RISK ASSOCIATED WITH DESIGN-BUILD PROJECT DELIVERY METHOD

The design-build project delivery method is when the design-builder (typically the contractor) is responsible for both the design and construction of the project. Thus, the responsibility for both the design and construction falls under the same umbrella and, naturally, carries more risk. The discussion below demonstrates risk involved in the design-build project delivery method, particularly in the government contracting arena:

Design-build contracts are common for construction, renovations, and repair projects, where the government provides the contractor with its requirements, but the contractor is free to exercise its ingenuity in achieving that objective or standard of performance and selecting the means to do so. It is not uncommon for issues to arise in design-build contracts. One of the more common issues is when the contract describes a certain requirement, but later during the design process, the contractor will submit in the 35% or 100% design submittal with a lower requirement. The government will unknowingly approve that design, not realizing the contractor may have “slipped in” or made an error on one of the requirements; thus, the approved 100% design has a lower requirement as compared to the contract. In these situations, we have found that the government is justified in demanding the contractor provide the requirements specified in the RFP and resulting contract.

Thus, our long-held rule has been that the government cannot properly be blamed for approving the design when the contractor failed to inform the government that its design deviated from Task Order minimum requirements.

Appeals of – Meltech Corporation, Inc., ASBCA No. 61766, 2025 WL 2166133 (ASBCA 2025) (internal citations omitted).

What about the opposite? If the government approves a design that contains components of a HIGHER, not lower, quality?

In a recent appeal with the Armed Services Board of Contracts Appeal, the design-build contractor made a mistake during the design process where it was giving the government a higher quality than required of it in the RFP with the design criteria for the project. (It is typically the opposite where the design-builder gives the government a lower quality than required of it in the RFP.) The design-build contractor sought to substitute the higher quality material for the material required by the RFP. Through the substitution, the government wanted a credit claiming the design-builder should be bound by the 100% design that the government approved with the higher quality material.  The Board, however, did not see it the unfair way the government saw it:

As we have held that the government does not waive RFP requirements when it unwittingly approves a lesser quality design, a contractor’s reasonable mistake should not require it to provide materials above and beyond the contracts requirements. This is an example of a contractor’s mistake during the design-build phase, in which the contractor ultimately provided a finished material at the quality specified in the RFP/Design Criteria. There was no savings by [the design-builder] nor a loss to the government. The equitable adjustment should not increase or decrease the contractors’ loss at the government’s expense. Moreover, the government presented no evidence to the Board that it incurred any costs of significance associated with its review of [the design-builder’s] submittals on these issues. Accordingly, the government has failed to carry its burden of establishing that it is due a deductive credit….

Appeals of – Meltech Corporation, Inc., ASBCA No. 61766, 2025 WL 2166133 (ASBCA 2025) (internal citations omitted).

Thus, while the design-builder cannot skirt its responsibilities by providing a lesser quality than required of it. The government can’t take advantage of the design-builder’s mistake with a higher quality when the higher quality exceeds the benefit of the bargain.

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

SPEARIN DOCTRINE CAN APPLY IN DESIGN-BUILD CONTEXT

The Spearin doctrine is a doctrine in the construction industry that broadly means the owner impliedly warrants the constructability of the plans and specifications given to the contractor. This implied warranty attaches to a design specification, but not a performance specification. A question arises as to whether the Spearin doctrine can apply in the design-build context where the contractor is responsible for both the design and construction.  It can, as discussed in the case below.

In Balfour Beatty Construction, LLC v. Administrator of the General Services Administration, 2025 WL 798865 (Fed. Cir. 2025), a design-build contractor appealed a decision from the Civilian Board of Contract Appeals (Board) claiming it was entitled to recover for design errors in the government’s bridging documents. In other words, the contractor claimed there was a design defect in the government’s bridging documents and, pursuant to the Spearin doctrine, the government should be liable for the contractor’s increased costs.

Often, in a design-build solicitation, there are bridging documents which are basically conceptually design documents as to what the government is looking for with the objective for the design-build contractor to complete the design. There is oftentimes a disclaimer reflecting the preliminary or conceptual nature of the bridging documents and that they are not intended to describe the full scope of the design or the work.

Here, the design-build contractor submitted a claim for increased costs due to design errors based in the bridging documents.  One issue dealt with claimed design defects with the mat slab foundation in the bridging documents. The contractor argued it needed to “redesign and depart from the bridging documents to accommodate a thicker mat slab, which was required to handle the loads of the equipment and bridging columns.” Balfour Beatty, supra, at *2.

Regarding the Spearin doctrine:

In United States v. Spearin, the Supreme Court held that “if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications.” We have since clarified that this implied warranty attaches in contracts that contain design specifications, which “explicitly state how the contract is to be performed and permit no deviations.” But if the contract contains a performance specification, which specifies the result to be obtained but leaves the contractor free to determine how to achieve those results, the implied warranty does not attach.

In a design-build bridging project delivery method, the government provides a partial design with the expectation that the contractor will complete the design and build the project. The Board analyzed the provisions of the contract and“consider[ed] to what extent a thirty-percent design … was design or performance.” The Board determined that the bridging documents did not contain a warranty for the design of the mat slab at a particular thickness. The Board noted that, in addition to the contract drawing that directed the contractor to match the existing foundation thickness of 18 inches, [the government] provided calculations from [government] consultants that called for a 24-inch foundation. The Board concluded that because these documents “raised a question about the mat slab thickness that should have caused [the contractor] to raise the issue before contract award,” [the contractor] was not entitled to recover costs related to designing the thicker mat slab. We disagree.

The contract drawing indicated that [the contractor] should “match existing building foundations,” which were 18 inches thick. We determine the language in the drawing is sufficiently definite to constitute a design specification, and the Board erred in construing this as a performance specification. We conclude that there was an implied warranty with respect to the mat slab thickness. Further, even if there were a conflict between the drawing and the calculations, the mat slab [the contractor] ended up having to build was between 43 and 53 inches thick—almost double what the calculations required.

Balfour Beatty, supra, at *2 (internal citations omitted).

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

UNDERSTAND PROJECT DELIVERY METHODS SO THAT YOU SELECT A METHOD THAT BEST MEETS YOUR NEEDS

There are numerous project delivery methods or a method to deliver an owner the design and construction of a project.  Selecting a project delivery method requires the owner to consider many factors including the 1) project size, complexity, and scope, 2) insurance, 3) emerging technology such as building information modeling, 4) lean construction, 5) sustainability, 6) risk allocation, 7) control, 8) internal resources, 9) budget, 10) schedule, 11) contractor input during preconstruction, 12) risk allocation, 13) dispute resolution, and 14) collaboration amongst ownership, the design team, and the construction team. After carefully considering all of these factors, the objective is for an owner to select the project delivery method that will best bring it value including allocating responsibility of the design and construction to those best equipped to manage and handle that responsibility.  Learn more about the following project delivery methods by analyzing  considerations and perspectives of each method in the attached primer:

 

1. Design-bid-build

2. Multi-prime

3. Design-build

4. CM-agency

5. CM-at risk

6. Integrated project delivery

7. Public private partnership

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2016/02/Project-delivery-handout.pdf”]

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSULTANTS’ COMPETITIVE NEGOTIATION ACT (“CCNA”) PRIMER


Florida Statute s. 287.055 is known as the Consultants’ Competitive Negotiation Act (“CCNA”).  This Act governs a public entity’s acquisition of professional architectural, engineering, landscape architecture, and surveying and mapping services.  Applicable here, it indirectly applies to the procurement of design-build contracts for public projects in excess of $325,000.  It also applies to the procurement of construction management contracts for public projects in excess of $325,00. See Fla. Stat. s. 255.103(2) (“A governmental entity may select a construction management entity, pursuant to the process provided by s. 287.055, which is to be responsible for schedule control, cost control, and coordination in providing or procuring, planning, design, and construction services.”)

 

First, the CCNA contains a competitive selection process as follows:

  • Public body shall evaluate current statements of qualifications and performance date on file, together with those that may be submitted by other firms regarding the project, and may require public presentations by no fewer than 3 firms regarding the firm’s qualifications, approach to the project, and ability to furnish the professional services;
  • Public body shall select in order of preference no fewer than 3 firms deemed the most qualified.  Public body shall consider qualification factors such as “ability of professional personnel; whether a firm is a certified minority business enterprise; past performance; willingness to meet time and budget requirements; location; recent, current, and projected workloads of the firms; and the volume of work previously awarded to each firm by the agency, with the object of effecting an equitable distribution of contracts among qualified firms, provided such distribution does not violate the principle of selection of the most highly qualified firms.”

*Public body may request, accept, and consider proposals for compensation to be paid only during the competitive negotiation process.

 

Second, the CCNA contains a competitive negotiation process:

  • Public body shall negotiate contract with the most qualified firm at compensation public body determines is fair, competitive, and reasonable. “In making such determination, the agency shall conduct a detailed analysis of the cost of the professional services required in addition to considering their scope and complexity.”
  • If Public body unable to negotiate satisfactory contract with firm it considers most qualified at compensation it determines to be fair, competitive, and reasonable, public body shall terminate negotiations with this firm and move on to the second most qualified firm.  (If public body cannot negotiate fair, competitive, and reasonable compensation with this firm, public body shall terminate negotiations and move on to third most qualified firm.)

 

With respect to design-build contracts, municipalities, political subdivisions, school districts, and school boards can either select design-builder based on above qualifications process(**) or can use competitive proposal selection process with the following minimum procedures:

  • Public body must prepare design criteria package. (“The purpose of the design criteria package is to furnish sufficient information to permit design-build firms to prepare a bid or a response to an agency’s request for proposal, or to permit an agency to enter into a negotiated design-build contract. The design criteria package must specify performance-based criteria for the public construction project, including the legal description of the site, survey information concerning the site, interior space requirements, material quality standards, schematic layouts and conceptual design criteria of the project, cost or budget estimates, design and construction schedules, site development requirements, provisions for utilities, stormwater retention and disposal, and parking requirements applicable to the project.”)
  • Selection of no fewer than 3 design-build firms as most qualified “based on the qualifications, availability, and past work of the firms, including the partners of members thereof.”
  • Evaluation criteria for evaluating design-build contractor proposals “based on price, technical, and design aspects of the public construction project, weighted for the project.”
  • Solicitation of competitive proposals from those qualified design-build firms and evaluation of responses from those firms based on evaluation criteria.

** If public body “elects the option of qualifications-based selection, during the selection of the design-build firm the procuring agency shall employ or retain a licensed design professional appropriate to the project to serve as the agency’s representative.”

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

GENERAL UNDERSTANDING OF CONSTRUCTION PROJECT DELIVERY METHODS


Ever hear the expression, “there are many ways to skin a cat?”  Of course you have!  Well, this expression can apply to construction as there are many ways to build a project to accomplish the same objective–to deliver a completed project.  

 

The various ways projects are delivered are oftentimes referred to as construction project delivery methods.  Such delivery methods can be the traditional method of design-bid-build to the much more sophisticated and collaborative delivery mthod of integrated project delivery (“IPD”) to the method aimed at delivering needed public projects (such as infrastructure) known as the public private partnership (“P3”). 

 

Below is a basic presentation illustrating the following construction project delivery methods:

1)   design-bid-build

2)   design-bid

3)   construction manager at-risk

4)   integrated project delivery (“IPD”) and

5)   public private partnership (“P3”).

Check out the presentation to get a general understanding of the highlights of each of these project delivery methods.

[gview file=”https://floridaconstru.wpengine.com/wp-content/uploads/2015/08/project-delivery-methods.pdf”]

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

DESIGN-BUILD PROJECT DELIVERY IN FLORIDA (AND LICENSING EXEMPTIONS)

Under a design-build project delivery, typically the general contractor contracts with the owner to be responsible for both the design and construction of the project.  This benefits the owner because if there is a design or construction issue–whether causing an increase in budget, a defect, or a delay–the owner can point to the contractor since it is the entity responsible for both disciplines.  This benefits the contractor (in addition to the owner) because it is now working closely with the design professional so their interests are aligned and the contractor can have more control over value engineering or cost savings implementation and obtaining answers to requests for information or approvals to submittals and shop drawings.  Since the contractor is fully accountable for both the design and construction, it is working closely and collaborating with the design professionals to improve the efficiency in the construction process. Furthermore, since the contractor is responsible for the design, it has more flexibility fast-tracking the construction in phases even though the complete design is not finalized.  By fast-tracking the construction and overlapping the construction with the design, the contractor is ideally in a position to efficiently meet scheduling and production requirements.

 

 

A contractor is able to offer and perform design-build services because there is an exemption under the required licensing statutes for a contractor, architect, and engineer that allow these entities to negotiate / contract for design-build work as long as they are engaging a licensed professional to perform those tasks in which they are not licensed.  For instance, a contractor is exempt from the requirement of being a licensed architect when contracting and offering design-build work as long as the contractor engages a licensed architect to perform the design. This is set forth in Florida Statute s. 481.229(3) that provides:

 

“Notwithstanding the provisions of this part, a general contractor who is certified or registered pursuant to the provisions of chapter 489 is not required to be licensed as an architect when negotiating or performing services under a design-build contract as long as the architectural services offered or rendered in connection with the contract are offered and rendered by an architect licensed in accordance with this chapter.”

 

 

Similarly, while less common, an architect or engineer is exempt from the requirement of being a licensed contractor when contracting and offering design-build work as long as these design professionals engage a licensed contractor to perform the construction.  This is set forth in Florida Statute s. 489.103(16) that provides:

 

 “An architect or landscape architect licensed pursuant to chapter 481 or an engineer licensed pursuant to chapter 471 who offers or renders design-build services which may require the services of a contractor certified or registered pursuant to the provisions of this chapter, as long as the contractor services to be performed under the terms of the design-build contract are offered and rendered by a certified or registered general contractor in accordance with this chapter.” 

 

Despite these exemptions, recently the Florida Board of Architecture and Interior Design in Diaz & Russell Corp. v. Department of Business and Professional Regulation,  39 Fla. L. Weekly D 1125a (Fla. 3d DCA 2014), charged a general contractor for improperly performing services as an architect (when it was not a licensed architect) simply because the general contractor was offering design-build services.  Basically, the Florida Board of Architecture maintained that the contractor needed to identify the designated architect in its proposal to the owner offering the architectural services.  On appeal, the Third District Court of Florida correctly reversed this ruling because there is nothing that requires the contractor to identify the architect or engineer at the time of the proposal / contract just like there is nothing requiring the architect or engineer to identify the contractor at the time of the proposal / contract.  The statutory exemption would simply require the contractor to engage a licensed architect to perform the design, which was not an issue in this case because the contractor properly hired an architect to prepare the design.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.