UNRAVEL THE FACTS BEFORE ASSERTING FDUTPA AND TORTIOUS INTERFERENCE CLAIMS
Posted on 30 July, 2022
CMR Construction and Roofing, LLC v. UCMS, LLC, 2022 WL 3012298 (11th Cir. 2022) is an interesting opinion where a contractor asserted a Florida’s Deceptive and Unfair Trade Practices Act (known by its acronym “FDUTPA”) claim and tortious interference claims (with a contract and...
WHEN A REQUEST FOR EQUITABLE ADJUSTMENT SHOULD BE TREATED AS A CLAIM UNDER THE CONTRACT DISPUTES ACT
Posted on 24 July, 2022
In federal contracting, contractors are sometimes torn about submitting a request for equitable adjustment (known as an “REA” under 48 C.F.R. 252.243-7002) or submitting a formal claim under the Contract Disputes Act (41 U.S.C. s. 7103), the latter requiring a
Narrow Promissory Estoppel Exception to Create Insurance Coverage
Posted on 17 July, 2022
There is an affirmative claim known as promissory estoppel. (Whereas equitable estoppel is used an affirmative defense, promissory estoppel is used as an affirmative claim.)
To prove promissory estoppel, a plaintiff must plead and prove the following three elements: “(1) a representation as to a material fact that is contrary to...
THE RISK OF A FIXED PRICE CONTRACT IS THE MARKET
Posted on 10 July, 2022
When performing work on a fixed price or unit, there is risk that is being assumed on your end. One risk is the market. You are ultimately banking on the fact that the market is not going to make your fixed prices unprofitable. That’s not an...
NOTIFICATION TO INSURER AND THE “UNTIMELY NOTICE” FIGHT
Posted on 2 July, 2022
Notice, notice, notice. This should be your mindset when it comes to notifying your insurance carrier of a potential claim or loss. I get it. Notice means opening up a claim number and the potential increase in insurance premiums. Yet, untimely notice could mean fighting with your insurance...
About The Author

David Adelstein
Phone: (954) 361-4720
Email: Dadelstein@gmail.com
Pages
- About Me (David Adelstein)
- Bid Protests (Florida bid protests and Federal bid protests)
- Construction & Design Defects (and Florida Statutes Chapter 558)
- Construction Contracts
- Construction Liens
- Construction Safety, Workers Compensation Insurance, and Premise Liability Claims
- Delays, Acceleration, and Inefficiency (Lost Productivity)
- Insurance and Performance Bonds
- Payment Bonds Including Miller Act