QUICK NOTE: DON’T FORGET TO SERVE THE CONTRACTOR FINAL PAYMENT AFFIDAVIT

If you are a contractor in DIRECT CONTRACT with an owner, serve a contractor final payment affidavit on the owner, as a matter of course, and without any undue delay, particularly if you are owed money and have recorded a construction lien.  In numerous circumstances, I like to serve the contractor final payment affidavit with the construction lien.

 

The contractor final payment affidavit is not a meaningless form.  It is a statutory form (set forth in Florida Statute s. 713.06) required to be filled out by a lienor in direct privity of contract with an owner and served on the owner at least 5 days prior to the lienor foreclosing its construction lien.  The contractor final payment affidavit serves as a condition precedent to foreclosing a construction lien.  Failure to timely serve a contractor final payment affidavit should result in a dismissal of the lien foreclosure lawsuit, presumably by the owner moving for a motion for summary judgment.  This should not occur.  

 

I always suggest working with a lawyer to finalize a contractor final payment affidavit (as well as the lien in order to utilize the advice of counsel defense) for two reasons.  First, you will ideally want the amount in the affidavit to be the same as the lien amount.  Second, you may want to include certain clarifications or exceptions in the final payment affidavit for amounts not included in the lien (e.g., delay-type damages or certain disputed change orders that you do not feel comfortable including in the lien).  

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

QUICK NOTE: REMEMBER TO TIMELY FORECLOSE LIEN AGAINST LIEN TRANSFER BOND

When a construction lien is transferred to a lien transfer bond pursuant to Florida Statute s. 713.24, instead of foreclosing the lien against the real property, you are foreclosing the lien against the lien transfer bond.  This is not a bad deal and, oftentimes, is probably ideal.   Remember, however, just because a construction lien was transferred to a lien transfer bond (pre-lawsuit) does not mean you get more time to file your lien foreclosure lawsuit.  A lawsuit must still be filed within one year (short of that period being specifically shortened under operation of the law).  The only exception is that if the lawsuit is filed and the lien transfer bond is then recorded (post-lawsuit), the lienor has one year to amend its lawsuit to sue the lien transfer bond.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

 

PAROL EVIDENCE CAN BE USED TO DEFEAT FRAUDULENT LIEN

shutterstock_162610553Parol or extrinsic evidence can be used to defeat an argument that a lien is a fraudulent lien.  And, just because a lien amount exceeds the total contract amount does not presumptively mean the lien is willfully exaggerated or recorded in bad faith.  Finally, a ruling invalidating a construction lien can create the irreparable harm required to support a petition for writ of certiorari.  All of these issues are important when dealing with and defending against a fraudulent lien and are explained in a recent case involving a dispute between an electrical subcontractor and its supplier.

 

In Farrey’s Wholesale Hardware Co., Inc. v. Coltin Electrical Services, LLC, 44 Fla.L.Weekly D130a (Fla. 2d DCA 2019), there were various revisions to the supplier’s  initial purchase order, both from a qualitative and quantitative perspective, and a ninth-revised purchaser order was issued and accepted.  The electrical subcontractor claimed that deliveries were late, unassembled, and did not include the required marking (likely the UL marking), to pass building inspections.  As a result, the subcontractor withheld money from the supplier and the supplier recorded a lien in the amount of $853,773.16 and filed a foreclosure lawsuit.

 

The subcontractor moved for a motion for partial summary judgment that the lien should be deemed a fraudulent lien and invalid because it was overstated by approximately $32,000.  The subcontractor argued that taking the amount of the ninth-revised purchase order and deducting the undisputed amount paid to the supplier would result in a lien amount of $825,417.06, approximately $32,000 less than the supplier’s lien amount.  The supplier, through an affidavit, argued this delta is nothing more than a good faith dispute and can be explained because the total cost of materials furnished to the job site was based on its initial purchase order and its revised purchase order.  The subcontractor countered that the affidavit is  parol evidence and should be disregarded because the parties agreed on the total amount of the supplies through the ninth-revised purchase order and the supplier was trying to create a new contract through the affidavit.  The trial court agreed and found the lien fraudulent, and issued a partial summary judgment invalidating the supplier’s lien.  The subcontractor moved for a petition of writ of certiorari.

 

Parol Evidence Rule

 

“[T]he parol evidence rule prevents the terms of a valid written contract or instrument from being varied ‘by a verbal agreement or other extrinsic evidence where such agreement was made before or at the time of the instrument in question.’” Farrey’s Wholesale, supra(citation omitted). The parol evidence rule, however, is not applied to exclude evidence of subsequent agreements modifying the original agreement, or of fraud, accident, or mistake.  Id.  

 

The appellate court, reversing the trial court, found that the parol evidence rule “does not bar extrinsic evidence offered for the purpose of showing whether the filing of a construction lien was made in good or bath faith.  This is a separate and distinct inquiry that does not trigger the parol evidence rule.”   Hence, the appellate court maintained there were disputed issues of material fact as to whether the lien was fraudulent.

 

The appellate court further found that the trial court erred in finding the lien fraudulent in that just because the lien amount exceeded the ninth-revised purchase order does not mean it was willfully exaggerated.  In other words, even if the ninth-revised purchase order was the complete agreement, the lien, in of itself, is not willfully exaggerated just because the lien exceeded the total amount of the contract. 

 

Appeal of Lien

 

On another important point in this case, because the appeal was based on a writ of certiorari (versus a final appeal of a final dispositive judgment), there had to be irreparable harm to justify the basis of the appeal.  The appellate court held there would be irreparable harm if the supplier had to wait until the end of the litigation to appeal because its judgment would then be unsecured (it would be without a remedy to pursue its lien which had been transferred to a lien transfer bond).  See Farrey’s Construction Wholesale, supra  (“This means that on remand [back to the trial court], all matters pertaining to Farrey’s construction lien, which includes the status of the lien transfer bond, will be returned to their prejudgment postures.”). 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

TERMINATING NOTICE OF COMMENCEMENT WITHOUT CONTRACTOR’S FINAL PAYMENT AFFIDAVIT

shutterstock_399902515Prior to construction work being performed on your property, a Notice of Commencement should be recorded.  Among other things, construction liens will relate back in time to an effective Notice of Commencement (meaning it has not expired).  For this reason, lenders or others will want the Notice of Commencement to be terminated when the job is complete by recording in the official records a Notice of Termination of the Notice of Commencement.  There is a statutory procedure to terminate a Notice of Commencement pursuant to Florida Statute 713.132.  

 

Frequently, a clerk will want the Notice of Termination of the Notice of Commencement to be accompanied with a Contractor’s Final Payment Affidavit because 713.132 says, in material part:

 

(2) An owner has the right to rely on a contractor’s affidavit given under s. 713.06(3)(d), except with respect to lienors who have already given notice, in connection with the execution, swearing to, and recording of a notice of termination. However, the notice of termination must be accompanied by the contractor’s affidavit.

 

Notwithstanding, the Fifth District in Lasalle Bank National Ass’n v. Blackton, Inc., 59 So.3d 329, 331 (Fla. 5th DCA 2011) in interpreting this subsection stated:

 

We interpret this subsection to grant an owner the right to rely on the a contractor’s affidavit as an alternative to giving a sworn statement in its notice of termination that “all lienors have been paid in full.”  Here, the contractor’s affidavit attached to the notice of termination was superfluous because Independence, as owner, had already averred in the notice of termination that all lienors had been fully paid. 

 

 

It is always beneficial for an owner to obtain and rely on the Contractor’s Final Payment Affidavit since the contractor would be the one to hire the subcontractors  and know whether all lienors (including itself) have been fully paid and, if not, those that are still owed money.  However, there are times an owner may not be able to get that affidavit for a host of reasons (for example, if the job never actually commenced or the contractor is uncooperative in this regard).   In these circumstances, the owner should be able to record the Notice of Termination of the Notice of Commencement absent the Contractor’s Final Payment Affidavit by averring in the Notice of Termination that all lienors have been paid.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

PRE-SUIT SETTLEMENT OFFERS AND CONSTRUCTION LIEN ACTIONS

shutterstock_127849640It is unfortunate, but in certain matters, a construction lien foreclosure action is not actually driven by the principal amount in dispute.  Oh no.  Rather, it is driven by attorney’s fees.  That’s right.  Attorney’s fees. This is true even though Florida applies the significant issues test to determine the prevailing party for purposes of attorney’s fees.  However, oftentimes  the prospect of attorney’s fees is enough for parties to fear that exposure. 

 

There is a 1985 Florida Supreme Court case that I like to cite if applicable, C.U. Associates, Inc. v. R.B. Grove, Inc., 472 So.2d 1177, 1179 (Fla. 1985), that finds, “in order to be a prevailing party entitled to the award of attorney’s fees pursuant to section 713.29 [a construction lien claim], a litigant must have recovered an amount exceeding that which was earlier offered in settlement of the claim.”  Accord Sullivan v. Galske, 917 So.2d 412 (Fla. 2d DCA 2006) (explaining that although contractor is receiving a judgment in his favor, he may not be the prevailing party if the homeowner offered to settle prior to the lawsuit for an amount equal to or greater  than the award in the judgment).

 

If there is a pre-suit settlement offer on the table, and it is a good faith offer (which presumably it is), than that offer can very well come into play to determine whether the party that will the action should be deemed the prevailing party for purposes of attorney’s fees.  This is still good law.  Therefore, before readily dismissing a pre-suit offer, consider the potential ramifications if you are unable to beat this offer at trial. Banking on attorney’s fees may not be prudent if there is a pre-suit offer that is within striking distance from where you need to be or can very well be a likely outcome based on a reasonable argument raised by the opposing party.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

CONSTRUCTION LIEN NEEDS TO BE RECORDED WITHIN 90 DAYS FROM LIENOR’S FINAL FURNISHING

shutterstock_239963452A lienor needs to record its construction lien within 90 days of its final furnishing dateThis final furnishing date excludes punchlist, warranty, or the lienor’s own corrective work.   A lien recorded outside of ths 90-day window will be deemed invalid.

 

The opinion in In re: Jennerwein, 309 B.R. 385 (M.D. Fla. 2004) provides a good discussion of this 90-day window.  This matter dealt with a debtor / owner’s bankruptcy where the owner was contesting the validity of a construction lien by its pool contractor.  The owner contended that the lienor’s lien was recorded outside of this 90-day window thus rendering the lien invalid.  The bankruptcy court was determining the validity of the lien.

 

In this matter, the owner hired a swimming pool contractor to construct a pool.  On October 25, 2002, the pool contractor installed pavers around the pool.  After this was performed, the pool contractor realized the owner was unable to obtain the financing to pay for the pool.  As a result, the pool contractor ceased doing any more improvements.  But, neither the pool contractor nor the owner terminated the contract.  Then, on November 27, 2002, the pool contractor sent a supervisor to the property to inspect the pool (work-in-place), the pool equipment, the installed pavers, made a list of the unfinished work, and remove any debris.  On January 27, 2003, the pool contractor recorded its lien.

  

The issue is that if the last day the pool contractor did work was on October 25, 2002 which is when it installed the pavers (the final furnishing date), then the lien it recorded on January 27, 2003 was not timely.  The lien was recorded more than 90 days from October 25, 2002.  However, if the last day the pool contractor did work was on November 27, 2002 when it sent a supervisor to inspect the work and remove debris, then the lien was timely as it was recorded within the 90-day window.

 

In Florida, the test to determine whether labor, services, or materials were furnished is whether the work was: (i) performed in good faith; (ii) within a reasonable time; (iii) in pursuance of the terms of the contract; and, (iv) whether the work was necessary to a “finished job.”… The application of this fairly straight- forward four step test is fact driven, and the facts of each construction project vary widely.

In re: Jennerwein, 309 B.R. at 388.

 

The Bankruptcy Court applied this four step test to determine whether the pool contractor’s inspection / visit on November 27, 2002 constituted its final furnishing date.  Based on the facts, the Court held that November 27, 2002 did constitute a final furnishing date meaning the lien was valid.   Although the pool contractor’s visit on this day was limited, the contract was still in effect (i.e., it was not terminated).  The pool contractor was operating in good faith and the supervisor was conducting his normal job duties by checking on the status of the work. This visit was also deemed to occur within a reasonable time after the pavers were installed. Although the project remained idle after the pavers were installed, this was because the owner was trying to find financing to pay for the work.  Further, the supervisor’s inspection was performed in pursuance of its work and the contract.  Without a list as to the work that remained to be completed, the contractor would not have a schedule of work and materials needed to finish its job.

 

This factual-based finding is favorable to a lienor.  Between the October 25, 2002 date the pavers were installed and the November 27, 2002 date the supervisor visited the property, there was no work.  The pool contractor stopped work because it was not getting paid and it obviously did not want to perform more work knowing that work was not going to get paid for.  However, neither party formally terminated the contract.  The supervisor’s visit was nothing more than confirming the work it performed versus the work it did not perform and remove any debris, etc., that remained on the job.  In other words, the pool contractor was leaving based on the non-payment.  However, the Court deemed the visit to be in good faith and pursuant to the contract allowing this date to be deemed a final furnishing date.  That is a favorable finding when, in reality, the last date the lienor physically improved the property was a month earlier when the pavers were installed.

 

The final furnishing date, as you can tell, will be a fact-based determination.  And, the four step test will be applied to determine the merits of the final furnishing date.  However, I always try to operate conservatively; it is always safer to record the lien sooner than later to take away any close-call argument that the lien should be invalid because it was recorded outside of the 90-day window.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

ARE YOU A CONSTRUCTION LIENOR?

shutterstock_98314763When it comes to construction lien rights, not everyone that touches the project is a proper lienor.  Forget about timely serving a Notice to Owner or recording a claim of lien, if you are not a proper lienor, it does not matter if you properly perfected your lien rights.  If you are not a proper lienor, you have NO lien rights under the law!

 

 

 

 

 

 

 

Florida Statue s. 713.01(18) defines a lienor as follows:

 

(18) “Lienor” means a person who is:

(a) A contractor;

(b) A subcontractor;

(c) A sub-subcontractor;

(d) A laborer;

(e) A materialman who contracts with the owner, a contractor, a subcontractor, or a sub-subcontractor; or

(f) A professional lienor under s. 713.03;

and who has a lien or prospective lien upon real property under this part, and includes his or her successor in interest. No other person may have a lien under this part.

 

Let’s break this down.

 

A contractor is one other than a materialman (supplier) or laborer that enters into a contract with the owner to improve the owner’s property.  A contractor can be a design-builder.   Fla. Stat. s. 713.01(8).

 

A subcontractor is one other than a materialman (supplier) or laborer who is hired by the contractor.   This definition would include a labor company that furnishes skilled or unskilled labor.  Fla. Stat. s. 713.01(28).

 

A sub-subcontractor is one other than a materialman (supplier) or laborer who is hired by the subcontractor. Fla. Stat. s. 713.01(29). This definition would also include a labor company.  

 

A laborer is a person (excluding a professional) that enters into a contract to personally perform improvements to the property.   Fla. Stat. s. 713.01(16).  This definition would not include a labor company.  See V L Orlando Bldg. Corp. v. Skilled Services Corp., 769 So.2d 526 (Fla. 5th DCA 2000). 

 

A materialman (supplier) furnishes materials to an owner, contractor, subcontractor, or sub-subcontractor but does not perform labor.  Fla. Stat. s. 713.01(20).  This includes a supplier of rental equipment.  Fla. Stat. s. 713.01(13). 

 

A professional lienor is an architect, landscape architect, engineer, interior designer, or surveyor and mapper who has a direct contract with the owner or performs professional services that improves the real property.  Fla. Stat. s. 713.03.

 

You can also check out this chart for guidance.  Make sure to consult with counsel if you have questions regarding your lien rights. There is no reason not to.

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

RECOMMENCING CONSTRUCTION ON A PROJECT DUE TO A CESSATION OR ABANDONMENT

shutterstock_733809610There are instances where the owner of a construction project terminates its general contractor prior to the completion of the project.  There are instances where the owner suspends the work prior to the completion of the project, meaning there is a cessation in the construction.  And, there are instances where the project is simply abandoned.  I have been involved in all instances, and the owner’s reasons vary…from an owner claiming a termination for default, termination for convenience, or a suspension or abandonment due to the market or financial factors. Regardless of the owner’s reasoning, at some point—hopefully—the owner will want to resume or, more properly stated, recommence construction and complete the project. 

 

Based on the length of the cessation, when the owner finally recommences construction, oftentimes the right approach is for the owner to strictly comply with the recommencement procedure set forth in Florida Statute s. 713.07(4):

 

 

If construction ceases or the direct contract is terminated before completion and the owner desires to recommence construction, he or she [1] may pay all lienors in full or pro rata in accordance with s. 713.06(4) prior to recommencement in which event all liens for the recommenced construction shall take priority from such recommencement; or [2] the owner may record an affidavit in the clerk’s office stating his or her intention to recommence construction and that all lienors giving notice have been paid in full except those listed therein as not having been so paid in which event 30 days after such recording, the rights of any person acquiring any interest, lien, or encumbrance on said property or of any lienor on the recommenced construction shall be paramount to any lien on the prior construction unless such prior lienor records a claim of lien within said 30-day period. A copy of said affidavit shall be served on each lienor named therein. Before recommencing, the owner shall record and post a notice of commencement for the recommenced construction, as provided in s. 713.13.  [Per Florida Statute s. 713.13(5)(a), if an owner changes contractors, the owner must record either a new notice of commencement or notice of recommencement.]

 

Under this statute, when the owner wants to recommence construction, the owner has two options. 

 

First, the owner can pay all lienors in full or pro rata pursuant to Florida Statute s. 713.06(4), which lists the priority of payments to lienors.  I like the idea of getting final releases or a release through the date of payment with no carve-out (for retainage or otherwise).

 

Second, the owner can record an affidavit stating his/her intention to recommence construction and that all lienors giving notice (the contractor and those that served a notice to owner) have been paid in full except those specifically listed.   Thirty days after the affidavit is recorded, the rights of any person that acquires an interest in the property or liens the property is superior to any lien on the prior construction (before construction ceased) unless such lienor records a claim of lien within the 30-day window.   If the lienor already recorded a lien, the lienor would need to re-record the lien within this 30-day window to preserve its lien priority (although, importantly, the re-filing does not extend the one year period for the lienor to foreclose on its lien).   See Foy v. Mangum, 528 So.2d 1331 (Fla. 5th DCA 1988) (re-filing the lien ensures the lienor has priority over lienors performing recommenced work, but it does not delay the lienor’s requirement to timely foreclose the original recorded lien).  Any lienor identified in the affidavit would get served with a copy of the affidavit.

 

The owner also records a new notice of commencement / notice of recommencement for the recommenced work where any liens relating to the recommenced work would relate back, from a lien priority standpoint, to this notice of commencement.

 

A value to the owner complying with this procedure is that it can apply the remaining contract balance to the recommenced work and if the funds are expended the total amount the owner will be liable for liens recorded before the cessation could be reduced or eliminated (i.e., the proper payments defense). See Alton Towers, Inc. v. Coplan Pipe & Supply Co., 262 So.2d 671 (Fla. 1972) (if owner complies with the recommencement procedure, the owner’s liability is limited to original direct contract price, thus where completion costs exceeded defaulting contractor’s direct contract amount, supplier was not entitled to recover from owner).

 

If you are an owner or contractor involved in a ceased project, or a project where construction will be recommencing, it is in your interests to engage legal counsel familiar with the recommencement procedure.  It is important that you understand construction lien priority, how the recommencement can impact lien priority, and the owner’s potential liability if it properly complies with the recommencement procedure.

 

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.

 

TERMINATING THE NOTICE OF COMMENCEMENT (WITH A NOTICE OF TERMINATION)

shutterstock_259385300The notice of commencement is important for purposes of construction lien priority.   Stock Bldg. Supply of Florida, Inc. v. Soares Da Costa Const. Services, LLC, 76 So.3d 313, 317 (Fla. 3d DCA 2011) (“[A] notice of commencement serves to determine the priority of liens under the Construction Lien Law.”).   A lien relates back in time to the date the notice of commencement was recorded assuming the notice of commencement is still in effect when the lien is recorded (or an amended noticed of commencement is recorded).  Lien priority is very important and the reason why a contractor should always want to ensure there is an effective notice of commencement in place rather than an expired notice of commencement.

 

For the same reasons why a contractor wants to ensure there is an effective notice of commencement, there are times an owner wants to terminate a notice of commencement.  An owner may want to terminate the potential priority of a construction lien.  For instance, say the owner is refinancing or obtaining a construction loan in the midst of construction.  A lender will want to ensure its mortgage maintains first priority and certainly priority over a potential construction lien.  Otherwise, why would a lender finance the construction if it does not maintain first priority. It generally will not.  Thus, an owner needs to terminate the notice of commencement so that the closing occurs on the loan and the mortgage recorded before a new notice of commencement is recorded and construction continues.

 

Florida Statute s. 713.132 allows an owner to statutorily terminate the effectiveness of a notice of commencement by recording a notice of termination.  It is a statutory procedure that must be followed and it is important that an owner and contractor seek the assistance of counsel in following this procedure.  The statute contains in relevant part:

 

(3) An owner may not record a notice of termination except after completion of construction, or after construction ceases before completion and all lienors have been paid in full or pro rata in accordance with s. 713.06(4). If an owner or a contractor, by fraud or collusion, knowingly makes any fraudulent statement or affidavit in a notice of termination or any accompanying affidavit, the owner and the contractor, or either of them, as the case may be, is liable to any lienor who suffers damages as a result of the filing of the fraudulent notice of termination; and any such lienor has a right of action for damages occasioned thereby.

 

(4) A notice of termination is effective to terminate the notice of commencement at the later of 30 days after recording of the notice of termination or the date stated in the notice of termination as the date on which the notice of commencement is terminated, if the notice of termination has been served pursuant to paragraph (1)(f) on the contractor and on each lienor who has a direct contract with the owner or who has served a notice to owner.

 

If a notice of termination of a notice of commencement is recorded as a result of the cessation of construction, a new notice of commencement must be recorded before completion of the improvement may be recommenced.”  Stock Bldg. Supply of Florida, 76 So.3d at 317-18.    

 

From a lienor’s perspective, it is important that they understand that when a new notice of commencement is recorded, the lienor must re-serve any required notices to preserve lien or bond rights (such as a notice to owner or notice of intent to look to the contractor’s bond).  Stock Bldg. Supply of Florida, 76 So.3d at 318 (when owner recorded new notice of commencement, the project began anew and lienor was required to re-serve notices under Florida’s Construction Lien Law).

 

Please contact David Adelstein at dadelstein@gmail.com or (954) 361-4720 if you have questions or would like more information regarding this article. You can follow David Adelstein on Twitter @DavidAdelstein1.