rental equipment from the delivery through the time the equipment is last available for use at the site, or 2 business days after the lessor of the rental equipment receives a written notice from the owner or the lessee of the rental equipment to pick up the equipment, whichever occurs first.”

Fla. Stat. s. 713.01(13). 

 

This language is important to the rental equipment supplier because if the supplier has the documentation as to when the rental equipment was delivered and picked-up, then this should shift the burden to the owner to prove that the rental equipment was not actually used on the project to diminish the amount of the lien.

 

Notably, the language in Florida’s Lien Law regarding rental equipment used to provide: “to the extent of the reasonable rental value for the period of actual use (not determinable by the contract for rental unless the owner is a party thereto),” meaning that the onus was on the rental equipment supplier not in privity with the owner to determine actual usage of the equipment on the project and the reasonable value for the period the equipment was actually used on the project.  This verbiage has since been removed from Florida’s Lien Law (in 2007), such that burden is really shifted to the owner to prove that the equipment was not actually used on the job site irrespective of when it was delivered and when it was picked-up.  While an owner may still argue that the supplier must also prove the “reasonable value” of the equipment actually used on the job site (with the reasonable value differing from the contract rental rate), this argument is based on the statutory language and case law interpreting the verbiage that has since been removed from Florida’s Lien Law. See, e.g., Rosenholz v. Perrine Development Co., 340 So.2d 1264 (Fla. 4th DCA 1976) (interpreting older version of Fla. Stat. s. 713.01 and finding that contractual rental rate, although unchallenged, did not support the reasonable rental value because the supplier did not introduce evidence of the reasonable, actual use of the equipment required for the lessee’s scope of work).  In other words, to the extent the owner wants to maintain this argument, it really should have the burden challenging (a) the actual use of the equipment, perhaps by resorting to daily reports showing the equipment was not actually used and (b) the reasonable rental value should be different than the contractual rental rate based on evidence supporting this position.

 

Now, even under the older verbiage in Florida’s Lien Law, a rental equipment supplier did not have to jump through hoops in an action against a payment bond for a private project (issued per Florida Statute s. 713.23) to prove both the actual use of the rental equipment and the reasonable rental rate for that equipment.  See, e.g., Insurance Co. of N. America v. Julien P. Benjamin Equipment Co., 481 So.2d 511, 513 (Fla. 1st DCA 1985) (“We distinguish from this [language in the payment bond] the language found in the statute [Fla. Stat. s. 713.01], which, in our view, is substantially more restrictive and clearly requires actual proof of the time of use of rental equipment and the reasonable value thereof unless the owner of the project is shown to have been a party to the rental contract covering such equipment.”).

 

Therefore, it is important for the rental equipment supplier to keep records documenting the delivery date and pick-up date from the specific project in which it plans to lien.  The owner, especially an owner that did not contract for the rental equipment, needs to obtain this information and, to the extent there are daily reports from the lessee (party that rented the equipment), cross-reference the equipment with the daily reports to examine when the equipment was actually used.  While the owner may still choose to argue the “reasonable rental value” for the equipment based on “actual usage,” this burden should fall on the owner with evidence supporting the reasonable rental value the owner believes should apply based on actual usage.  Sometimes, even though these arguments may have teeth, it may be efficient for the owner to negotiate a resolution with respect to equipment it recognizes was utilized on its project in the performance of the work.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

SERVING PRELIMINARY LIEN / PAYMENT BOND NOTICES ON PRIVATE PROJECTS

Subcontractors and suppliers need to know the preliminary notices (such as a Notice to Owner for liens or Notice to Contractor for payment bonds) that need to be served to preserve their lien or payment bond rights on private projects.

 

 A.    Obtaining a Copy of the Notice of Commencement

 

images-1The first thing a potential lienor should do is obtain the Notice of Commencement for the project (or any Amended Notice of Commencement).  The Notice of Commencement will be recorded in the official records where the project is located and will provide a potential lienor with a description of the real property, the owner’s information, the contractor’s information, the construction lender’s information, whether the contractor has a payment bond (which should be recorded with the Notice of Commencement), and persons other than the owner that the Notice to Owner needs to be served on.

 

 B.    Preliminary Notices for Liens- the Notice to Owner

 

If there is no payment bond recorded with the Notice of Commencement, then the potential lienor knows it wants to preserve its lien rights.  Entities not in privity of contract with the owner will need to serve a Notice to Owner. The Notice to Owner must set “forth the lienor’s name and address, a description sufficient for identification of the real property, and the nature of the services or materials furnished or to be furnished.” Fla. Stat. s. 713.06(2).  A statutory form is included in Florida’s Lien Law (Florida States Chapter 713) and set forth at the bottom of this posting.  Importantly, the Notice to Owner must be served by the potential lienor “before commencing, or not later than 45 days after commencing, to furnish his or her labor, services, or materials.”  Fla. Stat. s. 713.06(2).  The key is that the Notice to Owner must be served within 45 days of the entity’s initial furnishing.  For instance, a supplier’s initial furnishing is when the materials arrive on site.  However, a supplier of specially fabricated material’s initial furnishing is when the supplier started fabrication irrespective of when the materials arrived on site.  A company supplying construction rental equipment’s initial furnishing is when the rental equipment arrived on site.  And, a subcontractor’s initial furnishing is when it first starts to furnish labor, services, or materials for the project.  Again, there is no reason to delay serving the Notice to Owner – it should be served immediately as a matter of course.

 

A copy of the Notice to Owner should be served on the contractor if the potential lienor was not hired by the contractor in addition to the potential lienor’s customer’s customer.  In other words: “A sub-subcontractor or a materialman to a subcontractor must serve a copy of the notice on the contractor as a prerequisite to perfecting a lien under this chapter and recording a claim of lien. A materialman to a sub-subcontractor must serve a copy of the notice to owner on the contractor as a prerequisite to perfecting a lien under this chapter and recording a claim of lien. A materialman to a sub-subcontractor shall serve the notice to owner on the subcontractor [potential lienor’s customer’s customer] if the materialman knows the name and address of the subcontractor.” Fla. Stat. 713.06(2). (Lien rights, however, are not automatic in that the further removed an entity is from the owner may impact whether or not that entity has lien rights.  For example, a sub-sub-subcontractor does not have lien rights and a supplier to a supplier is not going to have lien rights.  On the other hand, sub-subcontractors will have lien rights and a supplier to a sub-subcontractor should also have lien rights.)

 

 C.    Preliminary Notices for Payment Bonds-the Notice to Contractor and  the Notice of Nonpayment

 

Now, if there is a payment bond in place, the owner’s property is exempt from liens and the entities should look to the payment bond for payment.  In this case, entities not in privity of contract with the general / prime contractor “before beginning or within 45 days after beginning to furnish labor, materials, or supplies…shall serve the contractor with notice in writing that the lienor will look to the contractor’s bond for protection on the work.” Fla. Stat. s. 713.23(1)(c).  Similar to the Notice to Owner, this Notice to Contractor of the potential lienor’s intent to look to the bond must be served within 45 days of initial furnishing.  A statutory form for this notice is also included in Florida’s Lien Law and further set forth at the bottom of this posting.  Importantly, if a lienor is unsure and/or wants to preserve both lien and payment bond rights the lienor can combine the Notice to Owner form with the Notice to Contractor form by calling the Notice to Owner form “NOTICE TO OWNER/NOTICE TO CONTRACTOR.”  This is actually common as it kills two birds with one stone in the event the lienor is unsure and wants to preserve both lien and bond rights.

 

 

However, unlike perfecting a lien claim, potential lienors looking to recover under a payment bond for a private project must serve a Notice of Nonpayment to the contractor and payment bond surety within 90 days of finial furnishing at the project.  (As it relates primarily to subcontractors, “The failure of a lienor to receive retainage sums not in excess of 10 percent of the value of labor, services, or materials furnished by the lienor is not considered a nonpayment requiring the service of the notice provided under this paragraph. Fla. Stat. s. 713.23(1)(d).)  This Notice of Nonpayment even needs to be served by the subcontractor/supplier in privity of contract with the general contractor (even though the preliminary Notice to Contractor does not need to be served by the subcontractor/supplier in privity of contract with the general contractor).  Final furnishing refers to the last date the lienor furnished labor, services or materials (excluding warranty or punchlist work).  With respect to companies that furnish rental equipment, this final furnishing date is measured from the last date the rental equipment was on the project site and available for use.

 

Understanding the specific preliminary notices that need to be served and the timing of these notices is important to ensure that a subcontractor, supplier, etc. is properly preserving their lien or bond rights.

 

 D.    Preliminary Notice Companies

 

images-2There are numerous companies that cost effectively assist subcontractors and suppliers with serving preliminary notices as a matter of course based on the information provided by the subcontractor and supplier.  This is important to ensure the company preserves lien and bond rights!

 

One such emerging company that can assist with the generation, preparation and service of preliminary notices is FileMyPrelim (www.filemyprelim.com) with its cool, innovative web-based platform called PrelimTracker (www.prelimtracker.com).  FileMyPrelim and PrelimTracker have developed a preliminary notice service and tracking platform that adapts to a construction industry that is evolving with the generation and transmission of electronic documentation.  What is really cool is that by using FileMyPrelim, the lienor’s data is stored and tracked with PrelimTracker.  Because these preliminary notices (whether it is a Notice to Owner, Notice to Contractor, etc.) are linked to PrelimTracker, the general contractor, the owner, and even the owner’s construction lender can universally track those entities that served the preliminary notices jointly on this web-based platform.  By doing this, the general contractor, owner, and lender are all on the same page to ensure that those entities that preserved lien rights are properly transmitting releases of lien in consideration of progress payments (so that their lien rights are released through a specified date) and that a final release of lien is given in consideration of final payment to that lienor.  In fact, PrelimTracker can generate the lienor’s release of lien based on the information provided by the lienor and transmit it electronically with a secure electronic signature.  This allows all of the lienor’s releases to be stored and tracked in a platform accessible to the project team.  Even if a lien could not be recorded against the owner’s project because the general contractor furnished a payment bond, PrelimTracker could track the preliminary notices from lienors served through FileMyPrelim preserving payment bond rights to ensure the general contractor is obtaining releases of lien from those entities.  (Keep in mind, PrelimTracker provides value as it pulls data compiled in FileMyPrelim to report critical lien related documents.)  Check out the website links to learn more about this emerging technology that can serve as a beneficial tool to the entire project team.

 

 E.    Preliminary Notice Forms

 

 

Preliminary Notice for Liens

 

 

WARNING! FLORIDA’S CONSTRUCTION LIEN LAW ALLOWS SOME UNPAID CONTRACTORS, SUBCONTRACTORS, AND MATERIAL SUPPLIERS TO FILE LIENS AGAINST YOUR PROPERTY EVEN IF YOU HAVE MADE PAYMENT IN FULL.

 

UNDER FLORIDA LAW, YOUR FAILURE TO MAKE SURE THAT WE ARE PAID MAY RESULT IN A LIEN AGAINST YOUR PROPERTY AND YOUR PAYING TWICE.

 

TO AVOID A LIEN AND PAYING TWICE, YOU MUST OBTAIN A WRITTEN RELEASE FROM US EVERY TIME YOU PAY YOUR CONTRACTOR.

 

NOTICE TO OWNER

 

To (Owner’s name and address)

 

The undersigned hereby informs you that he or she has furnished or is furnishing services or materials as follows:

 

(General description of services or materials) for the improvement of the real property identified as (property description) under an order given by____________.

 

Florida law prescribes the serving of this notice and restricts your right to make payments under your contract in accordance with Section 713.06, Florida Statutes.

 

IMPORTANT INFORMATION FOR

 

YOUR PROTECTION

 

Under Florida’s laws, those who work on your property or provide materials and are not paid have a right to enforce their claim for payment against your property. This claim is known as a construction lien.

 

If your contractor fails to pay subcontractors or material suppliers or neglects to make other legally required payments, the people who are owed money may look to your property for payment, EVEN IF YOU HAVE PAID YOUR CONTRACTOR IN FULL.

 

PROTECT YOURSELF:

 

–RECOGNIZE that this Notice to Owner may result in a lien against your property unless all those supplying a Notice to Owner have been paid.

 

–LEARN more about the Construction Lien Law, Chapter 713, Part I, Florida Statutes, and the meaning of this notice by contacting an attorney or the Florida Department of Business and Professional Regulation.

 

(Lienor’s Signature)

(Lienor’s Name)

(Lienor’s Address)

 

Copies to: (Those persons listed in Section 713.06(2)(a) and (b), Florida Statutes)

 

 

Preliminary Notices for Payment Bonds

 

 

NOTICE TO CONTRACTOR

 

To (name and address of contractor)

 

The undersigned hereby informs you that he or she has furnished or is furnishing services or materials as follows:

 

(general description of services or materials) for the improvement of the real property identified as (property description) under an order given by (lienor’s customer) .

 

This notice is to inform you that the undersigned intends to look to the contractor’s bond to secure payment for the furnishing of materials or services for the improvement of the real property.

 

(name of lienor)

 

(signature of lienor or lienor’s representative)

 

(date)

 

(lienor’s address)

 

 

NOTICE OF NONPAYMENT

 

To (name of contractor and address)

 

(name of surety and address)

 

The undersigned notifies you that he or she has furnished (describe labor, services, or materials) for the improvement of the real property identified as (property description) The amount now due and unpaid is $___.

 

(signature and address of lienor)

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

LIEN RIGHTS FOR SPECIALLY FABRICATED MATERIALS

imagesSpecially fabricated materials are those materials that are specially manufactured, designed, or fabricated for a particular project and are not materials that can be universally used on all projects.  Specially fabricated materials have been described as those materials “not generally suited for nor readily adaptable to use in a like improvement.” Odolite Industries, Inc. v. Millman Const. Co., Inc., 501 So.2d 655, 656 (Fla. 3d DCA 1987) (quotation omitted).   For instance, the Florida Supreme Court in Stunkel v. Gazebo Landscaping Design, Inc., 660 So.2d 623, 625 n.2 (Fla. 1995), noted that trees the owner specifically selected for a project were not specially fabricated because they could be used on other projects; whereas, in Lehigh Structural Steel Co. v. Joseph Langer, Inc., 43 So.2d 335, 338 (Fla. 1949), the Court noted that structural steel fabricated for a specific building was specially fabricated materials. (Notably, furnishing specially fabricated materials does not include “design work, submittals, or the like preliminary to actual fabrication of the materials.” Fla. Stat. s. 713.01(13).)

 

Preserving lien rights under Florida’s Lien Law for specially fabricated materials is different than other materials (or non-specially fabricated materials).

 

Because specially fabricated materials are specifically fabricated for a particular project, these materials do NOT have to be actually incorporated into the project for the supplier / fabricator to have lien rights. Aquatic Management, Inc. v. Paramount Engineering, Inc., 977 So.2d 600 (Fla. 4th DCA 2007).  If the materials are not specially fabricated, the materials do need to be actually incorporated into the project.  Id.   This is a major difference.

 

And, because specially fabricated materials do not have to be actually incorporated for a supplier / fabricator to have lien rights for those materials, a notice to owner / intent to look to the payment bond (if there is a payment bond) needs to be served within 45 days from the start of actual fabrication and NOT from when the materials are actually delivered to the job site (since the materials do not actually have to be delivered and incorporated for lien rights for these materials). See Odolite Industries, 501 So.2d at 656; Fla. Stat. 713.01(13). This means that a supplier of specially fabricated materials not in privity with the contractor needs to absolutely serve its notice to owner immediately and no later than 45 days from when fabrication begins.

 

Also, if the supplier / fabricator is owed money: “Materials specially fabricated at a place other than the site of the improvement for incorporation but not so incorporated and the contract price or value thereof shall be separately stated in the claim of lien.”  Fla. Stat. s. 713.08(1)(c).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DON’T FORGET TO TIMELY FORECLOSE THE CONSTRUCITON LIEN IN COURT!

imagesKBDKQVLNA Notice of Contest of Lien under Florida Statute s. 713.22 is a vehicle that will shorten the statute of limitations for a lienor to foreclose on a recorded construction lien from one year to 60 days from the date the lien is contested.  A copy of a Notice of Contest of Lien is identified below.  An unwary lienor that fails to timely foreclose on its claim of lien in court will be deprived of its lien rights!

 

The recent decision in Snell v. Mott’s Contracting Services, Inc., 39 Fla. L. Weekly D1053a (Fla. 2d DCA), illustrates such an unwary lienor.  In this case, a contractor recorded a claim of lien on a residential project.  The owner then filed a lawsuit against the contractor and the contractor moved to dismiss or stay the action based on an arbitration provision in the contract.  The owner then filed a Notice of Contest of Lien to shorten the contractor’s statute of limitations to foreclose on the lien to 60 days.  The contractor, however, never moved to foreclose its lien in court; the court compelled the dispute to arbitration.

 

The contractor prevailed in arbitration and the arbitrator found that the contractor was the prevailing party under Florida Statute s. 713.29 that entitles a prevailing party in a lien action to its attorney’s fees (i.e., a party that prevails on the significant issues in the action).

 

However, the two issues on appeal were: (1) whether the contractor could be entitled to its attorney’s fees under s. 713.29 when it failed to timely foreclose on its lien in court after it received the Notice of Contest of Lien and (2) whether the arbitrator, absent express agreement of the parties, had authority to determine entitlement to attorney’s fees.

 

As it pertains to the first issue, the Second District found that because the contractor failed to comply with s. 713.22 by foreclosing on its lien in court within 60 days after the lien was contested, the contractor was not entitled to attorney’s fees pursuant to s. 713.29.  Stated simpler, the contractor was not entitled to attorney’s fees because it no longer had lien rights since it failed to timely foreclose on its lien in court within 60 days after the lien was contested by the owner.

 

As it pertains to the second issue, the Second District found that an arbitrator has no authority / jurisdiction to determine a party’s entitlement to attorney’s fees unless the parties to the arbitration expressly waive the right to have a court determine entitlement.

 

This cases raises a few important points:

 

  • Even if there is an arbitration provision in a contract, it is still imperative that a lien foreclose action be filed in court!  File the lien action and simultaneously move to stay the lien foreclosure action pending the arbitration.

 

  • If you receive a Notice of Contest of Lien, do not forget that it operates to shorten the statute of limitations to foreclose on the lien to 60 days.  Otherwise, the lien will not be enforceable.

 

  • If you want an arbitrator to determine the entitlement to attorney’s fees, it is good practice to ensure that the parties to arbitration expressly agree to grant the arbitrator this authority and waive the court’s authority to determine entitlement.

 

 

NOTICE OF CONTEST OF LIEN

To: (Name and address of lienor)

You are notified that the undersigned contests the claim of lien filed by you on ___, (year) , and recorded in ___ Book ___, Page ___, of the public records of ___ County, Florida, and that the time within which you may file suit to enforce your lien is limited to 60 days from the date of service of this notice. This ___ day of ___, (year) .

Signed: (Owner or Attorney)

 

For more information on Notice of Contests of Lien, please see: https://floridaconstru.wpengine.com/oh-no-a-lien-is-recorded-what-are-some-of-my-options/.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

 

 

OH NO! A LIEN IS RECORDED! WHAT ARE SOME OF MY OPTIONS?

Mechanics-LienYou are an owner and a construction lien is recorded on your property.  Or, you are a general contractor required to indemnify the owner for construction liens and a subcontractor you are in a dispute with records a construction lien (or one of the subcontractor’s suppliers or subcontractors records a lien).  What are your options (other than paying the lienor in consideration of a satisfaction of lien) to extinguish the lien or transfer that lien to another form of security other than the real property?

 

(1) Notice of Contest of Lien – This is an efficient, cost effective strategy that I oftentimes prefer to use to truly determine whether a lienor (entity that recorded lien) actually intends on foreclosing on the lien.  Recording a Notice of Contest of Lien pursuant to Florida Statute s. 713.22 shortens the statute of limitations to foreclose on the lien to 60 days after service of the Notice; if the lienor neglects to do so, the lien is extinguished.  (A construction lien is otherwise good for one year from its recording.)  Section 713.22 provides that an owner or an owner’s attorney can record a Notice of Contest of Lien in the official records (same official records where the lien is recorded).  The Notice is a statutory form (see form below).  Once it is recorded, the clerk serves it on the lienor at the address in the lien putting the lienor on notice that it must foreclose within 60 days.  Notably, because the statute says an owner or owner’s attorney should record this, if representing the general contractor, I typically suggest that the general contractor get the owner to sign the Notice (or, get the owner’s permission that it is acceptable for the general contractor to sign as a representative for purposes of the Notice).

 

(2) Filing a Lawsuit to Show Cause – Another approach to shorten a lienor’s statute of limitation to foreclose on the lien is to file a complaint pursuant to Florida Statute s. 713.21 where the clerk issues a special summons “to the lienor to show cause within 20 days why his or her lien should not be enforced by action or vacated and canceled of record.”  Fla. Stat. s. 713.21.   Any interested party can file this lawsuit and the lawsuit is typically accompanied with a fraudulent lien claim against the lienor.  When a lienor receives this lawsuit, it MUST foreclose on its lien within 20 days from service or else its lien should be discharged by the court.  However, this requires drafting of the lawsuit and the special show cause summons, filing the lawsuit, and serving the lawsuit, so it certainly is not as cost effective as the first option.  Also, sometimes, by the time the lawsuit is drafted, filed, and served, the 20 day show cause period would be pretty close to the expiration of the 60 days if the Notice of Contest of Lien was recorded.  Every situation is different and there are circumstances where filing this lawsuit is a more attractive option than recording the Notice of Contest of Lien.

 

(3) Transferring the Lien to Alternative Security such as a Lien Transfer Bond – Sometimes, an owner needs the lien off of its property immediately and wants the lien transferred from the real property to alternative security such as a lien transfer bond.  This is done pursuant to Florida Statute s. 713.24 where cash or a surety bond is posted with the court “in an amount equal to the amount demanded in such claim of lien, plus interest thereon at the legal rate for 3 years, plus $1,000 or 25 percent of the amount demanded in the claim of lien, whichever is greater, to apply on any attorney’s fees and court costs that may be taxed in any proceeding to enforce said lien.”  Fla.Stat. s. 713.24.   Typically, no one wants to post and tie up cash in the amount of the lien, plus 3 years of interest, plus another 25% of that lien amount to cover potential fees/costs.  And, obtaining a surety bond is not always easy without posting collateral or cash to the surety, etc., so that the surety’s risk in posting the bond in the event the lienor prevails is mitigated.  Now, a lien can be transferred to a lien transfer bond at any time including during the  pendency of a lawsuit.  For example, let’s say you elect option (1) or (2) above and the lienor does timely foreclose on the lien; the option of transferring the lien is still available.  The major difference is that if a lien foreclosure lawsuit is underway and the lien transferred to a bond (or cash), the lienor has one year from the date of the transfer to amend its lawsuit to assert a claim against the bond.  If the lien is transferred before the lien foreclosure lawsuit, then the one year to foreclose on the lien from the date the lien is recorded still applies.

 

An attorney should be consulted to assist you to determine the best option and strategy for you if a lien is recorded based on your circumstances.

 

NOTICE OF CONTEST OF LIEN

To: (Name and address of lienor)

You are notified that the undersigned contests the claim of lien filed by you on ___, (year) , and recorded in ___ Book ___, Page ___, of the public records of ___ County, Florida, and that the time within which you may file suit to enforce your lien is limited to 60 days from the date of service of this notice. This ___ day of ___, (year) .

Signed: (Owner or Attorney)

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

LEGAL COMPLEXITIES WHEN THERE IS A FAILED PROJECT

heavy civil photoIberiabank v. Coconut 41, LLC, 2013 WL 6061833 (M.D.Fla. 2013) is a new case involving a failed mixed-use master development (subdivision) that illustrates some of the complexities when a construction project goes bad. It is a great case discussing aspects of Florida’s Lien Law (such as liens for subdivision improvements, single claim of lien, fraudulent liens) that are important for all construction participants. It is also a great case that discusses an unjust enrichment claim for unpaid work and a slander of title claim due to a fraudulently recorded lien. While the facts and issues are lengthy, there are numerous take-aways from this case that should not be ignored and are pointed out at the end of this article.

 

 

I. The Failed Development

 

 

In this case, a developer purchased approximately 46 acres of land. The land was intended to be developed into a master development. The developer sold approximately 14 acres referred to Development Area 2 to HG Coconut. The developer was responsible for installing the necessary infrastructure outside of Development Area 2 that would be required to develop both the developer’s land and Development Area 2. (This included, among other things, widening a road and sanitary-sewer work.)

 

To construct the infrastructure, the developer hired a heavy civil contractor. Two contracts were executed. The first contract was for on-site infrastructure improvements to the developer’s land. The second contract was for off-site infrastructure improvements such as the infrastructure improvements needed to develop Development Area 2. (There was no contract between the contractor and HG Coconut, the owner of Development Area 2.)

 

Because of nonpayment, the contractor recorded a single claim of lien. The lien included Development Area 2 (owned by HG Coconut). Remember, the contractor did not have a contract with the owner of Development Area 2.

 

II. Claims against HG Coconut – the Owner of Development Area 2 – and HG Coconut’s Claims against the Contractor

 

 

The contractor filed a lawsuit and asserted an unjust enrichment claim and lien foreclosure claim against HG Coconut–the owner of Development Area 2.  HG Coconut asserted a fraudulent lien claim and slander of title claim against the contractor.

 

 

A. Unjust Enrichment

 

The contractor contended that it benefited HG Coconut (a party it did not have a contract with) through infrastructure work it performed that provided value to Development Area 2. HG Coconut argued that the unjust enrichment claim should be barred because the contractor’s work was incomplete—it did not finish all of its work. The Middle District dismissed this argument equating recovery under an unjust enrichment theory to that of recovery when a contractor substantially performs. When a contractor substantially performs / completes its work, it is entitled to the full contract price minus the owner’s right to recover damages due to the contractor’s failure to render full performance. Since the contractor substantially completed its work subject to the unjust enrichment claim that provided a benefit to Development Area 2, the Middle District held that the contractor was entitled to the fair market value of the work minus HG Coconut’s offset for the remaining work.

 

B. Lien Foreclosure and Fraudulent Lien

 

The contractor argued that it was not paid for work performed under its off-site contract (the infrastructure work outside of developer’s land that was also needed to develop HG Coconut’s Development Area 2). HG Coconut asserted an affirmative claim against the contractor arguing that the contractor recorded a fraudulent lien.

 

The Middle District entered judgment against the contractor on its lien foreclosure claim. The fraudulent lien claim asserted by HG Coconut establishes the problems under Florida’s Lien Law with the contractor recording a lien that included Development Area 2.

 

Contractor’s performing subdivision improvements are entitled to certain protections under Florida’s Lien Law. Florida Statute s. 713.04(1) provides:

 

Any lienor who, regardless of privity, performs services or furnishes material to real property for the purpose of making it suitable as the site for the construction of an improvement or improvements shall be entitled to a lien on the real property for any money that is owed to her or him for her or his services or materials furnished in accordance with her or his contract and the direct contract. The total amount of liens allowed under this section shall not exceed the amount of the direct contract under which the lienor furnishes labor, materials, or services. The work of making real property suitable as the site of an improvement shall include but shall not be limited to the grading, leveling, excavating, and filling of land, including the furnishing of fill soil; the grading and paving of streets, curbs, and sidewalks; the construction of ditches and other area drainage facilities; the laying of pipes and conduits for water, gas, electric, sewage, and drainage purposes; and the construction of canals and shall also include the altering, repairing, and redoing of all these things. When the services or materials are placed on land dedicated to public use and are furnished under contract with the owner of the abutting land, the cost of the services and materials, if unpaid, may be the basis for a lien upon the abutting land. When the services or materials are placed upon land under contract with the owner of the land who subsequently dedicates parts of the land to public use, the person furnishing the services or materials placed upon the dedicated land shall be entitled to a lien upon the land abutting the dedicated land for the unpaid cost of the services and materials placed upon the dedicated land, or in the case of improvements that serve or benefit real property that is divided by the improvements, to a lien upon each abutting part for the equitable part of the full amount due and owing. If the part of the cost to be borne by each parcel of the land subject to the same lien is not specified in the contract, it shall be prorated equitably among the parcels served or benefited. No lien under this section shall be acquired until a claim of lien is recorded. No notice of commencement shall be filed for liens under this section. No lienor shall be required to serve a notice to owner for liens under this section.”

 

 

However, just because a contractor performing subdivision improvements has certain lien rights, does not mean it can record a fraudulent lien. A fraudulent lien is defined in Florida Statute s. 713.31(2)(a):

 

Any lien asserted under this part in which the lienor has willfully exaggerated the amount for which such lien is claimed or in which the lienor has willfully included a claim for work not performed upon or materials not furnished for the property upon which he or she seeks to impress such lien or in which the lienor has compiled his or her claim with such willful and gross negligence as to amount to a willful exaggeration shall be deemed a fraudulent lien.”

 

If a lien is deemed fraudulent, it is unenforceable. Fla.Stat. s. 713.31(2)(b). Additionally, an owner (or contractor, subcontractor, etc. that suffers damage from a fraudulent lien) can assert a claim for damages against the lienor for recording the fraudulent lien:

 

An owner against whose interest in real property a fraudulent lien is filed, or any contractor, subcontractor, or sub-subcontractor who suffers damages as a result of the filing of the fraudulent lien, shall have a right of action for damages occasioned thereby. The action may be instituted independently of any other action, or in connection with a summons to show cause under s. 713.21, or as a counterclaim or cross-claim to any action to enforce or to determine the validity of the lien. The prevailing party in an action under this paragraph may recover reasonable attorney’s fees and costs. If the lienor who files a fraudulent lien is not the prevailing party, the lienor shall be liable to the owner or the defrauded party who prevails in an action under this subsection in damages, which shall include court costs, clerk’s fees, a reasonable attorney’s fee and costs for services in securing the discharge of the lien, the amount of any premium for a bond given to obtain the discharge of the lien, interest on any money deposited for the purpose of discharging the lien, and punitive damages in an amount not exceeding the difference between the amount claimed by the lienor to be due or to become due and the amount actually due or to become due.”

Fla.Stat. 713.31(2)(c).

 

 

A lien will be fraudulent if it contains willfully exaggerated amounts which can include liening for amounts that are NOT properly lienable. See Coconut 41, supra, at *15. This is why it is imperative to consult an attorney before recording a claim of lien! Not spending the due diligence in advising an attorney of the facts and the accounting comprising the amount you want to lien for can result in a fraudulent lien. Also, because a fraudulent lien contains a willful exaggeration of amounts, the lienor’s consultation with its lawyer is a factor a court can consider to determine that there was no willful exaggeration. Id. “[A] lienor can rely on consultation with counsel prior to filing the claim of lien as evidence of good faith only in the event of a full and complete disclosure of the pertinent facts to the attorney from whom the advice is sought before the lienor acts on the advice. Consultation with an attorney is not entitled to any legal weight if the contractor did not disclose all pertinent facts to the attorney.” Id. quoting Sharrard v. Ligon, 892 So.2d 1092, 1097 (Fla. 2d DCA 2004). Notably, this means that if a lienor is using this defense to counteract a fraudulent lien claim /defense, certain discussions with counsel must be waived to establish the consultation and advice to show the lien and amount was recorded and compiled in good faith.

 

Here, the contractor recorded a single claim of lien that included Development Area 2. However, the entire lien amount did NOT pertain to infrastructure improving Development Area 2.

 

The Middle District pointed out that a single claim of lien was not proper because the property liened was owned by different owners. Florida Statute s. 713.09 discusses the concept of a single claim of lien:

 

A lienor is required to record only one claim of lien covering his or her entire demand against the real property when the amount demanded is for labor or services or material furnished for more than one improvement under the same direct contract. The single claim of lien is sufficient even though the improvement is for one or more improvements located on separate lots, parcels, or tracts of land. If materials to be used on one or more improvements on separate lots, parcels, or tracts of land under one direct contract are delivered by a lienor to a place designated by the person with whom the materialman contracted, other than the site of the improvement, the delivery to the place designated is prima facie evidence of delivery to the site of the improvement and incorporation in the improvement. The single claim of lien may be limited to a part of multiple lots, parcels, or tracts of land and their improvements or may cover all of the lots, parcels, or tracts of land and improvements. In each claim of lien under this section, the owner under the direct contract must be the same person for all lots, parcels, or tracts of land against which a single claim of lien is recorded.”

 

For this reason, the Middle District found that the lien was willfully exaggerated. In other words, the contractor acknowledged that of its approximate $195,000 lien, the pro-rata share for work done on Development Area 2 was only approximately $61,000; thus, there was an exaggeration of over $100,000 in the lien that covered Development Area 2. “The Claim of Lien was for the total amount owing for offsite work even though Westwind Contracting knew that only a substantially lesser amount was apportionable to HG Coconut.” Coconut 41, supra, at *16. Although the contractor tried to counteract the fraudulent lien by testifying that it provided its counsel with certain information, there was no testimony that it advised counsel that the lien it wanted recorded included land owned by someone other than the entity that hired it.

 

Now, even though the lien was deemed unenforceable, HG Coconut still needed to prove its damages due to the fraudulent lien. The Middle District, however, found that HG Coconut failed to prove such damages. Remember, the damages are included in Section 713.21: “court costs, clerk’s fees, a reasonable attorney’s fee and costs for services in securing the discharge of the lien, the amount of any premium for a bond given to obtain the discharge of the lien, interest on any money deposited for the purpose of discharging the lien, and punitive damages in an amount not exceeding the difference between the amount claimed by the lienor to be due or to become due and the amount actually due or to become due.” HG Coconut did NOT put any evidence of the court costs, reasonable attorneys’ fees, bond premium, or punitive damages.

 

C. Slander of Title

 

In addition to asserting an affirmative claim for fraudulent lien, HG Coconut also asserted a claim against the contractor for slander of title based on the lien. This is a common claim when a party believes a lien was improperly recorded against their property. The elements of slander of title in Florida are: 1) a falsehood, 2) that has been published or communicated to a third party, 3) the defendant knew or should have known the falsehood would result in inducing others not to deal with the plaintiff, 4) the falsehood does result in others not dealing with the plaintiff, and 5) actual and/or special damages (inclusive of attorneys’ fees) are proximately caused by the falsehood. Coconut 41, supra, at *17 quoting McAllister v. Breakers Seville Ass’n, Inc., 981 So.2d 566, 574 (Fla. 4th DCA 2008). However, even if all of the elements above are proven, a defense to slander of title is good faith. Coconut 41, supra, at *18. This defense is important because good faith raises a privilege and shifts the burden to the plaintiff asserting the claim to prove actual malice in order to recover under a slander of title theory of liability. Id. quoting McAllister v. Breakers Seville Ass’n, Inc., 981 So.2d 566, 574 (Fla. 4th DCA 2008).

 

Here, the court did not need to delve into whether there was actual malice because HG Coconut did not prove the elements of slander of title. In particular, there was no evidence that the lien caused or induced anyone not to deal with HG Coconut or that the contractor should have known the lien would have that effect. Further, there was no evidence that HG Coconut incurred any actual and/or special damages caused by the lien. While HG Coconut clearly incurred attorneys’ fees, it did not put on any evidence as to the amount of fees it incurred.

 

III.  Important Take-Aways

 

Below are important points to take-away from this case:

 

  • Unjust enrichment is a claim that can be asserted if a contractor is not in contractual privity with the owner of the land and work was knowingly performed that conferred a benefit to the owner’s land
  • An owner can offset damages in an unjust enrichment claim by asserting as a defense that the work was incomplete/ the contractor failed to fully perform its work
  • A notice to owner is not required for subdivision improvements
  •  If a lien for subdivision improvements includes multiple parcels of land, it shall be prorated among the parcels (if not otherwise stated in the contract)
  • A single claim of lien can cover different land/ parcels if the owner is the same person
  • If there are multiple contracts, there should be separate liens for each contract (even if with the same owner)
  • A fraudulent lien includes a willful exaggeration and can include amounts not properly lienable
  • A party asserting a fraudulent lien needs to present evidence of its damages: attorneys’ fees, court costs, bond transfer costs, punitive damages, etc. to be entitled to damages due to the fraudulent lien
  • Consultation will a lawyer is a defense to a fraudulent lien but all of the important communications with the lawyer regarding the formation and compilation of the lien must be waived and must come into evidence to establish the good faith basis of the lien and lien amount
  • Slander of title is a difficult claim to prove based on a construction lien; the plaintiff must show defendant knew the lien would result in third parties not dealing with the plaintiff and, in fact, third parties did not deal with plaintiff because of the lien
  • A plaintiff in a slander of title action must prove its actual and/or special damages and special damages can include attorneys’ fees
  • A defendant in a slander of title action should assert good faith as a defense which would shift the burden to the plaintiff to prove actual malice

 

For more information on fraudulent liens and slander of title, please see: https://floridaconstru.wpengine.com/owners-defending-a-lien-especially-a-patently-fraudulent-lien/

 

For more information on liens and lienable items/ amounts, please see: https://floridaconstru.wpengine.com/the-final-furnishing-date-and-lienable-amounts-for-construction-liens-decided-on-a-case-by-case-basis/

 

For more information on unjust enrichment theories, please see: https://floridaconstru.wpengine.com/subcontractors-and-unjust-enrichment-claims/

and

https://floridaconstru.wpengine.com/the-reality-when-the-construction-lender-forecloses/

 

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.