DON’T DO THIS WHEN IT COMES TO CONSTRUCTION LIENS

When it comes to preparing and recording a construction lien, this case is an example of what NOT TO DO!   I mean it — this exemplifies what NOT TO DO!  It is also a case study of why a party should always work with counsel in preparing a construction lien so that you can avoid the outcome in this case–your lien being deemed fraudulent.

In Witters Contracting Company v. West, 2020 WL 4030845 (Fla. 2d DCA 2020), homeowners hired a contractor to renovate their home under a cost-plus arrangement where the contractor was entitled to a 10% fee on construction costs.  The contract also required extra work to be agreed in writing between the owner and contractor.

During construction a dispute arose.  The contractor texted the owner that it will cancel the permit and record a $100,000 construction lien if the owner did not pay it $30,000.   Shortly thereafter, the contractor’s counsel sent the homeowners a demand for $59,706 with back-up documentation.  Less than a week later, the contractor recorded a construction lien for $75,000.  The owners initiated a lawsuit against the contractor that included a claim for fraudulent lien.  The contractor then amended its construction lien for $87,239.

The trial court found that the contractor’s claim of lien was fraudulent because it was compiled “with such gross negligence as to the amount claims therein to constitute willful exaggerations.”   A trial was held on damages and $87,239 was awarded as punitive damages against the contractor, plus attorney’s fees and costs, all of which were permissible when a lien is deemed to be a fraudulent lien.

Think about it.  The contractor asked for $30,000 under the threat it will record a $100,000 lien.  It then sent a demand letter for $59,706.  Then it recorded a construction lien for $75,000.  Then it amended the construction lien to $87,239.  This was all in a very short time period.  And, this is likely why the lien was deemed to have been compiled with such gross negligence as the contractor, evidently, had no clue what he was owed under the cost-plus contract or, if he did, he went about it incorrectly.  It is possible the contractor was owed something, but the manner in which he went about it created the wrong perception.  It is unclear whether his counsel was involved in preparing the lien or why the lien was different from the amount in the demand letter sent by counsel.  Nevertheless, clearly, this is the perception you want to avoid and why working with counsel in preparing a lien is vital.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

VALUE IN RECORDING LIEN WITHIN EFFECTIVE NOTICE OF COMMENCEMENT

Construction lien priority is no joke!   This is why a lienor wants to record its construction lien within an effective notice of commencementA lien recorded within an effective notice of commencement relates back in time from a priority standpoint to the date the notice of commencement was recorded.  A lienor that records a lien wants to ensure its lien is superior, and not inferior, to other encumbrances.  An inferior lien or encumbrance may not provide much value if there is not sufficient equity in the property. Plus, an inferior lien or encumbrance can be foreclosed.

An example of the importance of lien priority can be found in the recent decision of Edward Taylor Corp. v. Mortgage Electronic Registration Systems, Inc., 45 Fla.L.Weekly D1447b (Fla. 2d DCA 2020). In this case, a contractor recorded a notice of commencement for an owner.  While an owner is required to sign the notice of commencement that the contractor usually records, in this case, the owner did not sign the notice of commencement.  Shortly after, the owner’s lender recorded a mortgage and then had the owner sign a notice of commencement and this notice of commencement was also recorded.  When there is a construction lender, the lender always wants to make sure its mortgage is recorded first—before any notice of commencement—for purposes of priority and has the responsibility to ensure the notice of commencement is recorded.  Here, the lender apparently did not realize the contractor had already recorded a notice of commencement at the time it recorded its mortgage.

An unpaid subcontractor recorded a lien and foreclosed on the lien.  Because the lien related back in time to the original notice of commencement, the subcontractor moved to foreclose the mortgage as an inferior interest.  (Remember, the mortgage was recorded after the notice of commencement the contractor recorded that was not signed by the owner.)  The lender argued that the notice of commencement was a legal nullity because it was not signed by the owner, therefore, its mortgage had priority.  The trial court agreed with the lender.  The appellate court did not:

[W]e hold that a notice of commencement not signed by the owner, but instead signed by the general contractor with the owner’s authority, is not a nullity, per se, in a lien foreclosure action brought by a subcontractor where the subcontractor has strictly complied with chapter 713 and relies upon the defective notice of commencement, which is otherwise in substantial compliance with section 713.07. In other words, the lender may not use the deficient notice of commencement as a sword against a subcontractor who bears no duty to ensure the validity and accuracy of the notice of commencement.

Edwin Taylor Corp., supra.

This is a good result for a subcontractor that is now in a position to have a lien that is superior to a lender’s mortgage — a situation that rarely occurs and should not occur.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

FORECLOSING JUNIOR LIENHOLDERS AND RECORDING A LIS PENDENS

When you foreclose on a construction lien, there are a couple of pointers to remember.

First, you want to make sure you include junior lienholders or interests you are looking to foreclose (or you want to be in a position to amend the foreclosure lawsuit to identify later).  The reason being is you want to foreclose their interests to the property. “[J]unior interest holders are a narrow class of mortgagees whose interest in the underlying property is recorded after the foreclosing contractor’s claim of lien is filed. This class is routinely joined to the construction lien enforcement action under section 713.26 to allow the construction lienor to foreclose out the junior lienholder’s interest in the property encumbered by the construction lien.” See Decks N Sunch Marine, infra.

Second, you want to record a lis pendens with the lien foreclosure lawsuit.  Failure to do so could be problematic because Florida Statute s. 713.22(1) provides in part, “A lien that has been continued beyond the 1-year period by the commencement of an action is not enforceable against creditors or subsequent purchasers for a valuable consideration and without notice, unless a notice of lis pendens is recorded.”

A recent case, Decks N Such Marine, Inc. v. Daake, 45 Fla.L.Weekly D1168b (Fla. 1st DCA 2020), discusses these pointers.  In this case, a contractor filed a construction lien foreclosure action in 2006 against residential real property. However, the contractor did not record a lis pendens until 2013.  The lis pendens, however, was recorded after the owner had a mortgage recorded on the property.  The contractor amended its construction lien foreclosure action to foreclose the mortgagee claiming the mortgagee was a junior lienholder.  The mortgagee moved for summary judgment pursuant to Florida Statute s. 713.22 arguing the lien was “not enforceable against creditors or subsequent purchasers for valuable consideration and without notice, unless a notice of lis pendens is recorded.”   In other words, the mortgagee was not a lienholder that could be foreclosed in light of the untimely recording of the lis pendens.  The mortgagee prevailed on this issue.

The mortgagee then sought its attorney’s fees against the contractor as the “prevailing party” under Florida Statute s. 713.29 (in Florida’s Lien Law).  The trial court agreed.  The appellate court did not.  The appellate court held that a junior lienholder is not entitled to attorney’s fees under Florida Statute s. 713.29 when prevailing in a construction lien enforcement action.  The contractor is not enforcing its lien against the junior lienholder but “joining it to the underlying action to ensue determination of superiority of liens or security interests upon a foreclosure sale.” Decks N Sunch Marine, supra.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: THE NOTICE OF CONTEST OF LIEN IS A POWERFUL TOOL

If you receive a Notice of Contest of Lien, do NOT ignore it.  The Notice of Contest of Lien is a powerful tool that shortens the limitations period for a linear to foreclose on a construction lien to 60 days or else the lien is discharged by operation of law.   Conversely, if you receive a construction lien, consider recording a Notice of Contest of Lien based on its utility.

As an example of the usefulness of the Notice of Contest of Lien, in Rabil v. Seaside Builders, LLC, 226 So.3d 935 (Fla. 4th DCA 2017), a contractor filed a construction lien foreclosure lawsuit on a residential project.  The homeowners then transferred the lien to a lien transfer bond and recorded a Notice of Contest of Lien.  The contractor did not amend the lawsuit to sue the lien transfer bond surety within the 60-day window.  Consequently, the homeowners moved to dismiss the lien foreclosure lawsuit, release the lien transfer bond, and discharge the corresponding lis pendens.  The trial court denied the motion.  On appeal, the Fourth District reversed holding that “[b]ecause the contractor did not file suit against the surety within sixty days [in response to the Notice of Contest of Lien], the lien was automatically extinguished by operation of law, and the clerk was obligated to release the bond.” Rabil, 226 So.3d at 937.

This case exemplifies the utility of recording a Notice of Contest of Lien and how it benefitted the homeowner upon filing the Notice of Contest of Lien after recording the lien to a lien transfer bond post-initiation of the lawsuit.  The is exactly why a Notice of Contest of Lien should not be ignored.  If you receive one, the smart play is to immediately consult with counsel, just like the smart play if you receive a construction lien is to consult with counsel.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: MAKE SURE TO TIMELY PERFECT YOUR CONSTRUCTION LIEN AND PAYMENT BOND RIGHTS!

In today’s current climate, you do not want to wait until the last minute to record your construction lien or serve your notice of nonpayment to preserve your payment bond rights.  Operate conservatively and preserve these rights now, not later.   Whether preserving construction lien or payment bond rights, the key date is 90-days from your final furnishing date.  A construction lien must be recorded within 90 days from your final furnishing date.  Likewise, a notice of nonpayment (to preserve payment bond rights on a private project) needs to be served within 90 days from your final furnishing date.

It is important to remember that performing punchlist, warranty, and corrective work does NOT extend your final furnishing date. In other words, do not think you can record a lien or serve your notice of nonpayment within 90 days from completing punchlist or warranty work.  That would be a bad idea.  See, e.g., Delta Fire Sprinklers, Inc. v. Onebeacon Ins. Co., 937 So.2d 695 (Fla. 5th DCA 2006) (performing punchlist items insufficient for extending final furnishing date in order for subcontractor to timely serve its notice of nonpayment).

MAKE SURE TO TIMELY PERFECT YOUR CONSTRUCTION LIEN AND PAYMENT BOND RIGHTS!

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION LIEN FORECLOSURE ACTION MUST BE BROUGHT IN COUNTY WHERE PROPERTY LOCATED

A construction lien foreclosure action is an action against the real property and MUST be brought in the county where the property is located. It is an action concerning subject matter jurisdiction (the jurisdiction of the court to hear the matter) and, thus, can be raised at any time in a proceeding.  If you are looking to foreclose a construction lien, please make sure 1) the lien is recorded in the right jurisdiction and 2) the lien is foreclosed on in the right jurisdiction.

In a recent case, Prime Investors & Developers, LLC v. Meridien Companies, Inc., 2020 WL 355930 (4th DCA 2020), a dispute arose between a general contractor and subcontractor on a hotel project in Miami-Dade County. The general contractor filed suit against the subcontractor for untimely and defective installation in Broward County. The subcontractor counter-sued the general contractor for breach of contract and asserted a claim against the developer of the hotel to foreclose a construction lien. Remember, the property was located in Miami-Dade County but the lawsuit was in Broward County.

The trial court granted summary judgment in favor of the subcontractor and against the developer and contractor. The trial court entered a money judgment against the contractor and the developer, but did not initiate any foreclosure proceedings.

The appellate court reversed the summary judgment because there were genuine issues of material fact. The subcontractor, in its motion for summary judgment, did not address the general contractor’s affirmative defenses. (“When a party raises affirmative defenses, a summary judgment should not be granted where there are issues of fact raised by the affirmative defenses which have not been effectively factually challenged and refuted. The movant must disprove the affirmative defenses or show they are legally insufficient.”). Prime Investors & Developers, LLC, 2020 WL at *4 (citation omitted).

The appellate court did address the construction lien foreclosure issue by reminding “that “[a] lien against property is in rem, affecting title to the property, and must be brought in the circuit with jurisdiction over the property.Prime Investors & Developers, LLC, 2020 WL at *4 (citation omitted).  In other words, the subcontractor filed the construction lien foreclosure lawsuit in the WRONG jurisdiction. Oops!

However, the appellate court did not seem to challenge the right of the subcontractor to obtain a monetary judgment, absent the foreclosure proceedings, against the developer. While the subcontractor cannot foreclose its construction lien, it may have a basis to obtain a monetary judgment that excludes foreclosure against the developer if it prevails at trial. This is certainly not the same leverage the subcontractor wanted when it recorded the lien and initiated a construction-lien foreclosure.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CIRCUMSTANCES IN WHICH DESIGN PROFESSIONAL HAS CONSTRUCTION LIEN RIGHTS

If you are a design professional (architect, landscape architect, interior designer, engineer, surveyor, or mapper) you have construction lien rights in the event you are not paid.   This does not mean your lien rights are absolute so it is important to understand the circumstances which allow you to record a construction lien on a project.  These circumstances are contained in Florida Statute s. 713.03:

(1) Any person who performs services as architect, landscape architect, interior designer, engineer, or surveyor and mapper, subject to compliance with and the limitations imposed by this part, has a lien on the real property improved for any money that is owing to him or her for his or her services used in connection with improving the real property or for his or her services in supervising any portion of the work of improving the real property, rendered in accordance with his or her contract and with the direct contract.

(2) Any architect, landscape architect, interior designer, engineer, or surveyor and mapper who has a direct contract and who in the practice of his or her profession shall perform services, by himself or herself or others, in connection with a specific parcel of real property and subject to said compliances and limitations, shall have a lien upon such real property for the money owing to him or her for his or her professional services, regardless of whether such real property is actually improved.

The first circumstance pertains to design professionals that do NOT have a direct contract with the owner of the property.  In this circumstance, you have lien rights for your services “used in connection with improving the real property” or your services “in supervising any portion of the work of improving the real property” that you perform under your contract and with the direct contract, presumably between the owner and your client.  The important, operative word in this circumstance involves improving the real property.

The second circumstance pertains to design professionals hired directly by the owner.  In this circumstance, you have broader lien rights as you have lien rights for your services “regardless of whether such real property is actually improved.”  Hence, improving the real property is of no moment.

A design professional does not need to serve any preliminary notice (such as a notice to owner) in order to preserve their lien rights.  However, a design professional still needs to record a construction lien within 90 days from their final furnishing date.

A construction lien from a design professional is less common than a lien from a contractor, subcontractor, or supplier. Nonetheless, design professionals do have construction lien rights that an owner should be cognizant of and a design professional should understand in furtherance of best ensuring payment.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

FILLING OUT THE CONTRACTOR’S FINAL PAYMENT AFFIDAVIT

When preparing a contractor’s final payment affidavit, I always suggest for a contractor (or anyone in privity of contract with the owner) to identify the undisputed amounts their accounting reflects is owed to ALL subcontractors, etc., regardless of whether that entity preserved their lien rights.  If the contractor provided a payment bond, I footnote this simply to support that none of the lower-tiered subcontractors have lien rights or are the traditional “lienor.”   (Thus, there is no prejudice to the owner if an entity is inadvertently omitted from the affidavit.)

There are times, however, where a contractor does not identify a subcontractor that did not serve a notice to owner and, therefore, has no valid lien rights.  Or, a contractor omits a lienor that actually did serve a notice to owner and preserve its lien rights; this happens.

There was an older First District Court of Appeals case that harshly (and, quite, unfairly) held that the contractor must identify everyone in the final payment affidavit regardless of whether that entity timely served a notice to owner or their lien is invalid.  This case, however, predated, a 1998 statutory change to Florida’s Lien Law.

Today, the statute (in Florida Statute s. 713.06) currently provides:

(d) When the final payment under a direct contract becomes due the contractor:

1. The contractor shall give to the owner a final payment affidavit stating, if that be the fact, that all lienors under his or her direct contract who have timely served a notice to owner on the owner and the contractor have been paid in full or, if the fact be otherwise, showing the name of each such lienor who has not been paid in full and the amount due or to become due each for labor, services, or materials furnished….

The contractor shall have no lien or right of action against the owner for labor, services, or materials furnished under the direct contract while in default for not giving the owner the affidavit; however, the negligent inclusion or omission of any information in the affidavit which has not prejudiced the owner does not constitute a default that operates to defeat an otherwise valid lien. The contractor shall execute the affidavit and deliver it to the owner at least 5 days before instituting an action as a prerequisite to the institution of any action to enforce his or her lien under this chapter, even if the final payment has not become due because the contract is terminated for a reason other than completion and regardless of whether the contractor has any lienors working under him or her or not.

Fla. Stat. s. 713.06(d)(1).

The Fourth District Court of Appeals in Fetta v. All-Rite Paving Contractors, Inc., 50 So.3d 1216 (Fla. 4th DCA 2010), claimed that the purpose of the statute is for the contractor to identify all lienors who have timely served a notice to owner that has not been paid in full.  (Hence, you do not need to identify those that did not timely serve a notice to owner even though, from a practical standpoint, identifying all makes sense as a just-in-case.). Further, even if there was an omission, that would not render a lien invalid unless the owner can prove prejudice and prejudice is not so easy to prove.

When in doubt, consult counsel when finalizing or filling out a contractor’s final payment affidavit.  Rights can be preserved and items footnoted as appropriate for clarification purposes, such as the fact that the amount in the affidavit may not include amounts that are not available under the lien law (i.e., delay damages).

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION LIEN DOES NOT INCLUDE LATE FEES SEPARATE FROM INTEREST

Construction liens can include unpaid finance charges.   But, what about late fees?  You know, the late fees that certain vendors like to include in their contract or purchase order unrelated to finance charges.  An added cost for being delinquent with your payment.  Can a late fee be tacked onto the lien too?

In a recent case, Fernandez v. Manning Building Supplies, Inc., 2019 WL 4655988 (Fla. 1st DCA 2019), a residential owner hired a contractor for a renovation job.  The contractor entered into a contract with a material supplier.  The terms of the supplier’s contract with the contractor provided that there would be a 1.5% delinquency charge for late payments and it seemed apparent that the delinquency charge was separate from finance charges.

Florida Statute s. 713.06(1) provides in relevant portion:

A materialman or laborer, either of whom is not in privity with the owner, or a subcontractor or sub-subcontractor who complies with the provisions of this part and is subject to the limitations thereof, has a lien on the real property improved for any money that is owed to him or her for labor, services, or materials furnished in accordance with his or her contract and with the direct contract and for any unpaid finance charges due under the lienor’s contract.

The supplier in this case recorded a construction lien and filed a lien foreclosure lawsuit.  The issue was whether a 1.5% per month “delinquency charge” or late fee, as set forth in the contract, should be factored into the lien amount.   The First District Court of Appeal held no:

[A] ate payment fee is not a “finance charge” as that term is generally understood…[T]he difference between a finance charge and delinquency fee is recognized by Black’s Law Dictionary (10th ed. 2014) which defines a “finance charge” as “[a]n additional payment, usu. in the form of interest, paid by a retail buyer for the privilege of purchasing goods or services in installments.” As such, a finance charge is the cost of credit — not the cost of paying late. The 1.5% fee required by the [the supplier’s] contract is to be paid only upon default; it is not a cost of credit per se.

Fernandez, supra

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

QUICK NOTE: “EFFECTIVE” NOTICE OF COMMENCEMENT

As a contractor (or subcontractor or supplier if an unconditional payment bond is not furnished by the contractor) you always want to make sure (1) there is a notice of commencement that was recorded for the job and (2) you are working under an EFFECTIVE notice of commencement or amended notice of commencement.  An effective notice of commencement is a notice of commencement (or amended notice of commencement that amends an original notice of commencement prior to its expiration) that has not expired and allows your lien to relate back to the date the notice of commencement was originally recorded.

 

In the event you are not paid, you will want to record a construction lien to secure your nonpayment against the property and you will want your lien to relate back in time to the original notice of commencement.   When it comes to liens, a lien is typically only as good as the equity in the property oftentimes dictated by the priority of the lien.  (For example, if the property is worth $1 Million, but there is a $1.1 Million mortgage on the property, there is no equity in the property because the mortgage would have priority over the construction lien.)

 

As an owner, there may be times you want to terminate an EFFECTIVE notice of commencement.  Maybe the job is completed and the notice of commencement is still in effect and you want to cut off lien priority rights.  Maybe you want to convert your construction loan into a permanent loan.  Maybe you want to re-finance.  Maybe you want to secure a construction loan after construction commenced.  Any one of these factors will support recording a notice of termination of the notice of commencement.  When you borrow money from a lender, a lender will typically want their mortgage to be first priority.  This means the mortgage cannot be recorded after an effective notice of commencement otherwise potential liens can take priority over the mortgage.  No lender will want this to occur.

 

It is always advisable to work with counsel when it comes to notices commencement, amended notices of commencement, notices of termination of a notice of commencement, and, of course, construction liens.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.